9 Jan 2008drilling progress report● Neutral

Freeborn-1 is in pressure build-up, with fracture stimulation planning under way. Outlar-1 is steady at 3.2 MMcf/d and 200 bbl/d. Harrison-2 is at 4,792 ft toward a 13,000 ft target.

Value this in the calculator →Discuss in chat

9 Jan 2008other● Neutral

Notice that the convertible note interest of $0.0504 per note is payable 31 January 2008 (record date 24 January). Administrative; no new substance.

Discuss in chat

8 Jan 2008capital raising announcement● Neutral

Antares is making its first draw on the Cornell equity line, issuing A$300,000 of shares at a 2% discount to the lowest daily VWAP, provided VWAP stays above 40 cents. A 3% commission applies. A small raise, in line with the December facility.

Discuss in chat

7 Jan 2008well test result● NeutralMajor

The first Freeborn-1 test, a 15 ft interval near 14,700 ft, flowed gas and load water at an unstable rate. The company blames likely near-wellbore damage and plans fracture stimulation. It calls the unstimulated flow encouraging, but there is no proven rate yet.

Discuss in chat

2 Jan 2008drilling progress report▲ Good

Freeborn-1's rig has been released and the first interval will be perforated Friday. Outlar-1 has stabilised at 3.44 MMcf/d and about 215 bbl/d. Harrison-2 (75%) was spudded 30 December.

Value this in the calculator →Discuss in chat

19 Dec 2007drilling progress report● Neutral

Freeborn-1 tie-back casing is being run ahead of testing. Outlar-1 is flowing at about 2.5 MMcf/d and 150 bbl/d on a small choke while rates are optimised. The Harrison-2 rig is arriving, with spud expected next week.

Value this in the calculator →Discuss in chat

19 Dec 2007asset acquisition disposition▲ GoodMajor

Sale of the Anadarko basin (South Goodwin) assets to Exoma Energy settled for USD4.35m, with USD3.9m received on top of the USD450,000 deposit. Effective date is 1 December 2007. It completes the July agreement and brings cash in.

Discuss in chat

18 Dec 2007production update▲ GoodMajor

Outlar-1 (West Wharton) began production at 2.4 MMcf/d of gas and 158 bbl/d of condensate, with no water, ending the wait for the pipeline. Antares' interest fell from 30% to 26.25% at first sales. Follow-up wells are planned.

Discuss in chat

18 Dec 2007capital raising announcement▲ GoodMajor

Antares secured an A$20m equity line with Cornell Capital (YA Global) over 36 months. It can draw up to A$300,000 per 10 trading days at a 2% discount to the lowest daily VWAP, with a 3% commission. It is optional funding, not cash raised.

Discuss in chat

12 Dec 2007drilling progress report● Neutral

Freeborn-1 has only 15 ft of obstruction left to clear before testing. Outlar-1 pipeline is pressure tested, with production expected this weekend. The Harrison-2 rig is due late next week.

Value this in the calculator →Discuss in chat

6 Dec 2007asset acquisition disposition▲ Good

Antares received a final USD882,000 and a full mutual release from Zorlu, closing out the 2005 sale of its Turkish subsidiary. With USD695,000 received in October, success fees total USD1.577m, against up to USD4.4m originally possible.

Discuss in chat

5 Dec 2007drilling progress report● Neutral

Freeborn-1 hole clean-out is nearing completion, with logging and tie-back casing still ahead of testing. Outlar-1 pipeline is almost finished, with production expected next week. Harrison-2 drilling is due this month.

Value this in the calculator →Discuss in chat

28 Nov 2007drilling progress report▼ Bad

Freeborn-1 testing is delayed because cement left in the hole after liner setting is being drilled out. A tie-back casing string must still be run before perforation. Outlar-1 start-up is still scheduled for early December.

Value this in the calculator →Discuss in chat

21 Nov 2007drilling progress report● Neutral

Freeborn-1 testing is now expected the week after the 25 November holiday. Outlar-1 pipeline trenching is under way, and the Harrison-2 location is built with drilling due in December. Nothing new in substance.

Value this in the calculator →Discuss in chat

19 Nov 2007asset acquisition disposition▼ BadMajor

IPR has withdrawn its offer to sell its Kenedy Ranch Group A interest, ending the deal announced 10 October that would have lifted Antares from 5% to 60%. Antares stays at 5% in Group A and 50% in Group B and is weighing options, including drilling Group B.

