17 July 2018investor presentation● Neutral

MD technical presentation to the Queensland explorers' association on the Galilee Basin, noting the 230,000 scf/d Albany 1 flow in June 2018. It repeats known information; no new announcements are visible in the text provided.

Discuss in chat

28 June 2018flow test result▲ GoodMajor

Albany 1 flowed a stable 230,000 scf/d from a 13 m interval (2,582-2,595 m) of the Lake Galilee Sandstone, which COI calls the Galilee Basin's best gas flow to date. The drillstring stuck and drilling is suspended with about 100 m of sandstone undrilled; a larger rig is sought and an Albany 2 step-out planned.

Discuss in chat

26 June 2018production update▲ GoodMajor

Mira 6/2 gas rate has passed 1.4 million scf/d with only 30 bwpd of water, above the 1.2-1.3 million COI had extrapolated in April. The Mahalo JV is finalising a multi-well program, including a long dual horizontal well, planned to spud in September.

Discuss in chat

25 June 2018drilling progress report▼ Bad

Albany 1 is at 2,581 m, in the top of the Lake Galilee Sandstone, after a week of delays from a hammer bit failure and a nitrogen booster failure on 24 June. Drilling should resume with about 200 m left.

Value this in the calculator →Discuss in chat

18 June 2018drilling progress report● Neutral

Albany 1 casing was cemented successfully at 2,470 m, just above the target sandstone. Nitrogen equipment is being pressure tested, with drilling of the Lake Galilee Sandstone section due to start later that day. TD is about 2,775 m.

Value this in the calculator →Discuss in chat

13 June 2018investor presentation● Neutral

COI presented at Credit Suisse's energy conference in Sydney, its first invitation. The MD says the company is now a developer/producer rather than just an explorer, citing Mahalo. Presentation largely restates known material.

Discuss in chat

12 June 2018drilling progress report● Neutral

Albany 1 reached 2,470 m, the base of the Jericho Formation just above the target Lake Galilee Sandstone. 7 inch casing is about to be run and cemented, then the final section will be drilled with nitrogen. TD is still about 2,775 m.

Value this in the calculator →Discuss in chat

8 June 2018production update▲ Good

Mira 6/2 gas rate was 1.193 million scf/d on 5 June, up from 1.0 million, after flare facility adjustments cut back pressure (about 20% gain). This approaches the 1.2-1.3 million limit COI extrapolated in April; further flowline work may lift it more.

Discuss in chat

4 June 2018drilling progress report● Neutral

Albany 1 is at 1,888 m, drilling ahead in 8-1/2 inch hole part-way through the Jericho Formation, up from 1,336 m. Total depth is still about 2,775 m. No reservoir results yet.

Value this in the calculator →Discuss in chat

1 June 2018remuneration report● Neutral

Commercial Director Chris Pieters gets five $50,000 success payments tied to gas offtake deals, Mahalo and Galilee FIDs and a Galilee Shallows farmout, plus a $45,000 bonus for the Mira horizontal well and reserves upgrade. Base rate is unchanged. Document text is dated 2016 but sits in June 2018.

Discuss in chat

28 May 2018drilling progress report● Neutral

Albany 1 is at 1,336 m, drilling ahead in 8-1/2 inch hole through the Jochmus Formation after setting surface casing at 747 m. Total depth is still prognosed at about 2,775 m. No reservoir results yet.

Value this in the calculator →Discuss in chat

21 May 2018drilling spud▲ GoodMajor

Albany 1 spudded on 19 May 2018 and was at 711 m by 21 May. It is programmed to reach about 2,775 m in roughly 25 days. It is 220 m from Carmichael 1 and is the first well in Vintage's farm-in.

Value this in the calculator →Discuss in chat

14 May 2018drilling progress report● Neutral

Rig 101 has been released from its other job and is moving to Albany 1, with first loads arriving that afternoon. Spud is expected late this week, possibly over the weekend. No well results yet.

Value this in the calculator →Discuss in chat

8 May 2018director officer appointment● Neutral

Peter Harding-Smith becomes full-time CFO, succeeding Don Langdon, who retires after nine years part-time and stays part-time briefly for the handover. COI says the move reflects increased activity after the Mahalo upgrade and the Albany 1 drilling.

Discuss in chat

7 May 2018drilling scheduled● Neutral

Rig 101 is about to move to Albany 1, with spud expected next week. The well targets roughly 40 m of interpreted net pay in about 140 m of sandstone, drilled with nitrogen. Certified contingent resource is 56/153/417 PJ (1C/2C/3C).

