27 June 2012production update▲ GoodMajor
May net output jumped to 1,816 boepd from 1,068 in April, up 70%, as 2012 drilling-program wells came on and gas curtailment ended. Company says 30-day rates beat its type curve and reiterates the 2,500 boepd end-2012 target.
Aloe Vera No. 3 and Yucca No. 2 (ten-stage frac done) are flowing back. McNew No. 2 is being fracked. Alamo No. 1 frac is set for 10 July. Coyote No. 2 is drilling at 7,197 ft. No rates yet.
Aloe Vera No. 3 frac done and plugs being drilled out. Yucca No. 2 is being fracked. Alamo No. 1 reached 10,260 ft with frac set for 5 July. Coyote No. 2 started drilling. McNew No. 2 frac is scheduled for 20 June. No new production rates.
Archer 16 No. 1 peaked at 117 bopd (137 boepd) but its 20-day rate is only 65 boepd, softer than the 90 bopd earlier reported. Ray No. 5 is above 500 boepd, the best 30-day rate Antares has achieved in the Permian. Aloe Vera No. 3 frac this week.
April net output was 1,068 boepd, up slightly from 1,027 in March. Two new compressors in early May lifted all Southern Star gas curtailment. The company says 30-day well rates beat its type curve and keeps its 2,500 boepd end-2012 target. Alamo No. 1 spud 25 May.
Archer 16 No. 1 (Northern Star) is flowing over 90 bopd, which the company calls commercial and says supports more wells there this year. 30-day rates: Live Oak No. 2 313 boepd, Cottonwood A 246, Aloe Vera No. 2 184. Ray No. 5 15-day rate is 387 boepd.
AGM chairman's address and slides repeat known figures: 1P 15,566 Mboe, 260m shares, US$30m drawn, A$1.00 target still unmet. Slides add current production of 1,900 boepd, A$8.934m cash at 31 March and 10 wells drilled in 2012. No new shares planned for two years.
Initial rates reported: Cottonwood A No. 1 313 boepd (22-day), Live Oak No. 2 289 boepd (16-day), Aloe Vera No. 2 177 boepd (24-day). Ray No. 5 made 178 boepd on day two. Aloe Vera No. 3 and Yucca No. 2 finished drilling; Archer 16 is above 40 bopd.
Cottonwood A No. 1 hit a peak 24-hour rate of 325 bopd, about 542 boepd with gas (earlier estimate near 500). Live Oak No. 2 peaked above 400 bopd, the best oil rate in Southern Star. Ray No. 5 and Archer 16 are flowing back.
March quarter net oil was 52,889 bo and gas 204,379 mcf, with receipts of A$4.87m, up 95% on the prior quarter. Six wells are drilled of the 30-well program. Cottonwood A reached a 24-hour peak near 500 boepd. Total drawn on the Macquarie facility is US$30m.
March net output fell to 1,027 boepd from 1,154 in February, which the company attributes to expected gas curtailment. It expects new wells to lift output from mid-April, and still targets 2,500 boepd by end-2012. Cottonwood A is estimated at 400 boepd.
Cottonwood A No. 1 produced 267 bopd, estimated over 400 boepd with gas, the best rate Antares has achieved in Southern Star. Live Oak No. 2 made over 150 bopd. Archer 16 No. 1 frac is done and Ray No. 5 is being fracked.
Cottonwood A No. 1 and Aloe Vera No. 2 each now produce over 100 boepd while still cleaning up. Live Oak No. 2 flows over 150 boepd. CR-21 No. 4 hit TD at 10,293 ft; Archer 16 cores show good Wolfcamp quality and its frac is underway.
CR-21 No. 4 is drilling near 10,055 ft. Yucca No. 1 frac is underway, Live Oak No. 2 frac is complete, and Cottonwood A No. 1 and Aloe Vera No. 2 are still flowing back with rising oil cut. No rates are given yet.
Administrative notice: convertible note interest of $0.0488 per note is payable 30 April 2012, record date 20 April. Slightly lower than the previous $0.0504 quarterly payment.
Unquoted performance rights lapsed (666,667 and 2,500,000) as vesting conditions were not met. Directors' holdings fall accordingly; shares stay at 260m, with 7.5m convertible notes and 5m performance rights remaining.
Antares drew a third US$10m from its US$200m Macquarie facility, bringing the total drawn to US$30m. It still plans US$50m drawn by end-2012 to fund the 30-well program, which would hold all of Southern Star by production.
Reserve summary for 31 Dec 2011 shows 1P up 2,209% from 674 Mboe in 2010, 2P up 1,795% and 3P up 2,068%, using $95.25/bbl oil. Gives per-share cash-flow values on 260m shares. Headline volumes are in the annual report and evaluation.
2011 annual report: 1P reserves 15,566 Mboe (up 2,209%), 2P 27,195 Mboe, 3P 42,621 Mboe. Sales revenue A$8.92m (+131%); production 145,602 boe. US$30m drawn on Macquarie facility; 260m shares after buy-back. The A$1.00 share price target for end-2011 was missed. No new shares planned for two years.
Full independent-style reserve and resource evaluation as of 31 Dec 2011, explaining SPE-PRMS definitions. The excerpt shown contains definitions only; the figures appear in the companion summary and annual report (1P 15,566 Mboe, 2P 27,195 Mboe).
Archer 16 No. 1 (Northern Star) reached TD of 11,362 ft, with frac due 18 April. Ray No. 5 reached 10,311 ft, frac 25 April. Live Oak No. 2 frac is underway and Yucca No. 1 frac is set for 11 April. No production rates yet.
February net output averaged 1,154 boepd, up slightly from 1,138 in January; no new wells came online in 2012. Management expects new-well output from April and still targets 2,500 boepd by end-2012. March gas is expected lower due to gas gathering curtailment.
22 Mar 2012asset acquisition disposition▲ GoodMajor
Antares bought Dinero's 1.3-2.7% working interests across most Southern Star leases, plus 224 net acres (320 gross) in western Howard County worth eight more drilling locations. No price given. It adds a little control and acreage to Southern Star.
Yucca No. 1 reached TD of 10,342 ft, with hydrocarbons logged in several zones, and will be fracked mid-April. Cottonwood A No. 1 and Aloe Vera No. 2 are flowing back with no rates yet. Archer 16 No. 1 may stop at about 11,200 ft.
Three rigs are now running together, a company first. Yucca No. 1 is at 8,394 ft, Ray No. 5 at 3,017 ft and Archer 16 No. 1 at 4,803 ft with intermediate casing being set. No new results.
Cottonwood A No. 1 frac is done and Aloe Vera No. 2 is being fracked. Yucca No. 1 is at 7,147 ft, Ray No. 5 is about to spud, and Archer 16 No. 1 will make three rigs running at once, a company first.
January net output averaged 1,138 boepd, down from 1,204 in December and 1,242 in November. Coyote No. 1 first produced in mid-February at 70 boepd, and Live Oak No. 1 is awaiting repairs, leaving the field about 100 boepd.
Yucca No. 1 has started drilling at Southern Star. Halliburton will frac Cottonwood A No. 1 and Aloe Vera No. 2 the week of 5 March. Archer 16 No. 1 is still expected to start in March.
Live Oak No. 2 reached TD of 10,308 ft with good shows in all main Wolfberry zones, and will be fracked in late March. Archer 16 No. 1 (Northern Star, 100%) is due to spud in March, to 12,400 ft.