Story beats
117 since 2018
Last event
15 June 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

28 Mar 2023production update● Neutral

Vali-3 began producing on 27 March 2023, later than expected because water had built up in the well over 237 days. Vali-1 averaged 3.9 MMscfd in its first 30 days, in line with forecasts. Vali-2, commissioned 8 March, still needs fluid removed before it can flow.

Discuss in chat

28 Mar 2023production update● Neutral

Metgasco's version of the Vali update: Vali-3 online 27 March after delay from accumulated water, Vali-1 at 3.9 MMscfd over 30 days, Vali-2 awaiting fluid removal. Repeats Vintage's announcement.

Discuss in chat

9 Mar 2023half year report▼ Bad

Half-year to 31 December 2022: loss of $2,683,408, up from $1,825,386 a year earlier. Vali construction was all but complete at period end, with first gas shortly after. Text is truncated, so balance sheet and going concern detail are not shown.

Discuss in chat

22 Feb 2023production update▲ Good

Metgasco's version of the Vali first gas news: production began 21 February 2023, three years after discovery, giving Metgasco (25%) its first revenue. Repeats Vintage's announcement: 101 PJ gross reserves, 85 PJ uncontracted, Odin flowline laid, supply targeted Q3 2023.

Discuss in chat

22 Feb 2023production update▲ GoodMajor

Vali, discovered in 2020, delivered first gas on 21 February 2023 under the AGL contract (9-16 PJ to end-2026), giving Vintage its first revenue. Vali-3 is expected in early March and Vali-2 later that month. A development plan is expected in the second half of 2023.

Discuss in chat

13 Feb 2023production update▲ Good

Vali-1 facilities were handed over for commissioning on 11 February 2023, with first gas expected in 7-12 days. Vali-2 and Vali-3 handover is expected by early March. Commissioning is the last step before revenue.

Discuss in chat

13 Feb 2023production update● Neutral

Metgasco's version of the Vali commissioning news: Vali-1 handed over 11 February, first gas expected in 7-12 days. Repeats Vintage's announcement.

Discuss in chat

30 Jan 2023quarterly activities report● Neutral

December quarter report: cash $7.5m, down from $10.2m, with net debt of $2.5m. Vali pipelines and flowlines are installed and tested, handover is expected early February, and Odin site works have started.

Discuss in chat

25 Jan 2023production update● Neutral

Metgasco's version of the Vali update: handover and commissioning expected early February, and Odin trenching has begun. Repeats Vintage's announcement.

Discuss in chat

25 Jan 2023production update▼ Bad

Vali mechanical handover slips to early February 2023, with commissioning to follow, because of January rain and extreme heat restrictions. This pushes first gas beyond the January target, a fourth schedule slip. Odin flowline trenching has started.

Discuss in chat

21 Dec 2022production update● Neutral

Metgasco's version of the Vali and Odin update: pipelines tested, January first gas targeted. Adds that, on its reading, Vali and Odin production falls outside the gas price cap. Repeats Vintage's announcement otherwise.

Discuss in chat

21 Dec 2022production update● Neutral

Vali export pipelines are installed and pressure tested, with January 2023 first gas still targeted after the Christmas break. Odin accelerated connection work has begun. Vintage is reviewing the new federal gas price cap legislation; its impact on Vintage is not yet stated.

Discuss in chat

29 Nov 2022investor presentation● Neutral

Investor deck repeating known facts: Vali first gas expected January 2023, 101 PJ gross 2P (84% uncontracted), Odin ~40 PJ 2C with connection targeted Q3 2023. No new information.

Discuss in chat

22 Nov 2022agm notice● Neutral

All five AGM resolutions passed on a poll, including the remuneration report, Ian Howarth's re-election, performance rights for Neil Gibbins and Daniel Gibbins, and the 10% placement capacity (about 81.7% in favour, the lowest).

Discuss in chat

22 Nov 2022other● Neutral

Chairman's AGM address: calls 2022 a watershed year as Vintage nears first Vali gas. Credits AGL's $15m prepayment and the Dec/Jan raisings for funding to first gas. Says the Vali delays, now to January, came from supply chain, staffing and weather, not poor field performance. Text truncated.

