Each one in plain English, with the numbers worked through for a shareholder.
29 Nov 2023investor presentation● Neutral
AGM presentation largely repeats known facts: Odin-1 producing about 5 MMscf/d, all Odin gas contracted to Pelican Point to December 2026, Vali-2 plugging due in coming weeks, Vali-3 still shut in. Up to 2 more Odin wells are under review. Independent reserves certification is in progress.
The Vali-2 plugging contractor has rescheduled, so work is now likely from end-November rather than early November. Vali and Odin restarted on 27 October, ahead of schedule, at a combined rate above 7 MMscfd. No further outages are scheduled this quarter.
Metgasco's version of Vintage's 14 November update: Vali-2 work pushed to end-November, and Vali-1 and Odin-1 restarted 27 October above 7 MMscfd combined. Adds no new figures.
Metgasco's version of Vintage's 17 October update: Vali-2 plug planned for early November to cut water, Vali and Odin shut in for downstream maintenance, Odin-1 averaging 5.4 MMscfd. Metgasco says it is fully funded for the plugging. Adds no new figures.
Vali-2's excess water was traced to the two lowest perforated zones; the joint venture agreed to plug them off, planned for early November (about 3 days). Vali and Odin were shut in for third-party maintenance until about 4 November. Odin-1 has averaged 5.4 MMscfd.
A second Odin gas contract with Pelican Point Power covers 1 January 2025 to 31 December 2026, extending Odin's contracted supply to end-2026 on interruptible terms. Prices are in line with east coast expectations. Vintage says it has met its medium-term contracting targets.
Metgasco's version of the second Odin contract with Pelican Point Power, covering 2025 to end-2026 at market-consistent prices. Metgasco says the contract gives the JV confidence to assess further Odin appraisal wells.
FY23 annual report. The chair says the 5 cent raise compares with a year high of 13 cents, Odin started after year end, and Vali-2 and Vali-3 need further work. He says reserves and resources saw no significant change. Text is truncated.
Metgasco's version of the Odin-1 update: production is in line with or modestly ahead of its expectations, and it expects Odin to be material to its revenues. Adds no new figures.
Odin-1 averaged 6.0 MMscfd over four days to 19 September, slightly above the initial target rate, with negligible water. The rate is deliberately controlled to protect the well's pipe connection. It compares with 6.5 MMscfd on the 2021 test.
Metgasco's version of the Odin first-gas news: Odin-1 began producing on 14 September, supplying Pelican Point Power to end-2024. Metgasco calls it its second revenue stream and says it intends to build on Odin through future drilling.
Odin began producing gas on 14 September 2023, on schedule and in line with expectations, supplying Pelican Point Power to end-2024. It is Vintage's second producing field after Vali, 10 months after the decision to speed up the connection. Odin 2C is 40 PJ (Vintage 19 PJ).
Odin has regulator approval to commission and is still on track for September. Vali-3 could not be restarted despite repeated fluid removal and will stay shut in while remediation options, such as the Patchawarra, are assessed. This resolves the late-August restart expectation negatively. Vali-2 log results are due this month.
Metgasco's version of Vintage's 11 September update: Odin approved to commission and on schedule for September; Vali-3 stays shut in after failed restarts; Vali-2 log interpretation due this month. Metgasco says it remains fully funded for the Odin tie-in.
Managing Director Neil Gibbins' holding rose by 1,845,300 shares to 18,033,511 on 31 August 2023 through conversion of performance rights, at no cost. Routine director interest notice.
Conference slides restating known facts: Vali 2P of 101 PJ gross (Vintage 50.5 PJ, 42.5 PJ uncontracted), Odin 2C ~39 PJ, Odin start in September 2023. Says Vali-2 and Vali-3 have yet to sustain production; root-cause analysis under way. Text is truncated.
Odin's final equipment is due on site, with production still targeted for September 2023. Vali-2's production log has been run and is being interpreted. Vali-3 still needs more swabbing before its log can be run. Vali-1 remains in line with expectations.
Metgasco's version of Vintage's 1 September update: Odin on schedule for September, Vali-2 log completed and awaiting interpretation, Vali-3 swabbing continuing. Metgasco says it is fully funded for the Odin tie-in.
Metgasco's version of Vintage's 31 July update: Odin on schedule for first gas by end September quarter, Vali-1 in line, Vali-2 high water and shut in, Vali-3 restart late August. Metgasco says it is fully funded for the Odin tie-in.
Odin site works began 23 July and the flowline passed its hydrotest, on track for September start-up. Vali-2 gave more water and less gas than forecast and is shut in pending a production log; Vali-3 has been offline all but 4 days since March, restart expected late August.
Webinar slides restating known facts: Vali 2P of 101 PJ gross (Vintage 50.5 PJ, 42.5 PJ uncontracted), Odin 2C ~39.7 PJ, Odin online September quarter 2023. No new figures visible; text is truncated.
28 June 2023capital raising announcement● NeutralMajor
Retail offer completed, raising about $2.6m at $0.05, with 31.05m shares taken up and 21.5m allocated to underwriters. This completes the $5.6m raise, funding the Vali and Odin ramp-up.
What it means for a shareholder
31.1m new shares at about A$0.0837 to raise about A$2.6m. That's 3.7% dilution: every existing holder's slice gets 3.7% smaller. If you held A$1,000 of shares (11,942 at the issue price), your slice goes from 0.00148% to 0.00143% of the company. To keep it you'd need 460 more shares - about A$39 at the issue price.
Vali-1 resumed on 8 June at 3.6 MMscfd after a maintenance shut-in from 22 May. Rain-related road closures delayed Vali-2 and Vali-3, so stable production is now likely after 30 June. Odin's construction contract went to Global, with supply targeted before September quarter end.
Metgasco's version of Vintage's 22 June update: Vali-1 at 3.6 MMscfd, Vali-2 and Vali-3 stable production likely after 30 June, Odin on schedule with Global awarded construction. Metgasco says it is fully funded for the Odin tie-in.
Retail offer booklet for the 5-for-52 entitlement offer at $0.05 per share, aiming for about $3.6m in total and fully underwritten. It opens 7 June and closes 23 June. Booklet is largely legal terms; no new figures.
Administrative notice that the retail entitlement offer booklet was sent to eligible shareholders on 7 June, with a letter to ineligible holders. The offer closes 23 June. No new substance.
The institutional part of the raise is done: about $3.0m at $0.05 ($2.0m placement plus ~$1.0m entitlement), around 59.3m new shares. The ~$2.6m retail offer opens 7 June. Vintage says it is not subject to the gas price cap and is likely exempt from the draft code's price measures.
What it means for a shareholder
59.3m new shares at about A$0.0506 to raise about A$3.0m. That's 7.4% dilution: every existing holder's slice gets 7.4% smaller. If you held A$1,000 of shares (19,767 at the issue price), your slice goes from 0.00265% to 0.00245% of the company. To keep it you'd need 1,570 more shares - about A$79 at the issue price.
Capital raising presentation supporting the $5.6m raise announced the same day. Text is truncated; only disclaimers are visible, so no new figures can be reported.