History
Sigma Lithium built a Brazilian lithium mine from site mobilisation to production in under eighteen months, then faced a sale process, an offtake arbitration, a 2025 mining stoppage and local legal disputes.
2021-2022: Funding and building Phase 1
Sigma Lithium set out to build a lithium concentrate plant at Grota do Cirilo in Minas Gerais, Brazil, owned 100% through its subsidiary Sigma Mineracao S.A. In October 2021 it signed a binding term sheet with LG Energy Solution for 60,000 tonnes a year, rising to 100,000, though it still had to become a definitive agreement. Workers and equipment reached the site in November 2021, and foundation work began in December with 180 people.
The company paid for construction with equity. A placement at C$11.75 a share began at about C$60 million, was raised to C$85 million and then to C$136.7 million after BlackRock added C$64.2 million. It closed on 23 December 2021 with 11,634,137 shares sold, and the company said this fully funded Phase 1. Shares on issue ended 2021 at 99,377,349.
Through 2022 the studies grew. In May, reserves rose 2.6 times to 34 million tonnes, and Phase 1 was valued at US$1.6 billion after tax. In June the total resource rose about 50% to 85.7 million tonnes. In December an expansion study valued Phases 1 to 3 at US$15.3 billion for US$155 million of capital, and Sigma secured a US$100 million pre-export loan from Synergy Acquisitions Holding. Commissioning began on 20 December.
2023: Licence, first production and a sale process
The environmental operating licence was granted on 31 March 2023 by unanimous vote, sixteen months after mobilisation. First production came on 17 April. Cash fell from C$96.4 million at the end of 2022 to C$67.1 million by early June as the plant was commissioned. The first revenue arrived in May, and 30,000 tonnes shipped in July.
In September the board said it had received proposals for the operating company, the parent and the project, and began a strategic review. Glencore prepaid 50% of a 22,500 tonne cargo, the first of a repeating pattern of prepayments. Courts attached conditions to the transfer of two exploration sub-plots, which Sigma said did not impede expansion. The plant reached a record 890 tonnes a day in October. The sale process reached a final round in November and contractual negotiation with finalists in December, when Sigma also began preparing a separate listing of the Brazilian subsidiary. The record shows no outcome of the sale process.
2024: Expansion funding and a dispute with LG
The plant held its design rate of 270,000 tonnes a year through 2023, and an audited resource rose 27% to 109 million tonnes. Funding turned to debt. BNDES, Brazil's development bank, issued a letter of intention in February. In March Sigma closed US$90 million of trade finance lines, and Glencore prepayments rose to 85%. Also in March, LG Energy Solution began arbitration, alleging breach of the 2021 term sheet. Sigma said the claims had no merit, and no outcome is recorded.
In May reserves rose 40% to 77.0 million tonnes, enough for about 25 years at a planned 520,000 tonnes a year. LX International, formerly LG International, bought a cargo that month. In August BNDES committed a BRL 487 million, sixteen-year loan that fully funded the second plant, and construction began. At its September investor day Sigma set out a plan to roughly triple capacity by the end of 2026. In December a record 27,500 tonne cargo went to IRH of Abu Dhabi, and the Barreiro pit received all its licences together by unanimous approval. Shares on issue rose only to 111,267,279 by year end.
2025: A silent year
The record is almost silent on 2025. Later releases show that mining stopped at some point in the year, but no filing here says when or why.
2026: Restart and legal pressure
In January 2026 Sigma sold 100,000 tonnes of high-purity fines, signed a working capital revolver and began remobilising the mine. Katia Abreu, a former agriculture minister, joined the board. The company denied reports of an operational injunction, saying a labour ministry process concerned its waste piles. Mining restarted on 2 February with more than 600 people on site. On 4 February the mining regulator ANM issued a statement, dated 2 February, finding no evidence of serious risk in the piles and no legal basis for closure. Selling fines, and processing tailings and stockpiles, carried the company through the stoppage. In February it began drawing a US$96 million revolver and guided to 240,000 tonnes a year. In March it resumed selling high-grade concentrate at US$1,712 a tonne, against US$140 a tonne for fines. In April a US$100 million bank guarantee was signed to unlock the BNDES money for the second plant.
On 17 May a local judge ruled against the company, raising a possible US$10 million deposit. The state appeal court overturned this on 9 June. By 22 July 2026, Sigma was negotiating a conduct adjustment agreement with the Minas Gerais government after a notice from the regional office of SUPRAM, while reporting a second-quarter production beat. No equity has been issued since December 2021, and shares on issue stood at 111,402,979 at the end of 2025.
Written from the 54 story beats below (2021 to 22 July 2026), which come from the company's own announcements and filings.