Story beats
200 since 2006
Last event
21 Aug 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

14 Jan 2026drilling progress report▲ Good

The production packer passed a 2,500 psi pressure test and Victorian Government approval to test was received. Crews mobilise 14 January; plan is a four-day extended flow test then up to three weeks of shut-in, running mid-January to February 2026.

Value this in the calculator →Discuss in chat

25 Nov 2025drilling progress report▼ Bad

Test equipment arrived and was rigged up, but the upper swellable packer had not swelled enough to seal. About 10 more days are needed, so the crew is demobilised. Re-test is around 5 December, with testing the following week: another delay.

Value this in the calculator →Discuss in chat

10 Nov 2025drilling progress report▼ Bad

Wombat-5 production testing is delayed because equipment and staff are tied up elsewhere. First equipment is due 19 November, all onsite by 23 November, versus the earlier 10 November target. Lakes is confident of the third sand's contribution despite the stuck assembly.

Value this in the calculator →Discuss in chat

2 Oct 2025drilling result▲ GoodMajor

Wombat-5 drilled about 1,500 m horizontally through three high-gas sand intervals; the middle one is a new discovery of gas shows. A stuck assembly and suspected fault at 2,450 m stopped the completion short, leaving 614 m barefoot. Flow testing starts 10 November.

Value this in the calculator →Discuss in chat

1 Oct 2025drilling progress report● Neutral

Wellhead installed and pressure tested; drilling rig released at 1pm on day 61. Site is secured until the workover unit and gas flow test package arrive, scheduled for 10 November.

Value this in the calculator →Discuss in chat

30 Sept 2025drilling progress report▲ Good

The 4-1/2 inch completion is set at 2,438 m and the well secured for testing. Rig is to be released, with the workover unit and gas flow test scheduled for 10 November. The chair says flow testing is next to show commerciality.

Value this in the calculator →Discuss in chat

29 Sept 2025drilling progress report● Neutral

Day 59: the 4-1/2 inch swellable packer completion is being run, at 2,185 m, to be set at 2,440 m. Rig then demobilises; workover unit and flow test package are scheduled for 10 November, after the packers set.

Value this in the calculator →Discuss in chat

26 Sept 2025drilling progress report● Neutral

Day 55: the contractor is running in for a clean-up run to prepare the hole for fishing tools to recover the stuck bottom hole assembly. No new result.

Value this in the calculator →Discuss in chat

25 Sept 2025drilling progress report▼ Bad

While pulling out at total depth, tight hole jammed the drill pipe, leaving 44 m of bottom hole assembly stuck in the well. Management is assessing options; the board calls it a further delay and complication, adding to earlier Wombat-5 setbacks.

Value this in the calculator →Discuss in chat

24 Sept 2025drilling result▲ GoodMajor

Wombat-5 reached planned total depth of 3,052 m MD with 1,500 m of horizontal hole in the gas-saturated Strzelecki Formation. Final 200 m showed gas up to 35.82%, matching the best Wombat-3 sands. These are mud-gas shows, not a flow test.

Value this in the calculator →Discuss in chat

23 Sept 2025drilling progress report▲ Good

Day 53: Wombat-5 at 2,916 m MD, 1,364 m lateral, in the Wombat-3 sand package with gas shows up to 67.49%. Repeats the 22 September result with the chair's comment; mud-gas readings only, not a flow test.

Value this in the calculator →Discuss in chat

22 Sept 2025drilling result▲ GoodMajor

Wombat-5 drilled 522 m in 72 hours to 2,916 m MD and entered the Wombat-3 sand package near 2,825 m on prognosis. Gas shows reached 3,374 units (67.49%). Target depth is about 3,050 m. Mud-gas readings, not a flow test.

Value this in the calculator →Discuss in chat

19 Sept 2025drilling progress report● Neutral

Day 49: well path corrected back to 87.2° and 24 m drilled to 2,297 m MD. The motor assembly was pulled to be replaced with the rotary steerable tool. Gas shows up to 458 units.

