Stockle - the stock oracle

ADX Energy Ltd

ASX:ADX
A$0.019Close 7 Oct 2026 · delayed

Past year: ▼ 37%(1.80c – 3.20c AUD)

Market cap
A$20.4m
Shares on issue
1.08bn
In-ground value
A$1.76bn
Risked multiple
under review
Story beats
268 since 2006
Last event
28 Aug 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

10 Nov 2011resource reserve update▲ GoodMajor

ADX estimates a mean contingent oil in place of 51 million barrels for the Sidi Dhaher discovery. This is oil in place, not recoverable; recoverable volumes depend on a successful well test, with rig selection under way. It follows the 3 October discovery.

Value this in the calculator →Discuss in chat

3 Nov 2011well test result▲ Good

Lab analysis confirmed the Sidi Dhaher-1 samples are typical live crude oil with mud filtrate and minor water. Tender for a well-test rig went to 5 providers. Commerciality still depends on testing, and a resource range is described as imminent.

Discuss in chat

31 Oct 2011other▲ Good

Appendix 5B for September 2011 quarter: cash rose to $2.408m from $783k, helped by $1.862m received from JV partners and a $1.021m exploration bond release. Lambouka buybacks from Carnavale and PharmAust completed. Planned outflow next quarter is $855k.

Discuss in chat

26 Oct 2011drilling progress report● Neutral

The Challenger rig has left Sidi Dhaher-1 and the site is cleared. A cheaper rig is being chosen for oil testing. Oil quality results are expected within a week and a resource range for the discovery in early November.

Value this in the calculator →Discuss in chat

10 Oct 2011annual report● Neutral

2011 annual report with chairman's review citing a challenging year from Tunisia's political situation and capital market turbulence. Plans include a Dougga appraisal well and farm-out, Lambouka testing and Romania seismic. It mostly repeats known facts; the text is truncated.

Discuss in chat

3 Oct 2011drilling result▲ GoodMajor

Sidi Dhaher-1 found an interpreted oil column of about 30 m in Upper Cretaceous rock at 2,011 m total depth, but a well test is needed to confirm commercial rates. The well will be suspended and the rig released. This is ADX's first discovery since the Lambouka gas find.

Value this in the calculator →Discuss in chat

30 Sept 2011annual report● Neutral

Annual financial report for the year to 30 June 2011, lodged with directors and Rothsay as auditor. The provided text is truncated and contains no financial figures, so no results can be stated.

Discuss in chat

30 Sept 2011other● Neutral

XState Resources, a 10% Sidi Dhaher partner, re-lodged ADX's 30 September statement on the erroneous report. Cover letter only; no new information.

Discuss in chat

30 Sept 2011regulatory community update● Neutral

ADX says an unsubstantiated, erroneous report speculated on Sidi Dhaher-1 results. It calls premature discussion of hydrocarbons inappropriate and promises to release accurate results when practical. No well results are given.

Discuss in chat

26 Sept 2011admin correction● Neutral

Re-release of the 26 September Sidi Dhaher update, correcting its number from 7 to 6. All other content is unchanged.

Discuss in chat

26 Sept 2011drilling progress report● Neutral

Sidi Dhaher-1 was logged to 1,785 m without problems, then deepened to 2,011 m. Logs and pressure tests were run, and sampling (MDT) of zones of interest was being prepared. No result stated. Numbered #7 in error.

Value this in the calculator →Discuss in chat

22 Sept 2011drilling progress report● Neutral

Sidi Dhaher-1 reached 1,785 m, then a pump failure and a hole obstruction at 1,366 m limited the first logging. Several potential reservoirs were found higher than predicted. Logs are being interpreted; no hydrocarbon result stated.

Value this in the calculator →Discuss in chat

16 Sept 2011drilling progress report▲ Good

Sidi Dhaher-1 is drilling at about 1,700 m. Two potential reservoirs, Tertiary and Cretaceous, were hit higher than predicted. The next casing point is now planned at about 2,000 m, followed by logging.

Value this in the calculator →Discuss in chat

12 Sept 2011drilling progress report● Neutral

Sidi Dhaher-1 has set 13 3/8-inch casing and is drilling 12 1/4-inch hole at about 1,300 m. Two potential reservoir zones have been intersected and will be wireline logged before the next casing.

Value this in the calculator →Discuss in chat

9 Sept 2011farm in farm out agreement▲ GoodMajor

ADX will buy back PharmAust's 10% of Lambouka for 1,000,000 ADX shares, with PharmAust paying US$50,000 and ADX forgiving $400,473 of past costs. ADX would hold 60% of Lambouka, subject to JV pre-emption. This extends the Carnavale buyback.

