Sigma Lithium built a Brazilian lithium mine from site mobilisation to production in under eighteen months, then faced a sale process, an offtake arbitration, a 2025 mining stoppage and local legal disputes.

2021-2022: Funding and building Phase 1

Sigma Lithium set out to build a lithium concentrate plant at Grota do Cirilo in Minas Gerais, Brazil, owned 100% through its subsidiary Sigma Mineracao S.A. In October 2021 it signed a binding term sheet with LG Energy Solution for 60,000 tonnes a year, rising to 100,000, though it still had to become a definitive agreement. Workers and equipment reached the site in November 2021, and foundation work began in December with 180 people.

The company paid for construction with equity. A placement at C$11.75 a share began at about C$60 million, was raised to C$85 million and then to C$136.7 million after BlackRock added C$64.2 million. It closed on 23 December 2021 with 11,634,137 shares sold, and the company said this fully funded Phase 1. Shares on issue ended 2021 at 99,377,349.

Through 2022 the studies grew. In May, reserves rose 2.6 times to 34 million tonnes, and Phase 1 was valued at US$1.6 billion after tax. In June the total resource rose about 50% to 85.7 million tonnes. In December an expansion study valued Phases 1 to 3 at US$15.3 billion for US$155 million of capital, and Sigma secured a US$100 million pre-export loan from Synergy Acquisitions Holding. Commissioning began on 20 December.

2023: Licence, first production and a sale process

The environmental operating licence was granted on 31 March 2023 by unanimous vote, sixteen months after mobilisation. First production came on 17 April. Cash fell from C$96.4 million at the end of 2022 to C$67.1 million by early June as the plant was commissioned. The first revenue arrived in May, and 30,000 tonnes shipped in July.

In September the board said it had received proposals for the operating company, the parent and the project, and began a strategic review. Glencore prepaid 50% of a 22,500 tonne cargo, the first of a repeating pattern of prepayments. Courts attached conditions to the transfer of two exploration sub-plots, which Sigma said did not impede expansion. The plant reached a record 890 tonnes a day in October. The sale process reached a final round in November and contractual negotiation with finalists in December, when Sigma also began preparing a separate listing of the Brazilian subsidiary. The record shows no outcome of the sale process.

2024: Expansion funding and a dispute with LG

The plant held its design rate of 270,000 tonnes a year through 2023, and an audited resource rose 27% to 109 million tonnes. Funding turned to debt. BNDES, Brazil's development bank, issued a letter of intention in February. In March Sigma closed US$90 million of trade finance lines, and Glencore prepayments rose to 85%. Also in March, LG Energy Solution began arbitration, alleging breach of the 2021 term sheet. Sigma said the claims had no merit, and no outcome is recorded.

In May reserves rose 40% to 77.0 million tonnes, enough for about 25 years at a planned 520,000 tonnes a year. LX International, formerly LG International, bought a cargo that month. In August BNDES committed a BRL 487 million, sixteen-year loan that fully funded the second plant, and construction began. At its September investor day Sigma set out a plan to roughly triple capacity by the end of 2026. In December a record 27,500 tonne cargo went to IRH of Abu Dhabi, and the Barreiro pit received all its licences together by unanimous approval. Shares on issue rose only to 111,267,279 by year end.

2025: A silent year

The record is almost silent on 2025. Later releases show that mining stopped at some point in the year, but no filing here says when or why.

2026: Restart and legal pressure

In January 2026 Sigma sold 100,000 tonnes of high-purity fines, signed a working capital revolver and began remobilising the mine. Katia Abreu, a former agriculture minister, joined the board. The company denied reports of an operational injunction, saying a labour ministry process concerned its waste piles. Mining restarted on 2 February with more than 600 people on site. On 4 February the mining regulator ANM issued a statement, dated 2 February, finding no evidence of serious risk in the piles and no legal basis for closure. Selling fines, and processing tailings and stockpiles, carried the company through the stoppage. In February it began drawing a US$96 million revolver and guided to 240,000 tonnes a year. In March it resumed selling high-grade concentrate at US$1,712 a tonne, against US$140 a tonne for fines. In April a US$100 million bank guarantee was signed to unlock the BNDES money for the second plant.

