30 Nov 2021drilling scheduled▼ Bad
Buffalo-10 is ready to receive the Valaris JU-107 rig, with handover expected within two weeks and the last regulatory approvals due before arrival. Spud slips again from early November. Results are now expected early in the new year; 31 MMbbl mid case unchanged.
Name changed from Carnarvon Petroleum Limited to Carnarvon Energy Limited, approved by shareholders at the 12 November AGM and effective 15 November 2021. ASX code CVN is unchanged. Administrative only.
AGM presentation under the 'Generating Value Through the Energy Transition' theme. Visible text is only the disclaimer and a highlights heading, so nothing new can be confirmed; treated as a repeat of known material.
Euroz Hartleys conference presentation under the 'Generating Value Through the Energy Transition' theme. Visible text is only the disclaimer and resource-estimate statements, so nothing new can be confirmed; treated as a repeat of known material.
Glossy 2021 annual report lodged, repeating the earlier financial report: Buffalo-10 planned for late October 2021 and Dorado FID mid-2022, with production targeted late 2025. The chairman says three wells are to be drilled in the coming year. No new announcements are visible in the available text.
2021 Sustainability Report lodged. It restates the net zero by 2050 target, the biorefinery joint venture with Frontier Impact Group and a new risk and sustainability committee. The CEO says core focus remains Dorado, Pavo, Apus and Buffalo-10.
Renewable diesel venture with Frontier Impact Group reports tests showing lower emissions than petroleum diesel. Feedstock MoUs are signed and FEED for the first biorefinery is expected next month. The plant is planned at about 18 million litres a year.
Buffalo-10 spud now expected early November, later than the late-October target, with the rig release from its prior job the stated dependency. Mid-case 31 MMbbl (gross, 2C) is unchanged; the well is to be kept as the first production well if successful, and the target should be reached in about 35 days.
September 2021 investor presentation titled 'Generating Value Through the Energy Transition'. The visible text is only the disclaimer and resource-estimate statements, so nothing new can be confirmed. Treated as a repeat of known material.
Corporate presentation repeating known facts: Dorado FEED, Sapura and Altera awards, FID mid-2022, 2C resource 162 MMbbl liquids (gross) and Buffalo 2C 31.1 MMbbl. Pavo-1 and Apus-1 volumes are unchanged. No new information.
The Valaris JU-107 jack-up rig is contracted for Buffalo-10, finalising the rig selected in June. It is the same rig that drilled Dorado-1 in 2018. Drilling starts after the rig finishes current work in about 8-10 weeks, still subject to support services and approvals.
Annual financial report to 30 June 2021 lodged. The chairman's review repeats known plans: Buffalo-10 spud late October 2021 (15-48 MMbbl prognosed), Advance funding US$20m, Dorado FID mid-2022. It states production is targeted for late 2025, whereas recent announcements say 2026. Text is truncated, so no financial figures are confirmed here.
Appendix 4G corporate governance checklist lodged with the annual report, pointing to the governance statement on the company website. Administrative filing with no new information.
Santos awards the Dorado wellhead platform FEED contract to Sapura Energy, which it calls the project's last significant commitment before FID around mid-2022. Completes the FEED contract awards flagged in June. Pavo and Apus are to be drilled early next year.
Carnarvon confirms Santos's award of the Dorado wellhead platform contract to Sapura Energy, called the final major contract. FID remains around mid-2022 and first production 2026. Development drilling is planned for 2024-25; Pavo and Apus are to be drilled early next year. Repeats the Santos news of 26 Aug.
Carnarvon confirms the Altera FPSO FEED award and has now formally begun talking to financiers about funding its share. FID remains mid-2022. First oil is given as 2026, later than the 'late 2025' Santos had indicated earlier.
Santos awards the Dorado FPSO FEED contract to Altera Infrastructure, the project's largest contract. It begins with full definition engineering. A wellhead platform contract is to follow soon, keeping Dorado on track for FID around mid-2022.
Keraudren Extension 3D is complete, with ~2,600 km2 acquired over about 50 prospects and leads, up from the 30 noted before. Data now goes to processing; 68% of the basin acreage has 3D coverage. Pavo-1 and Apus-1 drilling remains late 2021 or early 2022.
3,119,670 performance rights granted to management and executives under the new plan flagged earlier. A further 2,724,655 for MD Adrian Cook await shareholder approval at the AGM. Long-term rights vest on shareholder return hurdles over three years.
Carnarvon forms a 50/50 joint venture with Frontier Impact Group to make renewable diesel from biomass, investing A$2.6m seed capital. First production is targeted for late 2022. It is a new line outside oil and gas, which the company says will not draw on its core projects' resources.
Carnarvon commits to net zero emissions by 2050 or earlier, starting by offsetting its current head-office emissions. A roadmap is still being developed. The focus stays on Dorado and Buffalo, with portfolio diversification into lower carbon assets mentioned as a future aim.
A jack-up rig has been selected for Buffalo-10, with a letter of intent signed and the formal contract being finalised. Drilling is expected to start late October 2021. Carnarvon stays free carried for the first US$20m. Timing still depends on approvals and support services.
Carnarvon confirms Dorado FEED has begun, with FID on schedule for around mid-2022. It has engaged advisers to fund its 20% share and will approach financiers once the FPSO and WHP FEED contracts are finalised. Repeats the Santos announcement.
Santos launches Dorado FEED, the step expected this quarter. Phase 1 gross capital cost is about US$2bn, with initial gross oil of 75,000-100,000 bpd and FID around mid-2022. Santos is also seeking buyers for non-operated equity in Dorado.
Archer 3D (~1,600 km2) finished 1 June and the Keraudren Extension 3D (~3,200 km2) has begun. Carnarvon restates Pavo-1 (82 MMbbl mean, Pg 34%) and Apus-1 (235 MMbbl, Pg 23%) plans; the Tom Prosser rig has been delivered to Santos. No new results.
Archer 3D seismic survey is about 63% acquired of the planned ~1,600 km2, progressing as planned. The survey vessel then moves to the Keraudren Extension 3D. This is data acquisition, with no results yet.
Buffalo-10 is planned for Q4 2021. Advance Energy has paid the US$20m, so drilling costs Carnarvon nothing unless the well exceeds that. Long lead equipment orders are placed and the rig tender is nearing completion.
The Archer 3D seismic survey has started over Dorado and the area south-west of it, expected to take 40-50 days. The Keraudren Extension 3D, covering over 30 prospects and leads in WA-436-P and WA-438-P, follows. This is new data acquisition, not a result.
The Buffalo farm-out to Advance Energy is complete: it now holds 50% and has met its funding requirement, so Carnarvon is free carried on Buffalo-10 up to US$20m. The well is now said to be on track for late 2021, subject to securing a rig.
Advance Energy has raised the capital for its 50% Buffalo stake, subject to its shareholder vote in mid-April, and Timor-Leste government approval is received. Carnarvon is carried for Buffalo-10 up to US$20m. This clears two of the conditions in the December deal.