7 Dec 2022drilling progress report● Neutral
Wolf Pack's curve has landed in the planned Sycamore bench at ~9,900 ft and the well is drilling the horizontal section at ~10,950 ft measured depth. Reported on schedule; routine progress, no flow results yet.
Wolf Pack's intermediate section has been drilled, cased and cemented, and drilling of the curve has begun. The well targets the Sycamore with ~7,500 ft lateral and ~17,750 ft planned measured depth. Routine progress, no results.
Wolf Pack's surface hole is drilled, cased and cemented, and the well is drilling the intermediate section at ~6,000 ft TVD. Reported on schedule; routine progress with no results yet.
The Rangers well has paid out seven months after first production, with drilling and completion costs recovered. It produced ~173,400 BOE (~83% oil and NGLs) and US$13.243m of revenue. This resolves the open payout thread, which had been forecast for late Q3 2022.
The Juanita well hit an over-pressured zone in the Springer Group at ~3,500 ft TVD, so drilling is suspended and the rig demobilised as it is unsuited. Oil shows were seen in the first of ten target zones. Restart is likely early in the New Year.
The Wolf Pack well, first of the Phase Two SWISH development wells, has spudded using Latshaw Rig 12 and is drilling the vertical section toward the first casing point. This follows the rig contract and pad work; operations are reported on schedule, with no results yet.
The Juanita well, the first in the new Bradbury area, has spudded with surface casing cemented and is drilling the straight hole at about 2,000 ft TVD toward ~6,450 ft. Operations are reported on schedule; no zone results yet.
November 2022 company presentation repeating known points: market cap ~A$60m, cash ~A$29.0m at 30 September, ~4,300 acres, 11,606,000 BOE prospective resource, three SWISH units held by production. Text is truncated, so no new detail is confirmed.
7 Nov 2022asset acquisition disposition▲ GoodMajor
Brookside added a fourth operated SWISH unit, the Bruins DSU, next to its Jewell and Flames units, lifting SWISH acreage by 34%. It is not yet held by production; price and interest are not stated here. Adds to the 20+ well inventory.
Wolf Pack pad is complete and the conductor is set and cemented. Drill rig and crew are expected on site the week of 7 November. Preparation step ahead of the spud; no drilling results yet.
Record September-quarter receipts of A$17.0m and operating cashflow of A$11.6m (up 34%). Net production 1,395 BOE/d (up 45%). Cash A$28.8m, no debt, 5,012,272,899 shares. Flames IP24 ~1,500 BOE/d; Flames unit now held by production, enabling reserve bookings.
The Flames well, producing since early August, reached an IP24 of ~1,500 BOE/day (75% liquids), second highest Woodford rate in SWISH, and an IP30 of ~1,200 BOE/day. This resolves the pending Flames rates and is comparable to Rangers' IP30 of 1,200.
Pad construction has started for the Wolf Pack well, the first Phase Two SWISH well, with crews on site and work said to be on schedule. This is early site preparation ahead of the rig contracted for the early November spud.
Juanita pad construction is finished and the 70-foot conductor hole is cased and cemented. The rig and crew are due on site the week of 17 October. Preparatory step toward the Bradbury spud; no drilling results yet.
Managing Director David Prentice will present at the Noosa Mining Investor Conference on 10 November 2022. Shareholders can register for free until 4 November. Notice of an event only; no new company information.
Brookside has tripled its acreage in the new Bradbury area, east-northeast of SWISH, holding three 40-acre units at ~80% working interest. The first low-cost vertical well, Juanita (~6,450 ft TVD), is set to spud mid-October, funded from cash and cashflow.
Black Mesa has contracted Latshaw Rig 12 to drill the Wolf Pack well, a Sycamore horizontal (~17,000 ft planned) and the second well in the Rangers unit. Spud is expected in early November. It is the first well of the post-HBP development phase.
14 Sept 2022security holder rights change● Neutral
Brookside has set up a sale facility for holdings under A$500 (fewer than 38,461 shares at A$0.013). CPS Capital will buy them at $0.013 unless holders opt out by 31 October 2022. Admin step to cut the cost of small holdings.
Half-year to 30 June 2022 shows gross revenue over $22m, adjusted net profit of $9m, gross production of 250,792 BOE and cash of $34m. All three SWISH units are held by production. Highlights only; the full accounts are not in this text.
Flames began commercial oil and gas sales during early flow-back, so its unit is now held by production, completing the three-unit HBP program. Brookside's working interest is stated as ~71.3% (earlier estimate ~80%). IP rates to be reported later.
29 July 2022quarterly activities report▲ GoodMajor
Record June-quarter receipts of A$11.723m and operating cashflow of A$7.941m (up 236%). Net production 961 BOE/d (up 117%). Cash A$31.6m (A$23.4m after Loan Note repayment), no debt, 5,011,272,899 shares. Rangers cumulative 81,733 BOE; Rangers unit now held by production.
Rangers is stabilising at 1,200 BOE/day average (IP30), with ~82,000 BOE (87% liquids) produced by end-June, up from ~73,160 BOE in June. Peak oil rate was 952 bbl/day. Payout is forecast late in Q3 2022. Resolves the pending IP30 figure; IP24 and IP90 are not given here.
July 2022 presentation for Spark Plus Aussie Equities Day, largely repeating known points: three wells on production, all three units held by production, ~3,400 acres, 11,606,000 BOE prospective resource. Market cap shown as ~A$80m. Cash quoted is the old A$17.7m March figure.
With the three-well HBP program nearly complete, Brookside has lodged OCC applications for a new Sycamore well in the Jewell unit (the Ruby well, east half) and is preparing similar applications for Rangers. Pre-drill planning has started; no spud date or cost given.
Flames flow-back has begun, with the well flowing to temporary facilities and some oil and gas already recovered alongside stimulation fluid. Next step is switching to permanent facilities and starting sales. No flow rates given yet.
14 July 2022capital raising announcement▲ GoodMajor
The remaining 37,654,688 unexercised BRKOB options were placed through the CPS Capital underwriting. This closes out the options exercise process begun in March; total proceeds are not stated here.
Flames fluid circulation is complete and the site is connected to the Enerfin gas sales pipeline with a meter installed. Temporary flow-back equipment is set and tested. Flow-back is next; no flow rates yet.
The final batch of option exercises produced 163,878,320 new shares. Options still unexercised will be placed under the CPS Capital underwriting from 7 March 2022. Adds to the share count; value of proceeds not stated.
Flames isolation plugs have been milled out. Next is circulating fluid to clean out debris before flow-back begins to temporary facilities. On schedule and without incident; no flow results yet.
A further 504,725,579 BRKOB options were exercised by expiry on 30 June 2022, leaving 201,533,008 still being reconciled. Any remainder goes to CPS Capital under the 7 March underwriting. Exercise at $0.011 brings in new cash, and the amount is not stated here.