On 17 May a local judge ruled against the company, raising a possible US$10 million deposit. The state appeal court overturned this on 9 June. By 22 July 2026, Sigma was negotiating a conduct adjustment agreement with the Minas Gerais government after a notice from the regional office of SUPRAM, while reporting a second-quarter production beat. No equity has been issued since December 2021, and shares on issue stood at 111,402,979 at the end of 2025.

Written from the 54 story beats below (2021 to 22 July 2026), which come from the company's own announcements and filings.

Beat by beat

The events that changed the company's story, in plain English, each written against everything known about the company at the time. The dot shows whether it was good, bad or neutral for shareholders.

shares on issue market cap (log scale)

2026111m shares

  1. 22 July

    Began negotiating a conduct adjustment agreement with the Minas Gerais state government after a notice from the regional office of the state environmental body SUPRAM, while reporting a second-quarter production beat. The state environmental regulator that granted the licences in 2023 and 2024 is now the counterparty in a settlement.

    regulatory community update

    111m sh
  2. 9 June

    The Minas Gerais appeal court overturned the local judge's decision and the US$10 million deposit with it, accepting the year of independent environmental monitoring data. Three weeks from adverse ruling to reversal at state level.

    regulatory community update

    111m sh
  3. 18 May

    A local judge in Aracuai ruled against the company on 17 May, raising the possibility of a US$10 million legal deposit; Sigma appealed and linked the reporting around it to a campaign against the company. The regulatory risk here is local and judicial, not federal.

    regulatory community update

    111m sh
  4. 2 Apr

    Signed a US$100 million bank guarantee with a large Brazilian bank, itself collateralised by customer guarantees, letters of credit and export receivables. The guarantee is what unlocks the development bank money for the second plant, which would take capacity from 270,000 to 520,000 tonnes a year.

    debt financing

    111m sh
  5. 20 Mar

    Resumed selling high-grade concentrate, expecting first-quarter revenue equal to about 28,000 tonnes at US$1,712 a tonne, and closed a first at-plant sale of 400,000 tonnes of fines on which it expects a US$20 million profit. Beneficiating dry-stacked tailings and stockpiles is what carried the company through the mining stoppage.

    production update

    111m sh
  6. 23 Feb

    Guided to 240,000 tonnes a year over the next twelve months and restarted planning for Phase 2 civil works and equipment orders, funded by the fines sales.

    production update

    111m sh
  7. 13 Feb

    Sold 150,000 tonnes of fines at US$140 a tonne delivered to the port warehouse, with an option over another 350,000 tonnes, and began drawing on a US$96 million revolver secured against 70,500 tonnes of concentrate to be delivered during 2026.

    asset acquisition disposition

    111m sh
  8. 4 Feb

    Brazil's mining regulator ANM issued a technical statement, dated February 2, that found no evidence of serious risk in the waste piles and no legal grounds for precautionary closure. The company said this supports its case in the still-open labour ministry enquiry.

    regulatory community update

    111m sh
  9. 2 Feb

    Mining resumed at Mine 1 with over 600 people on site, ending the restructuring. The company said fines sales helped pay for it, and that selling its 950,000t of fines at US$140/t could potentially equal the proceeds of about 70,000t of concentrate.

    production update

    111m sh
  10. 23 Jan

    Sold another 100,000 tonnes of fines at a higher price and said remobilisation would finish in January. It also denied reports of an "operational injunction", saying the matter is an administrative process opened by Brazil's labour ministry about its waste piles.