Discuss in chat

14 Nov 2007drilling progress report● Neutral

A liner was run and cemented at Freeborn-1 (50%), with testing expected after the 22-25 November holiday. Outlar-1 is still waiting for its pipeline, and Harrison-2 (75%) is due to start drilling in December. No new results.

Value this in the calculator →Discuss in chat

14 Nov 2007other● Neutral

Antares cancelled 26,875 shares under its on-market share buy-back, notified to ASIC by Form 484. Administrative; no new substance.

Discuss in chat

7 Nov 2007drilling result▲ GoodMajor

Freeborn-1 reached 16,030 ft. Logs show potential gas sands across four intervals between 14,180 and 14,760 ft with good reservoir quality. A liner will be run to test about 75 ft of net sand. Also, a Harrison-2 appraisal well at Oyster Creek (75%) is planned before year end.

Value this in the calculator →Discuss in chat

31 Oct 2007drilling progress report▲ Good

Freeborn-1 hit a thick, apparently unconsolidated sand at 14,500-14,900 ft with strong gas shows. Sand was the main pre-drill uncertainty, but commerciality awaits logs and tests. Outlar-1 pipeline is still awaiting written approvals.

Value this in the calculator →Discuss in chat

31 Oct 2007quarterly activities report▲ Good

September quarter report: Outlar-1 flowed 1.7 MMcf/d and 120 bbl/d and awaits a roughly USD82,000 net pipeline. Freeborn-1 was at 15,476 ft with encouraging sand and gas. Largely repeats announced news.

Discuss in chat

24 Oct 2007drilling progress report● Neutral

Freeborn-1 is at 12,715 ft after setting a second intermediate casing 300 ft higher than planned because of heavy mud needs. No change to the program. Outlar-1 pipeline route chosen, with the operator estimating 4-8 weeks to production.

Value this in the calculator →Discuss in chat

17 Oct 2007drilling progress report● Neutral

Freeborn-1 is at 11,559 ft with high mud gas, and the Wilcox section is expected within a week. Outlar-1 is shut in awaiting a pipeline. Its unusually rich gas should favour a high-BTU sales line.

Value this in the calculator →Discuss in chat

15 Oct 2007flow test result▲ GoodMajor

Outlar-1 flowed about 1.7 MMcf/d of gas and 120 bbl/d of condensate with no water on a restricted choke, at over 7,000 psi. The company believes a higher rate is sustainable. Well is shut in pending a pipeline. Confirms a West Wharton discovery (30%).

Discuss in chat

10 Oct 2007asset acquisition disposition▲ GoodMajor

Antares agreed to buy IPR's (formerly Santos USA's) interest in Kenedy Ranch Group A, lifting its stake there from 5% to 60%, and will become operator. This enables testing of the gas sands found in KMF 228-1, with another well planned for early 2008. Price not stated.

Discuss in chat

10 Oct 2007drilling progress report● Neutral

Freeborn-1 set intermediate casing at 8,659 ft, slightly shallow because of high Queen City gas. The company says the forward program is unaffected. Outlar-1 testing has just begun.

Value this in the calculator →Discuss in chat

3 Oct 2007drilling progress report▲ Good

Freeborn-1 is at 8,621 ft, with high gas in the Queen City sandstones requiring heavier mud. The company calls the hydrocarbons encouraging but it is too early to judge commerciality. Outlar-1 needed a remedial cement squeeze, and testing should start soon.

Value this in the calculator →Discuss in chat

3 Oct 2007other● Neutral

Notice that the quarterly interest of $0.0504 per convertible note is payable 31 October 2007 (record date 24 October). Administrative; no new substance.

Discuss in chat

26 Sept 2007drilling progress report● Neutral

Freeborn-1 has set 13 3/8 in casing at 3,026 ft and will drill toward about 9,500 ft. A service rig is on site at Outlar-1 to inspect casing and run a cement bond log before testing.

Value this in the calculator →Discuss in chat

24 Sept 2007drilling spud▲ GoodMajor

Jean H. Freeborn-1 spudded 20 September on the Rowena Wilcox prospect, targeting 16,000 ft with potential over 200 BCF. Antares holds 50% with minimum dry cost about USD2.85m. Turnkey contract fixed at USD4.9m. The CEO calls it transformational if it succeeds.

Value this in the calculator →Discuss in chat

19 Sept 2007drilling progress report● Neutral

Outlar-1 casing is cemented and the rig was released 15 September to move to Freeborn-1. A service rig will arrive to test the three sand sequences, starting with the lowest.

Value this in the calculator →Discuss in chat