Discuss in chat

22 Nov 2022investor presentation● Neutral

AGM presentation repeating known facts: Vali 101 PJ gross 2P (Vintage 50.5 PJ, 84% uncontracted), AGL contract of 9-16 PJ to end-2026, Odin 39.7 PJ gross 2C. Says Vintage is fully funded to first gas. No new information.

Discuss in chat

18 Nov 2022production update▼ BadMajor

Vali commissioning is pushed to January 2023, after the Christmas break, because November weather disrupted pipeline installation and forced rework. First gas had been expected in December 2022. This is the third delay, following the slips from mid-2022 and from October.

Discuss in chat

18 Nov 2022production update▼ Bad

Metgasco's version of the Vali delay: commissioning is now expected in January 2023 after the Christmas break, because of November weather disruption to pipeline work. Repeats Vintage's announcement.

Discuss in chat

10 Nov 2022investor presentation● Neutral

Noosa conference presentation repeating known facts: 50.5 PJ net Vali 2P reserves (84% uncontracted), 9-16 PJ AGL contract, Odin enquiry from gas buyers, and Vali first gas in December 2022. No new information.

Discuss in chat

10 Nov 2022joint venture update▲ GoodMajor

The PRL 211 joint venture splits the Odin connection into two stages. An accelerated interim tie-in using rental equipment and a 1.4 km line targets first gas in Q3 2023. A longer-term link via the Vali facilities follows. Vintage expects to fund its share from internal resources.

Discuss in chat

27 Oct 2022quarterly activities report● Neutral

September quarter report: cash fell to $10.2m from $18.25m, with net cash of $0.2m. Vali wells are complete and pipeline site works have started. First gas is now December, after the earlier slip from October. Odin concept engineering is complete.

Discuss in chat

26 Sept 2022annual report● Neutral

Appendix 4G and corporate governance statement for the year ended 30 June 2022, dated 23 September 2022. Administrative filing; it carries no new commercial information.

Discuss in chat

26 Sept 2022annual report● Neutral

FY22 annual report. The chair calls the Vali delay from mid-2022 into the new financial year frustrating and says it is attributed to global events. The report notes about 84% of Vali reserves are uncontracted and calls the 30 June market value a poor reflection of intrinsic value. Text is truncated, so no financials are available here.

Discuss in chat

26 Sept 2022agm notice● Neutral

The AGM will be held on 22 November 2022. Director nominations close at 5pm Adelaide time on 13 October 2022. Administrative notice only.

Discuss in chat

20 Sept 2022production update▼ Bad

Metgasco's version of the Vali delay: first gas moves from October to December 2022 on contractor crew and trade shortages. Mechanical handover is expected in early December. Repeats Vintage's announcement.

Discuss in chat

20 Sept 2022production update▼ BadMajor

Vali first gas slips again, from October to December 2022, because of contractor crew availability and skilled trade shortages affecting fabrication. Pipeline site works start the week of 19 September. This is the second delay after the May slip from mid-2022.

Discuss in chat

12 Sept 2022regulatory community update▲ GoodMajor

Queensland renewed Galilee Basin permits ATP 743 and 744 for 12 years and awarded six Potential Commercial Areas (about 4,700 km2) for 15 years. Vintage holds 30% of the 'Deeps' with Comet Ridge. This secures tenure so exploration, paused after Albany-1, can resume.

Discuss in chat

6 Sept 2022investor presentation● Neutral

Conference presentation repeating known facts: Vali 101 PJ gross 2P (85 PJ uncontracted), Odin 36 Bcf gross contingent, 9-16 PJ AGL contract and $15m prepayment. First gas at Vali is still shown as Q4 2022. No new results.

Discuss in chat

18 Aug 2022production update● Neutral

Metgasco's version of the 18 August Vali update: the four-well completion campaign is finished and the rig released. Production skids are being fabricated and first gas is still expected in October 2022. Repeats Vintage's announcement.

Discuss in chat

18 Aug 2022production update▲ Good

The Vali well completion campaign is finished. Vali-1 ST1, Vali-2, Vali-3 and Odin-1 are ready for production, with no lost-time injuries. Pipeline and facilities construction is underway, and first gas is still expected in October 2022, subject to equipment deliveries.