Value this in the calculator →Discuss in chat

17 Sept 2025drilling progress report▲ Good

Day 48: a downhole motor assembly found no debris and drilled 73 m to 2,273 m MD (721 m lateral). Gas shows up to 1,565 units (31% gas). 777 m remains to the 3,050 m target.

Value this in the calculator →Discuss in chat

16 Sept 2025drilling progress report● Neutral

Re-lodgement of the 15 September update: 2,200 m, slow drilling from suspected reamer shoe debris, string being pulled. Same content, no new information.

Value this in the calculator →Discuss in chat

15 Sept 2025drilling progress report▼ Bad

Day 46: horizontal hole reached 2,200 m MD, 678 m lateral, but only 78 m in 72 hours. Slow drilling and torque, suspected dislodged reamer shoe debris, mean the string is being pulled for inspection. Gas shows up to 590 units.

Value this in the calculator →Discuss in chat

12 Sept 2025drilling result▲ GoodMajor

Horizontal drilling advanced 320 m in 24 hours to 1,899 m MD, passing the Wombat-2 location with gas shows up to 2,910 units (581,000 ppm) in good sands. Strong indication of gas-saturated reservoir, though a mud-gas reading and not a flow test.

Value this in the calculator →Discuss in chat

11 Sept 2025drilling progress report● Neutral

Re-lodgement of the 10 September update: horizontal section started, 60 m drilled, gas readings up to 81 units. Same content, no new information.

Value this in the calculator →Discuss in chat

10 Sept 2025drilling progress report▲ Good

Horizontal 6-1/8 inch section began 10 September; 60 m drilled by 9:30 am at about 20 m/hour. Gas readings reached 81 units (16,200 ppm). The chairman points to 250 Bcf at Wombat, which is a 2010 consultant estimate, not new.

Value this in the calculator →Discuss in chat

8 Sept 2025drilling result▲ GoodMajor

The 7 inch casing is set and cemented at 1,549 m, about 35 m into the Strzelecki, securing the well in the reservoir. Gas shows rose to 35 units (7,000 ppm). Target total depth remains 3,050 m.

Value this in the calculator →Discuss in chat

5 Sept 2025drilling result▲ GoodMajor

Wombat-5 entered the Strzelecki Formation at 1,410 m, about 4 m higher than prognosis, with first gas shows up to 12 units (2,400 ppm). Lakes says these are consistent with Wombat-2 and -3. Early indication only, not a flow test.

Value this in the calculator →Discuss in chat

4 Sept 2025drilling progress report● Neutral

Day 33: assembly running back to the bottom at 1,394 m after fluid volume was restored. Strzelecki top expected in about 20 m and the 7 inch casing point in about 150 m.

Value this in the calculator →Discuss in chat

3 Sept 2025drilling progress report● Neutral

Re-lodgement of the 2 September update: assembly paused at the casing shoe at 1,394 m while fluid volumes are restored. Same content, no new information.

Value this in the calculator →Discuss in chat

2 Sept 2025drilling progress report● Neutral

Day 32: no depth progress, stuck at 1,394 m. New assembly paused at the casing shoe while surface fluid volumes are restored. Strzelecki top still expected within 20 m TVD; 7 inch casing point about 1,530 m.

Value this in the calculator →Discuss in chat

1 Sept 2025drilling progress report● Neutral

Day 31: well at 1,394 m, 53° inclination, after changing the motor and bit for slow drilling. A human-error mechanical failure while pulling the string delayed repairs. The Strzelecki top is expected within about 20 m.

Value this in the calculator →Discuss in chat

28 Aug 2025drilling progress report▼ Bad

Day 26: only 14 m drilled to 1,256 m. Clay packed around the bit and stabiliser slowed drilling, so the assembly was pulled and a new one is being run in. A minor setback.

Value this in the calculator →Discuss in chat