    asset acquisition disposition

    111m sh
  11. 13 Jan

    Sold 100,000 tonnes of high-purity lithium fines, signed a working capital revolving facility and drew its first tranche, and appointed former agriculture minister Katia Abreu to the board. The release also describes remobilising the mine - mining had stopped at some point in 2025, for reasons no filing in this record explains.

    asset acquisition disposition

    111m sh

2024110m shares

  1. 23 Dec

    The Barreiro mine, the second pit at Grota do Cirilo, received its preliminary, installation and operating licences together and by unanimous approval, covering operations for the sixteen-year term of the BNDES loan. Brazil issued a full mining licence set in a single decision.

    regulatory community update

    110m sh
  2. 3 Dec

    Shipped a record 27,500 tonnes to IRH Global Trading of Abu Dhabi with the plant at full capacity.

    production update

    110m sh
  3. 30 Sept

    At its investor day set out a plan to roughly triple capacity to about 125,000 tonnes a year of lithium carbonate equivalent by the end of 2026, through a second line commissioning in 2025 and a third in 2026.

    investor presentation

    110m sh
  4. 29 Aug

    BNDES turned February's letter of intention into a binding commitment: a BRL 487 million loan over sixteen years that fully funds the second plant. The board took the final investment decision and construction started, targeting completion in mid-2025.

    debt financing

    110m sh
  5. 13 Aug

    Loaded an eleventh 22,000 tonne cargo, completing a full year of monthly shipments, and reported 365 consecutive days without a lost-time accident across 618 employees.

    production update

    110m sh
  6. 22 May

    Sold its ninth 22,000 tonne cargo to LX International, formerly LG International, at 9% of the LME lithium hydroxide price - a sale to an LG group company two months after another LG group company began arbitration against Sigma.

    production update

    110m sh
  7. 8 May

    Raised proven and probable open-pit reserves 40% to 77.0 million tonnes from 54.8 million, enough for about 25 years at the planned 520,000 tonnes a year of concentrate across two processing phases.

    resource reserve update

    110m sh
  8. 28 Mar

    Sold its eighth cargo of 22,000 tonnes at a fixed US$1,333 a tonne including 13% Brazilian tax, US$1,160 net, with 85% prepaid - a final rather than provisional price, set by closed private bidding and equal to about 8.75% of the lithium hydroxide index.

    production update

    110m sh
  9. 20 Mar

    LG Energy Solution began arbitration at the International Centre for Dispute Resolution, alleging Sigma breached the October 2021 offtake term sheet. That term sheet was expressly conditional on negotiating definitive agreements, which never happened; Sigma says the claims have no merit. The flagship customer of 2021 is now a litigant.

    other material event

    110m sh
  10. 8 Mar

    Closed US$90 million of trade finance lines - Citibank US$50 million, Santander US$20 million, Banco do Brasil US$10 million and XP US$10 million - and loaded another 22,000 tonnes to Glencore, this time with 85% prepaid rather than 50%.

    debt financing

    110m sh
  11. 15 Feb

    Brazil's development bank BNDES issued a letter of intention to lend against the second plant, whose construction and engineering cost is put at R$492.4 million, about US$100 million. A state lender funding the expansion is a different kind of backing from the equity and prepayments used so far.

    debt financing

    110m sh
  12. 31 Jan

    Audited resource up 27% to 109 million tonnes: 94.3 million measured and indicated at 1.40% lithium oxide and 14.6 million inferred at 1.37%, against the January 2023 report. Grade held while scale grew, and the company expects to reach 150 million tonnes.

    resource reserve update

    110m sh
  13. 31 Jan

    The plant sustained its design rate of 270,000 tonnes a year through December, completing the first year of production, with another 22,000 tonne Glencore shipment loading.

    production update

    110m sh

2023105m shares

  1. 18 Dec

    The sale process moved into contractual negotiation with finalists and slipped into the new year, and Sigma began preparing a primary listing of the Brazilian subsidiary on Nasdaq and in Singapore so that the Brazilian company could be sold or listed on its own.