Value this in the calculator →Discuss in chat

9 Sept 2011farm in farm out agreement● Neutral

PharmAust's side of the Lambouka buyback: it exits its 10% and cancels its Italian-waters option, citing the likely cost of a sidetrack and removal of abandonment liabilities. Same terms as ADX's release.

Value this in the calculator →Discuss in chat

7 Sept 2011investor presentation● Neutral

Good Oil conference presentation restating known facts: 398m shares, $43.8m market cap at 11 cents, ~254 mmboe most likely discovered resource across three Sicily Channel discoveries, and Sidi Dhaher drilling. Lambouka is shown at 50%. No new information.

Discuss in chat

6 Sept 2011drilling progress report● Neutral

Sidi Dhaher-1 has drilled to 1,001 m and is running 13 3/8-inch casing. The first potential hydrocarbon target, the Eocene reservoir, is expected to be reached later this week.

Value this in the calculator →Discuss in chat

1 Sept 2011investor presentation● Neutral

Notice of an audio broadcast by the chairman on the Sidi Dhaher spud, the earlier delays, Tunisia's political situation and Sicily Channel acreage. No new results or figures are in the notice itself.

Discuss in chat

30 Aug 2011drilling progress report● Neutral

ADX corrects the spud time to 6pm GMT on Friday 26 August, not 27 August. The 16-inch hole is drilled to 652 m, with casing to be run next week.

Value this in the calculator →Discuss in chat

29 Aug 2011drilling spud▲ GoodMajor

Sidi Dhaher-1 spudded at 07:00 GMT on 27 August 2011 and was drilling the 16-inch hole. It had a planned depth of 2,168 m and about 33 days of drilling, targeting 175 bcf of gas and 44 mmbbls of oil (prospective). ADX held 40% as operator.

Value this in the calculator →Discuss in chat

25 Aug 2011drilling progress report▲ Good

The Egyptian choke line arrived and passed testing, resolving the 22 August delay. Spud is described as imminent, with a pre-spud meeting set for 26 August. The rig goes on day rate once ADX accepts it.

Value this in the calculator →Discuss in chat

22 Aug 2011drilling progress report▼ Bad

Sidi Dhaher rig systems are tested, but ADX will not allow drilling until all critical spares are on site. A choke line must come from Egypt, causing another incremental spud delay. No new date given.

Value this in the calculator →Discuss in chat

22 Aug 2011joint venture update▲ Good

Shell has finished 2D seismic over ADX's Kerkouane-1 gas discovery offshore Tunisia under a data exchange deal, giving ADX and partners 104 km of new data. ADX says Kerkouane's potential could be on the order of Dougga and Lambouka (ADX's expectation, not a measured resource).

Discuss in chat

15 Aug 2011drilling progress report● Neutral

Sidi Dhaher blowout preventer failed initial pressure tests but was repaired and now passes; the diverter is installed and awaiting testing. This follows the 8 August equipment arrival. No spud date yet. ADX keeps 40% as operator.

Value this in the calculator →Discuss in chat

12 Aug 2011farm in farm out agreement● NeutralMajor

ADX will buy back Carnavale's 20% of Lambouka, lifting ADX to 50%, for 11,172,535 ADX shares, with Carnavale paying US$765k of past costs. Carnavale also gets two US$1m payments if Lambouka produces for 6 and 12 months. Subject to JV pre-emption.

Value this in the calculator →Discuss in chat

12 Aug 2011asset acquisition disposition● Neutral

Carnavale's side of the Lambouka buyback: it sells its 20% to ADX for 11,172,535 ADX shares plus two US$1m production-linked payments. It cites the high cost of a sidetrack and test after the well could not be flowed. Same deal as ADX's release.

Discuss in chat

8 Aug 2011drilling progress report▲ Good

Critical equipment, including the valve set from Libya, has reached the Sidi Dhaher rig site, resolving the delay reported on 3 August. Final testing of the blowout preventer and diverters should begin soon. No spud date given.

Value this in the calculator →Discuss in chat

3 Aug 2011drilling progress report▼ Bad

Sidi Dhaher spud is delayed again: safety-critical blowout preventer testing equipment, sourced from the contractor's Libya office, is held up by transport and customs problems. ADX cannot accept the rig and gives no spud date. Rig payments start only on acceptance.

Value this in the calculator →Discuss in chat

25 July 2011drilling progress report● Neutral

Sidi Dhaher rig-up is 95% complete. Minor camp infrastructure delays (sleeping quarters, kitchen) remain before 24/7 operations can start. No spud date is given.

Value this in the calculator →Discuss in chat