Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

25 June 2018material agreement▲ GoodMajor

Central signed a gas sales agreement to supply Incitec Pivot at least 20 TJ/d from Palm Valley and Mereenie, from NGP start (expected December 2018) to 31 December 2019. A 50:50 Queensland ATP 2031 joint venture was also agreed, with IPL funding up to $20m of drilling.

Discuss in chat

25 June 2018drilling progress report▼ Bad

West Mereenie-26 reached the target Lower Stairway 2 sandstone, with 425 m of horizontal section drilled. Only minor gas shows were seen, and there is evidence of fractures plugged with minerals, a cautious early sign for the Stairway play.

Value this in the calculator →Discuss in chat

12 June 2018investor presentation● Neutral

Credit Suisse conference presentation. Notes the gas sales ramp is now in two stages because of external pipeline lateral upgrades. Initial firm capacity is 44 TJ/d at Mereenie and 15 TJ/d at Palm Valley, and Central's cost is $15m. Otherwise repeats known plans.

Discuss in chat

7 June 2018drilling progress report● Neutral

West Mereenie-26 has surface casing set at 544.8 m and was drilling at 916 m measured depth, with 518 m to go before reaching the target Stairway Sandstone. No results yet.

Value this in the calculator →Discuss in chat

6 June 2018director officer appointment● NeutralMajor

Central promotes Mike Herrington to President – Operations and Chief Development Officer, appoints Ross Evans (ex-Lattice Energy) as Chief Operations Officer and Robin Polson as Chief Commercial Officer. MD Richard Cottee's tenure is to be extended two years, with details still to come.

Discuss in chat

23 May 2018drilling spud● NeutralMajor

West Mereenie-26 spudded on the night of 22 May, about a month later than the 20-21 April expected. It targets Stairway gas, with 36 days planned to reach 2,915 m measured depth including up to 1,481 m horizontal. Central operates with 50%.

Value this in the calculator →Discuss in chat

4 May 2018other● Neutral

Notice of a webinar on 9 May 2018 where the Managing Director will discuss the March quarter report. No new information.

Discuss in chat

30 Apr 2018director officer appointment● NeutralMajor

Chair Robert Hubbard retires on 14 May 2018, and the board unanimously backs director Martin Kriewaldt as the new Chairman. This resolves the open chair succession thread; Hubbard had flagged he would step down around the end of the financial year.

Discuss in chat

30 Apr 2018other● Neutral

Annual corporate governance statement describing board practices and committees. It carries no new events or figures of note visible here; routine compliance disclosure.

Discuss in chat

11 Apr 2018production update▲ GoodMajor

Board approved reopening Palm Valley without waiting for Palm Valley-13, after a review found existing wells can produce 15 TJ/d for two years. Central targets 15-20 TJ/d there and total sales of 54 TJ/d by 1 December, up from 17 TJ/d.

Discuss in chat

11 Apr 2018drilling scheduled● Neutral

West Mereenie-26 is expected to spud 20-21 April, drilling for 35-40 days; the $12m plant upgrade ($6m Central share) is on budget and time. Central also negotiated a further $5m extension of its Macquarie debt facility.

Value this in the calculator →Discuss in chat

29 Mar 2018regulatory community update▲ GoodMajor

The ACCC's final determination authorises Mereenie joint marketing for three years, resolving the open ACCC thread. Central says this lets more Mereenie gas be developed sooner.

Discuss in chat

29 Mar 2018regulatory community update▲ Good

The ACCC's own release of its final determination authorising Central and Macquarie to jointly market Mereenie gas for three years. Duplicates Central's own announcement of the same day.

Discuss in chat

22 Mar 2018drilling scheduled● Neutral

Ensign Rig 932 is moving to Mereenie, with the first equipment on site. West Mereenie-26, the first well of a now three-well programme, is expected to start in April 2018, after earlier hopes of March.

Value this in the calculator →Discuss in chat

21 Mar 2018contract award▲ Good

Central awarded contracts for the new Mereenie field compressor (delivery early October) and restaging of two existing compressors (mid to late November). With separators already delivered, key long-lead items are placed for the 1 December 2018 target.

Discuss in chat

21 Mar 2018investor presentation● Neutral

Roadshow presentation repeating known plans: Mereenie upgrade, three-well programme (current 2P 125.9 PJ, potential net 227-415.5 PJ) and the Queensland permit. No new announcements.

