Stockle - the stock oracle

Comet Ridge Ltd

ASX:COI
A$0.077Close 7 Oct 2026 · delayed

Past year: ▼ 41%(7.70c – 16.5c AUD)

Market cap
A$129m
Shares on issue
1.68bn
In-ground value
A$1.33bn
Risked multiple
5.61×
Story beats
212 since 2006
Last event
24 Aug 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

5 Mar 2019drilling progress report● Neutral

Vintage's version of the Koburra seismic completion: 336 km acquired 2 March, with processing alongside 619 km of older seismic. Rig 932 is due to leave Moomba by end of March, delayed by rain. Repeats Comet Ridge's announcement.

Value this in the calculator →Discuss in chat

5 Mar 2019drilling progress report● Neutral

The Koburra 2D seismic survey finished on 2 March at 336 km, slightly above the planned 325 km, with good-quality raw images. Albany 2 pad work starts next week; Rig 932 move is about two to three weeks late because of rain. Interpretation is due in the June quarter.

Value this in the calculator →Discuss in chat

30 Jan 2019contract award▲ GoodMajor

Per Vintage, Comet Ridge as operator signed Ensign Rig 932 for Albany 2 and Albany 1 sidetrack: two firm wells plus two contingent wells, starting March 2019 after the wet season. This resolves the open rig search and commits both parties to Stage 2.

Discuss in chat

23 Jan 2019investor presentation● Neutral

Corporate update presentation dated 23 January 2019. Capital structure shows 727.9m shares, $0.32 share price, $233m market cap and $24.9m cash at 30 September 2018. Remainder of text is truncated; it appears to restate known Mahalo reserves (172 PJ 2P).

Discuss in chat

22 Jan 2019auditor change● Neutral

COI is replacing Pitcher Partners, its auditor for over 10 years, with PricewaterhouseCoopers after a competitive tender. Pitcher Partners resigned with ASIC consent. The appointment needs shareholder ratification at the next AGM. The company ties the change to moving from explorer to developer.

Discuss in chat

9 Jan 2019drilling result▲ GoodMajor

Sirius Road 2 was drilled to 1,990 m with 1,437 m in the Castor seam (96% in seam), and the rig demobilised, completing the five-well Mahalo drilling. Memooloo 2 testing meets expectations; Struan 2 and Sirius Road 1 testing starts shortly.

Value this in the calculator →Discuss in chat

2 Jan 2019drilling scheduled● Neutral

A 325 km 2D seismic program across the Galilee permits began 30 December, run by Synterra. It should finish by early February, with data ready late in the March 2019 quarter. It aims to define drill targets beyond Albany 1 and 2.

Value this in the calculator →Discuss in chat

24 Dec 2018drilling spud● Neutral

Sirius Road 2 spudded 21 December as a single lateral targeting the 3.3 m Castor seam, not both seams. The thin Pollux seen in Sirius Road 1 is not considered representative, so Pollux testing is deferred to a future well.

Value this in the calculator →Discuss in chat

19 Dec 2018drilling result● Neutral

Sirius Road 1 vertical well reached 506 m with 6.9 m net coal. The Castor seam was 3.3 m, as expected, but the Pollux was only 0.9 m, thinner than predicted. Sirius Road 2 is due to spud 21 December.

Value this in the calculator →Discuss in chat

18 Dec 2018well test result▲ Good

Memooloo 2 production testing, running since 23 November, shows rising water rates with minimal pressure draw down, which the company calls encouraging. No gas rate is given. Testing continues and lab analysis is under way.

Discuss in chat

10 Dec 2018drilling result▲ GoodMajor

Struan 3, the first dual lateral well at Mahalo, was drilled: 822 m in the Pollux (88% in seam) and 1,512 m in the Castor (95%), over 2.3 km combined. The MD expects this to be a main production well design. Rig moves to Sirius Road 1.

Value this in the calculator →Discuss in chat

26 Nov 2018farm in farm out completion● NeutralMajor

Vintage says documents transferring a 15% interest in the Galilee Deeps joint venture from COI are fully executed, completing Stage 1. Vintage books 23 PJ 2C for Albany. COI is now 85% with Vintage 15%, ahead of Stage 2.

Value this in the calculator →Discuss in chat

21 Nov 2018farm in farm out agreement▲ GoodMajor

Vintage says Stage 2 of its Galilee farm-in starts December: a $3.5m gross 300-420 km 2D seismic survey. Vintage funds 50% of a $10m program to earn another 15% (30% total, leaving COI 70%). Long-lead items for Albany 2 and Albany 1 re-entry are being bought.

Value this in the calculator →Discuss in chat

21 Nov 2018investor presentation● Neutral

Managing Director's AGM presentation. It restates known highlights: 172 PJ net 2P, Mira 6 at 1.4 mmcf/d, the Vintage farm-out, Albany 1 gas flow and the $17.4m placement. The Mahalo program's third well is being drilled. Text is truncated.

