History
A small explorer that began as New Holland Mining built a coal bed gas business in Indonesia, funded by repeated dilutive raisings, and by August 2026 was still awaiting its first gas sales.
2006-2007: From gold plant to a gas bid
The company, then called New Holland Mining, started 2006 with a 20% interest in a consortium recommended to win a 15-year contract to enhance a producing Indonesian gas project. A share purchase plan aimed at $1.1 million raised only $266,000. In May it gained an option to lift its stake to 75% and agreed to sell its Heathcote gold plant for $495,000. In October the Indonesian authority cancelled the tender, and the option lapsed with it.
In 2007 the board added oil and gas directors. A 1-for-1 entitlement offer at 0.4 cents, aimed at about $3.5 million, raised $910,897 at close. A shortfall offer later added 21,139,040 shares. Shareholders approved a 1-for-30 consolidation and a change of name to NuEnergy Capital, trading as NGY from 9 July 2007. Shares on issue stood at 57,629,158 by the October close.
2007-2011: The long road to Indon CBM
In November 2007 NuEnergy agreed to buy Indon CBM Limited, holder of coalbed methane (gas trapped in coal seams) rights in South Sumatra and the Tarakan Basin, for $19.2 million in shares. Due diligence slipped, and the Heathcote sale finally completed for $500,000. The record is then quiet until 2009, when convertible loans were raised, reaching $3.5 million, and a $5 million offer of 50 million shares at $0.10 was underwritten. Production Sharing Contracts for South Sumatra II and Rengat were signed on 30 November 2009. Paul Underwood was appointed CEO in February 2010 but resigned in September.
The deal was reshaped so vendors received 160 million shares. A prospectus offered $9 million of shares at 56 cents, later cut to 51 cents after the offer was not fully subscribed. Shares were suspended from 25 August 2010. The acquisition completed on 1 March 2011, with 40 million shares issued to vendors and $9 million raised, leaving 124,804,751 shares. A third PSC, Muara Enim 2, was signed in April.
2011-2014: Drilling in Sumatra and a search for partners
Christopher Newport became CEO in September 2011. The company entered East Africa through Tanzanian joint ventures, and later took a Malawi licence. In December 2011 it raised $6.9 million at 9 cents, far below the March 2011 price. Only about 47% of the rights issue was taken up, and underwriters covered the rest.
The first Muara Enim well in January 2012 found 38.2 metres of net coal. Core tests showed gas content that the company said beat earlier estimates. Independent certifier NSAI put Muara Enim and Muara Enim II at 7.8 trillion cubic feet of gas in place. A pilot well flared gas in October 2012, but no sales followed. RPS certified small contingent resources in February 2013.
Funding came at falling prices: a $6 million rights issue at 7.5 cents in 2013, with almost no take-up from ordinary holders, then a 3.5 cent issue that raised $1.87 million against up to $2.5 million sought. Newport resigned in January 2014. Talks with an Asian investor over Rengat did not lead to a deal in the record.
2014-2017: New Century takes control
In 2014 New Century Energy Resources, 60% owned by Bursa-listed Globaltec, agreed to invest. A $2.5 million placement at 3 cents was followed in December by a $10 million placement of 333.3 million shares. Kong Kok Keong became chairman, and Dr Ian Wang became CEO in September.
In 2015 NuEnergy bought Dart Energy (Indonesia) for US$1 million, adding Tanjung Enim, Muralim and Bontang-Bengalon. A $10 million entitlement offer at 2.5 cents closed in December, with underwriters taking the shortfall. Tanjung Enim cores showed 80-110 scf/ton of gas, while Rengat's first well hit seams of low economic significance. In 2017 RPS certified the first, tiny reserves, and a $20 million offer at 3.5 cents was launched. Shares on issue reached 1,480,955,497 by the end of 2017. Rengat was to be relinquished.
2018-2021: Setbacks and a first approval
In April 2018 the company submitted Indonesia's first coal bed methane plan of development (POD) for Tanjung Enim, after certification of about 165 billion cubic feet of reserves. Cash was falling, and the FY2018 loss was $12.5 million, including an $11.4 million Rengat write-down. Funding talks with EPI Energy ended in October 2018. A $38.5 million Saujana placement for 51% was signed in April 2019 and terminated in June when an extension fee went unpaid. Bontang Bengalon was terminated in August 2019, and the FY2019 loss was $17.0 million, leaving cash of $323,000.
The company took full ownership of Muralim in 2019. In 2020 it sold its Fosterville gold royalty to Metalla for $2 million cash plus Metalla shares. In June 2021 Tanjung Enim POD 1 was approved, covering about 33 square kilometres. Lim Beng Hong became CEO in December 2021.
2022-2026: Waiting for first gas
The record is quiet for 2022. Later beats show an environmental permit for POD 1 in September 2023 and a heads of agreement with PGN in June 2024. Cash was $146,000 at 30 June 2024. An entitlement offer at $0.02 raised about $5.99 million, bringing shares to 1,780.7 million. In March 2025 the company relinquished Muara Enim 2, and in May it began drilling four early gas sales wells at Tanjung Enim. Government gas allocation came in September, and a November offer at $0.025 raised about $3.4 million, bringing shares to 1.919 billion. Globaltec held 45.41%.
A binding gas sales agreement with PGN was signed on 17 December 2025. In January 2026 PT Beijing Energy Linking agreed to fund development, and on 30 June 2026 a Field Service Contract worth about US$88 million was signed, with work starting only after conditions precedent such as engineering design and land access. On 24 August 2026, extensions of 12 months for Muralim and Muara Enim, and 18 months for Muara Enim II, were approved. At that date no gas had yet been sold.
Written from the 115 story beats below (2006 to 24 Aug 2026), which come from the company's own announcements and filings.