    other material event

    105m sh
  2. 3 Nov

    Phase 4 exploration results point to a resource about 25% larger, above 110 million tonnes, with up to 20 million tonnes more identified in a further pegmatite. Framed as potential rather than an estimate at this stage.

    drilling progress report

    105m sh
  3. 1 Nov

    The sale process reached a final round with bidders forming consortiums, and the company said it aimed to conclude by year end and that the remaining parties had agreed in principle to keep its sustainability model.

    other material event

    105m sh
  4. 2 Oct

    Hit a record 890 tonnes a day, an annualised 320,000 tonnes, running at 88% utilisation against an 85% design assumption and at full design throughput, with 2023 guidance of 130,000 tonnes intact.

    production update

    105m sh
  5. 29 Sept

    Denied press reports of an injunction, saying the Brazilian courts had approved the transfer of two exploration sub-plots from RIX to Sigma Brazil subject to conditions, and that these do not impede the Phase 2 and 3 expansion. The first title or permitting friction to appear in this record, and it arrived while the company was in a sale process.

    regulatory community update

    105m sh
  6. 21 Sept

    Finished trucking 22,500 tonnes of Triple Zero Green Lithium to Vitoria Port for shipment to Glencore that week. Under the agreement it was to receive a 50% prepayment before shipment, at a provisional price of 9% of the LME lithium hydroxide price.

    production update

    105m sh
  7. 13 Sept

    The board disclosed that it had received multiple proposals for the Brazilian operating company, for the Canadian parent and for the project itself, from companies in the energy, automotive, battery and lithium refining industries, and had begun a strategic review. Five months after first production the company put itself up for sale.

    other material event

    105m sh
  8. 26 July

    Shipped 30,000 tonnes of concentrate and by-products, and said the first shipment was carbon neutral after offsets, sold at a premium and operationally profitable. First revenue at scale, three months after first production.

    production update

    105m sh
  9. 13 June

    Filed the delayed 2022 accounts. Cash was C$96.4 million at 31 December 2022 and C$67.1 million by 9 June 2023 - a third of the balance gone in five months as the plant was commissioned. The same filing carries an amended and restated technical report.

    annual report

    105m sh
  10. 26 May

    Received its first revenue: a payment under a three-year offtake covering all of its tailings, which run about 1.3% lithium oxide, alongside a spot sale of 15,000 tonnes of concentrate priced at 9% of the lithium hydroxide index. Selling the waste stream as a product is what the company means by zero tailings.

    material agreement

    105m sh
  11. 17 Apr

    First production. The dense media separation circuit was commissioned and Phase 1 construction finished, with the plant running at 75% of nameplate and full capacity expected by July. Sigma went from mobilising to site in November 2021 to producing lithium concentrate in April 2023.

    production update

    105m sh
  12. 11 Apr

    The environmental operating licence was granted on 31 March 2023 by unanimous vote of the Minas Gerais mining chamber, including every NGO member, and issued by the state regulator COPAM - the final step of environmental licensing. Sixteen months from first mobilisation to an operating licence, with no opposition recorded on the vote.

    regulatory community update

    105m sh
  13. 14 Feb

    Finished commissioning the crushing circuit and the water pumping system, stayed on track for April production, and began detailed engineering to expand the plant from 270,000 to 760,000 tonnes a year.

    other

    105m shC$438m
  14. 23 Jan

    Started commissioning the dense media separation module a month early and within budget, with first ore crushed expected in mid-February.

    other

    105m shC$402m
  15. 20 Jan

    Filed the production expansion report. It describes the reserve increase as 60%, where the December release said 63%, and confirms the US$15.3 billion value and US$155 million of expansion capital.

    resource reserve update

    105m shC$402m

202299.4m shares · C$546m market cap

  1. 20 Dec

    Started commissioning the first module of the plant - the crushing circuit - on schedule and within budget, with the dense media separation circuit to follow in February and commercial production still planned for April 2023.

