21 Oct 2025contract award▲ GoodMajor
Signed Orica for blasting (2025-2028) and THOR S.A. for a 24-month blasthole drilling contract covering about 3.2Mt. Casposo plant refurbishment and commissioning is reported complete (per Austral Gold), ahead of CEL ore, with blasting due by early November.
30 Sept 2025regulatory community update▲ GoodMajor
The EIA amendment for hauling Hualilan ore to Casposo was approved, the last government approval needed. Hualilan is now fully permitted for toll milling, resolving the road-transport EIA thread; mining and drill-and-blast contracts are expected within weeks.
Half-year to 30 June 2025 shows a profit of A$7.26m, driven by an A$11.7m hyperinflation accounting gain (A$53.9m profit a year earlier). It repeats the June placement of about A$37.5m at 8 cents and the US$2m facility draw.
S&P Dow Jones index rebalance list; Challenger Gold is added to the All Ordinaries index from 22 September 2025. Index notice only, no company announcement or new business information.
Argentina's national security ministry granted the blasting permit for Hualilan toll milling. The company calls it the final permit needed to start drill and blast, clearing one of the remaining approvals ahead of mining.
Casposo plant refurbishment is reported on track, with commissioning targeted for August 2025 and processing of CEL ore in November 2025. That is later than the earlier second-half 2025 target but within it; primary crusher and SAG engine repairs are complete.
Elsztain Group raises its Tranche 2 commitment from about A$4.5m to about A$7.5m (93.5m shares plus free options), lifting the placement to A$37.5m. The extra A$3m goes to working capital; shareholder approval is still needed.
Carolina Zang, an Argentine securities lawyer, joins as Non-Executive Director. She takes the place of Saul Zang, who was foreshadowed for the board in January 2025 but never appointed.
Heap-leach column tests on Hualilan's low-grade halo gave average gold recovery of 75% (up to 85%) at half-inch crush. This could let material treated as waste in the 2023 Scoping Study be processed; full stand-alone PFS metallurgy due early Q4 2025.
July 2025 corporate presentation titled 'The Next High-Grade Gold Producer'. The excerpt shows only disclaimers and cautionary statements; no new information is visible in the text provided.
Toll-milling pre-feasibility study done, completing the thread open since the Scoping Study: 76.6koz payable gold from 465kt at 6.2 g/t, US$8.9m upfront. At US$2,500/oz, NPV5 US$50.5m; at US$3,300/oz, US$82.2m. Recoveries assumed 84.4%.
Full technical summary report behind the toll-milling pre-feasibility study, prepared by Fuse Advisors. The excerpt shows only the table of contents; the findings repeat the study announced the same day.
Shares suspended at the company's request, following a trading halt granted 2 June, pending an announcement about capital raising. Requested to last until 5 June or until the announcement is released.
4 June 2025capital raising announcement▲ GoodMajor
Raises about A$34.5m at A$0.08 per share (431m shares, 16.7% below last close), with one free option per two shares at A$0.12. A$30m from L1 and Helikon; A$4.5m from Elsztain Group needs shareholder approval. Funds toll milling, Hualilan drilling and studies.
Replies to an ASX query after the share price rose from A$0.085 to an intraday A$0.096 on heavy volume. Says it knows of no unannounced information explaining the trading and believes it complies with continuous disclosure rules.
Signs an Investment Protection Agreement with Ecuador's government for the 100%-owned El Guayabo project: regulatory stability and international arbitration (London, ICC), covering US$75m of investment through 2027, for an initial 8 years, renewable. Supports the planned Ecuador monetisation.
Appendix 4G, the checklist pointing to the corporate governance statement, lodged with the annual report. Administrative filing with no substance beyond that.
Annual report for year ended 31 December 2024 released, with sustainability report, financial statements, and auditor's report. The excerpt shown contains no financial figures; largely a re-release of the earlier statutory accounts in fuller form.
Corporate governance statement for FY2024, approved 30 April 2025. Says the board does not have separate committees given its size; one recommendation is only partially followed. Compliance document with no new business information.
Company says the Casposo plant refurbishment is on track, backed by Austral's update and a second independent inspection by the same engineers as the December audit. Inspection found enough time to meet the second-half 2025 commissioning target; solid-liquid separation, flagged as a key risk, appears adequate.
Ecuador resource doubles from 4.5Moz to 9.1Moz AuEq (570Mt at 0.50 g/t), including a maiden 4.4Moz at Colorado V; 6.9Moz is attributable to CEL. Exploration there is declared complete, with TSX spin-off, sale or farm-in under consideration.
Full-year statutory accounts to 31 December 2024 lodged, listing Elsztain as Non-Executive Chairman from 4 March 2025 and Rotondo as Executive Vice Chairman. Excerpt shows directors' details only; no financial figures visible in the text provided.
Draws the first US$2m (~A$3.2m) of a US$20m toll-milling project finance facility. Unsecured, 8.5% if repaid before 7 Dec 2025 (12.75% after), repayable from first toll-milling cash flow; 4% fee. Funds mining preparation and working capital; later tranches need due diligence.
4 Mar 2025director officer appointment● NeutralMajor
Eduardo Elsztain becomes Non-Executive Chairman with immediate effect, as foreshadowed in January after his 12.7% placement. Sergio Rotondo moves to Executive Vice Chairman and stays on the board.
Appoints mining engineer Bira De Oliveira, with 35+ years' experience, as General Manager Operations at Hualilan to lead toll-milling operational readiness. A release line says 450,000t annually, but the agreement covers 150,000t a year (450,000t over three years).
The company retracted the production target information on pages 5 to 7 of its 11 February 2025 release, saying it lacked a reasonable basis to disclose it. Investors were told to disregard that information, and a revised announcement was attached.
Update on toll-milling readiness: final pit designs and schedules done, with the first 150,000t averaging 8.7 g/t gold and plant refurbishment started. Pre-feasibility study due March 2025. The production-style figures were later retracted by the company (see 20 February).