History
Rubicon spun off its other assets to focus on Red Lake, made a rich gold find in 2008, built the Phoenix mine without a reserve, then slashed its resource by about 90% in 2016.
2006-2007: Focusing on Red Lake
In November 2006 Rubicon told shareholders its share price did not reflect a diverse asset base, so it would spin non-core assets out into separately listed companies through a plan of arrangement. The deal closed on 8 December 2006. Shareholders received shares in Africo Resources (Congo copper-cobalt assets) and Paragon Minerals (Newfoundland) alongside their Rubicon shares. That left Rubicon focused on its Red Lake project in Ontario. The record for 2007 is quiet.
2008-2009: The F2 discovery and a rush of funding
In March 2008 Rubicon reported a new gold zone at its Phoenix project, called F2, with intercepts including 283 g/t over 1.0 m. The company later dated the discovery to 27 February 2008. Further results followed in April, among them 42.4 g/t over 11.0 m. In March 2009 it received permits to begin underground advanced exploration, moving from drilling to physical access. It also raised C$40.0m at C$1.60 a share (25,000,000 shares) for exploration and development at Phoenix, and in April the board approved a C$25m, 12-month programme of at least 80,000 m of drilling. In late 2009 it raised C$86.3m at C$4.55 a share (18,975,000 shares), the highest price in its record, before any resource estimate existed. A C$60m Phase II programme for 2010 followed.
2010-2011: Resource estimates and a regulator's challenge
In May 2010 the first underground hole from the 305 m level returned 1.24 oz/ton gold over 22.5 feet. In October, Robert McEwen's entities filed an underwriting agreement to sell 45,714,357 existing shares at C$4.16 through GMP Securities; the shares were not new, so the filing shows no money for Rubicon, and completion was not confirmed. Underground drilling in November found 568.9 g/t over 2.5 m. On 1 December 2010 the first formal resource arrived: an inferred 4,007,000 ounces, with no indicated or measured category and no reserve. In February 2011 the British Columbia Securities Commission reviewed the report, and in March an amended estimate cut it to 3,597,000 inferred ounces, or 3,057,000 with high assays capped.
In June 2011 an AMC preliminary economic assessment declared 477,000 indicated ounces and outlined a 12-year mine costing C$214m to build. AMC warned the grades rested on a small number of high-grade intercepts. In July Agnico-Eagle bought 21,671,827 shares at C$3.23 for C$70.0m, taking 9.2%. In October Rubicon committed to a C$55m programme aimed at a possible start in the fourth quarter of 2013.
2012-2013: Building the mine
In February 2012 Rubicon raised C$200.9m by selling 49.0 million shares at C$4.10. In May it lifted its Phoenix budget to C$82.8m and reported C$235m of working capital. In June Agnico-Eagle said it had sold a significant part of its holding. In December 2012 a legal challenge began from Wabauskang First Nation over the closure plan. In June 2013 SRK produced a rebuilt estimate: 1.129 million indicated ounces and 2.219 million inferred, and a 13-year mine plan. It also disclosed a C$106m funding shortfall. The August report stated that there was no inference of mineral reserves.
2014-2015: Financing and first gold
Shaft sinking finished in December 2013 at 730 m. In February 2014 Rubicon signed a US$75.0m gold stream with a Royal Gold subsidiary, though about US$100m more financing was still needed. It also sold units at C$1.55, closing at C$115.1m with 74.29 million units, well below the 2012 price. The Wabauskang dispute ended in a settlement in November 2014. In May 2015 it borrowed US$50.0m from CPPIB at 7.5%, its first debt. First gold, about 741 ounces, was announced on 24 June 2015. In October Ontario's environment ministry ordered the mill shut over ammonia in the tailings water. In November underground work was suspended after interim CEO Michael Winship said the deposit was much more geologically complex than the historical drilling suggested.
2016: Write-down and unresolved debt
On 11 January 2016 SRK's rebuilt model cut indicated resources 91% to 106,000 ounces and inferred 86% to 307,000 ounces, and Rubicon said the 2013 study was no longer correct. Phoenix had produced 4,906 ounces in 2015 against a plan of 165,300 ounces a year. The board hired BMO and TD Securities to look at a sale, merger or restructuring. NYSE suspended trading on 11 January. On 12 February Rubicon missed a CPPIB loan covenant on mill throughput, though CPPIB said it supported the review and had no current intention to enforce. On 19 February it filed to end its US registration, keeping its TSX listing and OTC Pink quotation. As of that date the default and the strategic review were unresolved.
Written from the 44 story beats below (2006 to 19 Feb 2016), which come from the company's own announcements and filings.