    other

    99.4m shC$546m
  2. 19 Dec

    The debt itself: a US$100 million pre-export financing agreement dated 3 December 2022, borrowed by the Brazilian operating subsidiary Sigma Mineracao S.A., guaranteed by the parent, and lent by Synergy Acquisitions Holding Ltd.

    debt financing

    99.4m shC$546m
  3. 5 Dec

    One filing, three things: reserves up 63%, an expansion study putting Phases 1 to 3 together at an after-tax value of US$15.3 billion for US$155 million of expansion capital, and US$100 million of debt secured. The expansion would take output from 270,000 to 768,000 tonnes a year of concentrate.

    debt financing

    99.4m shC$546m
  4. 18 Nov

    Construction reached 94% of concrete and 76% of steel, with commissioning to start in December 2022 and commercial production planned for April 2023.

    other

    99.4m shC$470m
  5. 13 July

    Construction reached 25% and remained on schedule and budget for commissioning by December 2022, with about 600 people expected on site at peak. The release also reported favourable regulatory progress.

    regulatory community update

    99.4m shC$702m
  6. 22 June

    Raised the total resource about 50% to 85.7 million tonnes from 58.9 million: 73.6 million tonnes measured and indicated at 1.43% lithium oxide and 12.1 million inferred at 1.45%, the increase coming from 27 million tonnes at 1.49% in the Phase 3 area.

    resource reserve update

    99.4m shC$696m
  7. 26 May

    Filed the technical report for the combined Phase 1 and 2 project: after-tax value of US$5.1 billion, average free cash flow of US$595 million a year over thirteen years, 531,000 tonnes a year of concentrate and cash costs of US$454 a tonne delivered to China.

    resource reserve update

    99.4m shC$662m
  8. 3 May

    Reported 2021 annual results and said earthworks for the Phase 1 plant foundations were 100% complete, on schedule and budget, with commissioning planned for the end of 2022. The company said it was fully equity-funded after raising C$137 million in December 2021, and targeted 460,000 tpa from Phases 1 and 2 combined.

    resource reserve update

    99.4m shC$662m

2021

  1. 23 Dec

    Closed the twice-upsized C$136.7 million placement, issuing 11,634,137 shares at C$11.75. The company said the proceeds fully fund construction of the Phase 1 plant and mine and advance Phases 2 and 3, with BlackRock investing C$64.2 million.

    capital raising announcement

  2. 17 Dec

    BlackRock put in a further C$64.2 million, taking the placement to C$136.7 million and 11,634,137 shares - the second upsizing in a week, and the arrival of a large institutional holder.

    capital raising announcement

  3. 13 Dec

    Raised the placement by 42% to C$85 million and 7,234,042 shares at the same C$11.75 price, citing investor demand.

    capital raising announcement

  4. 10 Dec

    Announced a non-brokered placement of about 5,106,383 shares at C$11.75 to raise roughly C$60 million, aimed at ESG-focused institutions.

    capital raising announcement

  5. 6 Dec

    Began foundation and earthworks with 180 workers on site and placed deposits on 38 long-lead items, saying it was on track to produce in the fourth quarter of 2022 and had the equity to meet the conditions of its proposed construction debt facility.

    other

  6. 5 Nov

    Mobilised about 180 contractors and equipment to site for pre-construction earthworks and completed front-end engineering design. It also filed a preliminary base shelf prospectus in Canada and the US to qualify up to US$250 million of debt and equity securities.

    securities registration

  7. 6 Oct

    Signed a binding six-year offtake term sheet with LG Energy Solution: 60,000 tonnes a year of concentrate on a take-or-pay basis from 2023, rising to 100,000 tonnes a year from 2024 to 2027, priced off lithium hydroxide. It was still subject to definitive agreements.

    material agreement