Discuss in chat

13 Mar 2018investor presentation● Neutral

Rock Me Amadeus conference presentation mostly repeating known plans, and adding details on the new Queensland permit (ATPA 2031): 77 km2, 377 PJ gas in place with 150-180 PJ potentially recoverable, and a roughly $20m, 9-well programme.

Discuss in chat

12 Mar 2018joint venture update▲ GoodMajor

The Mereenie joint venture approved drilling West Mereenie-26 and an immediate $12m plant upgrade, lifting capacity from 25 to 63 TJ/d (58 TJ/d sold). Only one Stairway well will be drilled, with the second well's funds redirected to the larger upgrade.

Discuss in chat

2 Mar 2018regulatory community update▲ GoodMajor

Central confirms the ACCC's draft approval and interim authorisation of Mereenie joint marketing, ending the long wait. It will seek joint venture approval quickly for the West Mereenie-26 well and a plant upgrade to about 63 TJ/d gross.

Discuss in chat

2 Mar 2018regulatory community update▲ Good

The ACCC released a draft decision to authorise Central and Macquarie to jointly market Mereenie gas for three years, and granted interim authorisation now, so negotiations can start. Final decision is pending; this is the ACCC's own release of the news Central announced.

Discuss in chat

1 Mar 2018joint venture update● Neutral

Incitec Pivot confirms Central is preferred bidder for the Queensland acreage. It has an exclusivity MoU and may provide up to $20m for appraisal; IPL says gas could flow in 2022 if reserves are proven, and says the economics remain challenging.

Discuss in chat

1 Mar 2018asset acquisition disposition▲ GoodMajor

Central was named preferred bidder for a Queensland Government gas permit (PLR201718-1-1), partnering with Incitec Pivot. They are negotiating a 50:50 joint venture, with IPL providing up to $20m for exploration and appraisal. Not yet final.

Discuss in chat

26 Feb 2018half year report▲ Good

Half-year to 31 December 2017: operating revenue rose 39.8% to $17.7m and gas sales volumes rose 50.6%, reflecting the EDL contract. Producing-asset EBITDAX rose 81.7% to $8.7m. Cash was $28.6m. An ACCC decision on the Mereenie joint marketing was expected later in February.

Discuss in chat

7 Feb 2018investor presentation● Neutral

Notice of a quarterly webinar on 8 February 2018 about the December quarter report, with the presentation attached. Administrative; the visible text carries no new figures or events.

Discuss in chat

2 Feb 2018contract award● NeutralMajor

Central contracted Ensign's mothballed Rig 932 for up to four wells, structured so only two (Palm Valley and Ooraminna) need drilling, with an option for two at Mereenie. Palm Valley goes first if the ACCC is still delayed, with a spud in 6-8 weeks.

Discuss in chat

20 Dec 2017director officer appointment● Neutral

Timothy Woodall, a director of FAR Limited with 25 years in oil and gas M&A and finance, joins as non-executive director. With Hubbard's planned departure in the first half of 2018, the company says this completes the board renewal.

Discuss in chat

7 Dec 2017investor presentation● Neutral

Sydney Mining Club presentation arguing east coast gas is short. It says the Northern Gas Pipeline starts around November 2018 with 30 TJ/d contracted and about 60 TJ/d uncontracted, and drilling aims to lift 2P reserves from 126 PJ to 400-500 PJ. Mostly known themes.

Discuss in chat

29 Nov 2017agm notice● NeutralMajor

AGM chairman's address: Robert Hubbard intends to retire in the first half of 2018, saying the board should be led by someone not tied to the failed scheme recommendation. One more director is to be added. Funding is secure after the August raising.

Discuss in chat

29 Nov 2017investor presentation● Neutral

AGM presentation repeating the 'Closing the GAP' deck, with a reserves table: current 2P of 125.9 PJ, and potential net 227-415.5 PJ from the four-well, $25m programme if drilling confirms it. Largely known facts.

Discuss in chat

14 Nov 2017investor presentation● Neutral

'Closing the GAP' presentation restating known facts: targeted reserves of 446 PJ, cash of $28.6m, FY2018 EBITDA forecast positive, and the Mereenie marketing agreement awaiting ACCC interim approval. No new announcements.

Discuss in chat