Discuss in chat

20 Nov 2018drilling progress report● Neutral

Struan 2 reached 510 m and Struan 3, the first dual lateral well, spudded 17 November. Memooloo 2 completion is run and being readied for production testing. Sirius Road 1 and 2 follow.

Value this in the calculator →Discuss in chat

12 Nov 2018drilling spud● Neutral

Struan 2 vertical well spudded 9 November, second of the five-well Mahalo program, with planned depth about 550 m and full coring. It will be intersected by Struan 3, the program's first dual lateral well.

Value this in the calculator →Discuss in chat

5 Nov 2018drilling result▲ Good

Memooloo 2 reached 300 m with 7.2 m net coal, good to excellent permeability on short wireline tests, and results in line with expectations. About two months of production testing follows once pump is installed; rig moves to Struan 2.

Value this in the calculator →Discuss in chat

29 Oct 2018drilling spud▲ GoodMajor

Memooloo 2 vertical well spudded 28 October 2018, first of the 5-well Mahalo program, with target depth about 290 m. It will be cored to confirm gas content in the shallowest part of the block, then production tested for about two months.

Value this in the calculator →Discuss in chat

19 Oct 2018annual report● Neutral

Annual report for the year to 30 June 2018, now including the audited remuneration report. It repeats the earlier statutory report's highlights, including 2P reserves of 172 PJ and Mira 6/2 at 1.4 mmscf/d. Financials are not visible in the text provided.

Discuss in chat

19 Oct 2018other● Neutral

Appendix 4G corporate governance checklist lodged with the annual report. Administrative only, with no new business information.

Discuss in chat

19 Oct 2018other● Neutral

Annual corporate governance statement dated 19 September 2018. It says practices substantially follow ASX recommendations, with exceptions such as no formal agreements with non-executive directors. Administrative only.

Discuss in chat

12 Oct 2018drilling scheduled▲ Good

Mahalo well pad construction starts within days, with Rig 20 mobilising the week of 22 October and spud expected the week of 29 October 2018. First wells are Memooloo 2, Struan 2 and Struan 3, the first dual lateral well.

Value this in the calculator →Discuss in chat

21 Sept 2018capital raising announcement● Neutral

Routine paperwork: COI issued 51,225,437 placement shares at $0.34, completing the $17.4m placement announced on 14 September. The notice confirms compliance with disclosure rules.

Discuss in chat

21 Sept 2018annual report● Neutral

Statutory annual report for the year to 30 June 2018, calling it an outstanding year. It repeats known highlights: 2P reserves up 473% to 172 PJ, Mira 6/2 at 1.4 mmscf/d, the Vintage farm-in and Albany 1's 230,000 scf/d. Financials are not visible in the text provided.

Discuss in chat

14 Sept 2018capital raising announcement▲ GoodMajor

COI raised $17.4m through an institutional placement at $0.34 per share, about 51.2m shares (7.6% of capital), backed by new cornerstone institutions. Funds go to the Mahalo 2018 program, Albany 1 completion, Albany 2 and seismic, plus working capital.

What it means for a shareholder

51.2m new shares at about A$0.3398 to raise about A$17.4m. That's 7.0% dilution: every existing holder's slice gets 7.0% smaller. If you held A$1,000 of shares (2,943 at the issue price), your slice goes from 0.000435% to 0.000404% of the company. To keep it you'd need 223 more shares - about A$76 at the issue price.

Create a free account to see this worked out for your own holding.

Discuss in chat

13 Sept 2018other● Neutral

ASX paused trading in COI pending a further announcement. No reason is given in the notice; the next announcement shows it preceded a capital raising.

Discuss in chat

6 Sept 2018investor presentation● Neutral

MD presentation at the ASX Sydney conference. It shows 676.7m shares, $11.5m cash at 30 June 2018, a $0.36 share price and $243.6m market cap. Text is truncated; it appears to restate known Mahalo and Galilee material.

Discuss in chat

4 Sept 2018material agreement● NeutralMajor

Stanwell's Mahalo gas option deadline for a final investment decision moves 11 months, from 20 October 2018 to 30 September 2019. The parties will negotiate a new market-priced gas sales agreement by 15 July 2019, with Stanwell's volume still up to 40 PJ.

Discuss in chat

15 Aug 2018contract award▲ GoodMajor

Comet Ridge signed Silver City Drilling's Rig 20, the rig that drilled Mira 6 in 2017, for a 5-well Mahalo program. Spud is expected mid to late September 2018, finishing November/December. COI says it is fully funded for its share.

Discuss in chat

19 July 2018investor presentation● Neutral

Noosa Mining Conference presentation. It shows 676.7m shares, 4.4m performance rights, cash of $13.4m at 31 March 2018, a $0.385 share price on 17 July and a $260.5m market cap. Otherwise it restates known Mahalo and Galilee facts.

Discuss in chat