24 Aug 2026production update▲ Good
Site works began on PGN's CNG Mother Station and NuEnergy's Early Production Facility for the 1 MMSCFD early gas sales. These are the facilities needed before first gas can be sold, which is currently targeted for Q1 CY2027.
Indonesian approval received for exploration extensions: 12 months each for Muralim and Muara Enim, and 18 months for Muara Enim II, all from 13 August 2026, to submit development plans. Resolves the pending extension applications, including Muara Enim II, and keeps all three PSCs alive.
June 2026 quarter: the US$88m contract was signed and the updated reservoir simulation found a more capital-efficient development concept. First gas sales are now targeted for Q1 CY2027, with early production facility construction due from August 2026.
Field Service Contract signed with PT BEL (the PT BJEL named earlier) worth about US$88m to drill and complete wells to a 24 MMSCFD plateau, repaid from future gas sales. This delivers the funding promised in January; work starts only after conditions precedent, including FEED and land access.
March 2026 quarter: first gas sales slipped to Q1 FY27 after weather delays to the early production facilities and PGN's CNG station. The EPCC signing is moved to follow the revised field plan. This pushes back the 1H 2026 target given earlier.
PT BJEL deadline to sign the Tanjung Enim EPCC contract extended to 30 June 2026 (or later if agreed), after a revised field plan using horizontal drilling that may need fewer wells. Resolves the 120-day lapse risk; development still described as fully funded.
ASX paused trading in NuEnergy shares pending a further announcement. The text gives no reason; it is a procedural notice tied to the price query the same day.
ASX queried a jump in the share price from $0.039 to an intraday $0.087 on 25 March 2026. The company said it knew of no undisclosed information and pointed to a positive analyst article and increased interest in energy stocks due to the Middle East conflict.
Half-year report to 31 Dec 2025. Restates the Nov 2025 entitlement offer of 138.3m shares at $0.025 and total shares of 1.919bn, citing proceeds of $3,427,364 (the earlier notice said $3.457m). Financial figures were not in the supplied text.
Amended December 2025 quarterly report adds the required expense summary, tenement table and a statement of no related-party payments. Compliance fix only; operational content is unchanged.
December 2025 quarter: all four early gas wells at Tanjung Enim completed, dewatering and flaring under way, first gas sales still expected in 1H FY26. Restates the PGN gas agreement (17 Dec) and the PT BJEL collaboration deal; no new results.
Collaboration agreement signed with PT Beijing Energy Linking, to be lead EPCC contractor and finance 100% of Tanjung Enim POD 1 development at a capped price, repaid from future gas sales. Terminates if the EPCC contract is not signed within 120 days. Addresses the funding gap for the 25 MMSCFD plan.
Binding gas sales agreement signed with PGN on 17 December 2025 for 5.59 BSCF of gas, running to the PSC end on 3 August 2039 or full delivery. First gas sales expected in the first half of 2026. Resolves the long-pending GSPA signing after the 2024 heads of agreement.
28 Nov 2025capital raising announcement● NeutralMajor
Entitlement offer closed with acceptances for 138.3m shares raising $3.457m, short of the $4.62m maximum. Shares on issue rise to 1.919bn. Note the text states a 2-for-29 ratio, conflicting with the 2-for-19 announced earlier. Globaltec now holds 45.41%.
Final early gas sales well TE-B01-003 drilled to 451 m (planned 473 m), intersecting five coal seams between 299 and 419 m with gas shows. Pump installed, dewatering about to start. All four wells in the programme are now drilled; the rig is being demobilised.
AGM presentation restating known facts: Tanjung Enim POD 1 (165 BCF, 25 MMSCFD plateau), 1 MMSCFD early gas sales, 9.7 TCF gas in place across four assets. Cites a share price of $0.025 and market cap of $41.55m at 10 Nov 2025. No new results.
Offer document released for the entitlement offer: 2 new shares for every 19 at $0.025 to raise about $4.62m, closing 21 November 2025. Restates terms already announced on 4 November; new shares expected to trade 1 December.
Sets out underwriting terms for the entitlement offer: Global Energy Resources underwrites 68.60% of the offer and charges no underwriting fee. Standard termination events apply. Board says shareholder approval is not needed.
4 Nov 2025capital raising announcement● NeutralMajor
Offer to raise up to $4.62m via a non-renounceable entitlement offer, 2 new shares for every 19 held at $0.025. Partially underwritten to $3.21m by major shareholder Global Energy Resources. Funds mainly for the early gas sales initiative. Follows the $5.995m raise at $0.02 in 2024.
September 2025 quarter: three early gas wells at Tanjung Enim completed and gas flaring started to test flow rates. MEMR gas allocation (1 MMSCFD to PGN) is noted, with GSPA signing to follow. Muralim and Muara Enim each applied for 12-month POD extensions, pending MEMR approval.
FY25 annual report: net loss $941k (FY24 $807k); cash $2.43m at 30 Jun 2025 versus $145.8k a year earlier, helped by the $5.995m entitlement offer at $0.02. Net assets $31.5m. Further funding is still flagged as a key risk.
Corporate governance statement and Appendix 4G for FY25, describing board practices against ASX principles. Administrative compliance document with no new operational or financial information.
MEMR approved the gas allocation for Tanjung Enim, authorising sale of 1 MMSCFD of coal bed methane to PGN. This resolves the long-pending approval; the GSPA can now be finalised. Three of four wells are dewatering, the fourth is drilling.
Spudded the fourth and final early gas sales well, TE-B01003, planned to about 473 m. The first three wells are dewatering with gas pressure building as expected.
TE-B06003 drilled to 420 m, intersecting five coal seams between 248 and 371 m with gas shows. Pump installed and dewatering under way; rig moving to the fourth well. Third of four early gas sales wells completed.
June 2025 quarter: two early gas wells done, third spudded, fourth being prepared. Muralim gas flared at 0.7–1.2 m³/hour and a gas discovery report was lodged, which may allow up to 3 years to submit a POD. GSPA still awaits MEMR approval.