Value this in the calculator →Discuss in chat

24 Apr 2018drilling scheduled● Neutral

Albany 1 contracts, including Easternwell Rig 101, are in place and the drill site is built, but spud has slipped to mid-May until the rig finishes another job. Earlier target was mid-March to early April. Vintage earns 15% by funding the first well.

Value this in the calculator →Discuss in chat

28 Mar 2018production update▲ Good

Mira 6/2 gas flow passed 1 million scf/d (about 1 TJ/d) and is still rising, up from 840,000 earlier in March. Water rates are already falling from their peak, consistent with the earlier Mahalo pilot.

Discuss in chat

13 Mar 2018investor presentation● Neutral

March investor presentation repeats known facts: 2P 172 PJ and 3P 374 PJ at Mahalo, with a final investment decision targeted for late calendar 2018. It shows 673.5m shares, 7.0m performance rights and cash of $13.8m at 31 December 2017.

Discuss in chat

12 Mar 2018production update▲ Good

Mira 6/2 gas flow passed 840,000 scf/d and is still rising toward 1,000,000 scf/d, continuing the climb from 625,000 in February. Management says it supports the new reserves upgrade and expects future development to use longer horizontal wells.

Discuss in chat

12 Mar 2018half year report● Neutral

Half-year accounts to 31 December 2017 show a loss of $1.777m (prior year $2.033m). The report restates the 5 March reserves upgrade and the Mahalo program being completed on time and on budget. Cash balance is not visible in the text provided.

Discuss in chat

6 Mar 2018resource reserve update▲ GoodMajor

Independent certifier MHA lifts COI's net Mahalo 2P reserves 473% from 30 PJ to 172 PJ and 3P 71% to 374 PJ, with a maiden 1P of 18 PJ. The 334 PJ gross trigger is passed, so COI can cash call Santos for $1.348m of 2017 costs.

Value this in the calculator →Discuss in chat

1 Mar 2018farm in farm out completion▲ GoodMajor

All conditions are met for Vintage Energy's farm-in to the Galilee 'Deeps' (sandstone below the coals); the joint venture and co-ordination agreements are finalised. Vintage's roughly $8.5m earns up to 30%, and Albany 1 is expected to spud next month. COI keeps 100% of the coal 'Shallows'.

Value this in the calculator →Discuss in chat

26 Feb 2018production update▲ GoodMajor

Mira 6/2 gas flow passed 625,000 scf/d, now above the 2016 Mahalo pilot's output, which had 361 m in coal against Mira's 924 m. Management calls Mira the best performing pilot in the block and expects further increases. The reserves upgrade is still pending.

Discuss in chat

23 Feb 2018material agreement▲ Good

Santos has re-appointed Comet Ridge under a second agency agreement to run the Mahalo 2018 exploration work program and budget, after the 2017 program was completed. Comet expects the budget to be formally approved next week. It continues the 2017 arrangement.

Discuss in chat

7 Feb 2018production update▲ Good

Mira 6/2 gas flow passed 390,000 scf/d with the upward trend continuing. All technical data is now with the independent certifier for an updated Mahalo 2P and 3P reserves assessment, due in the first quarter. This follows the 200,000 scf/d mark in January.

Discuss in chat

15 Jan 2018production update▲ Good

Mira 6/2 gas flow passed 200,000 scf/d on a rising trend, rising faster than the shorter horizontal at the Mahalo pilot. Bottomhole pressure remains relatively high, which management says indicates room for more gas as pressure falls.

Discuss in chat

19 Dec 2017production update▲ Good

The Mira 6/2 combination began producing gas two days after start-up and is now the field's peak water producer. Three Mira pilot wells are producing gas, with rates rising steadily. Pump speed will be raised over Christmas; another update is due in early January.

Discuss in chat

11 Dec 2017production update▲ Good

The Mira 6 horizontal well, with about 920 m in coal, came on-line on 10 December via the Mira 2 pump, producing water as planned. Rain delayed the start by two weeks. Mira 5 and Mira 3 are already producing gas.

Discuss in chat

1 Dec 2017capital raising announcement▲ GoodMajor

The Share Purchase Plan drew over $4.4m of applications against a $3m target, and was scaled back to about $3.1m at $0.235. Together with the $10m placement, this completes the November raising; new shares are allotted 1 December.

Discuss in chat

22 Nov 2017drilling progress report▲ Good

The Mira 2 pump was installed on 21 November and the 2017 field work is finished. Management expects the three-step program to cost under the $5m approved JV budget. Mira 2 is to be reconnected by APLNG; no new gas results yet.

Value this in the calculator →Discuss in chat