Each one in plain English, with the numbers worked through for a shareholder.
19 Nov 2020material agreement▲ Good
At the SA Investment Conference, Renergen announced a cold-chain LNG trailer concept with Henred Fruehauf, claiming up to 23% fuel bill savings. It also said the Total LNG tie-up will extend to the N1 Johannesburg–Cape Town route in 2021.
Mazars' independent review report on the interim financials lodged 20 October, dated 16 October 2020. It gives an unmodified conclusion. No new information.
P2V2 has drilled through the base of the Karoo and is being logged. A gaseous odour was found on re-entering old well MDR1, where no gas was recorded originally. The CEO says it is encouraging but not a strike.
Replacement well P2V2 has set intermediate casing and is expected at or near target by the end of the first week of November. A second directional rig will start on 30 October re-entering old well MDR1, saving time and cost.
Reviewed interim results to 31 August 2020: revenue down 36% to R0.9m, with no Tetra4 revenue in April and May. Property, plant and equipment rose to R420.5m with plant construction. The second DFC draw of US$12.5m (R216.3m) is noted.
Half-year to 31 August 2020: revenue fell to R910k from R1.44m, blamed on COVID-19 lockdown. Net loss narrowed to R26.9m from R40.0m. Net tangible assets fell to 102.55 cents per share. Mazars gave an unmodified review conclusion.
JSE trading statement: half-year loss per share is expected at 19.38 to 26.42 cents, down 25% to 45% from 35.24 cents a year earlier. The prior year included once-off costs for the DFC loan and ASX IPO. Figures are unreviewed.
Renergen signed an LNG supply agreement with Logico Logistics, a transport company, to supply LNG at Total filling stations on the N3 Johannesburg–Durban route. No volumes or values are given. It adds to the offtake customers.
Quarterly report to September 2020: first inclined well abandoned, replacement well spudded, three more wells designed. LNG auction registrations beat expectations. Next milestone, plant batch 1 FOB due 1 November, is likely to run behind schedule because of COVID-19.
Appendix 5B for the quarter to 31 August 2020: cash rose to R250.7m from R82.5m, helped by R216.3m of loan proceeds (the second DFC tranche). Operating outflow was R9.0m and investing outflow R21.8m.
The first inclined well was abandoned after the bottom hole assembly was lost in a drill string rupture before reaching the base of the Karoo. It was drilled turnkey, so no cost to Renergen. A new rotary directional rig and an old cased well are now planned.
Registrations for South Africa's first LNG auction closed 28 August and 'significantly exceeded expectations', with no count given. Bids are due by end October after information sharing, so no prices or volumes are known yet.
The drill rig is preparing to spud the first well of the inclined programme at Virginia, which was delayed from earlier timing. Results are about a month away, when the well reaches the base of the Karoo. No result yet.
Plant design completed 22 days ahead of schedule, the fourth Phase 1 milestone, compared with the 18 August target in the quarterly report. The company still targets production in 2021. The release is dated 28 June, though lodged 29 July.
Renergen launches South Africa's first LNG auction, inviting parties to bid for allocation of Virginia-produced LNG. It restates Phase 1 production in 2021 and Phase 2 by 2023. No bid results or prices are given.
First inclined well is delayed by COVID-19 restrictions: drill site access was given 2 July, spud expected late July, and target reached late August. The CEO says the focus is a successful well over a fast one.
Sproule estimates undiscovered prospective helium resources at the Virginia project of 32.5 / 106.3 / 344.2 Bcf (low / best / high), un-risked. These are new and sit alongside the earlier 6.8 Bcf reserves and 20.9 Bcf contingent resources; they carry significant exploration risk.
Notice that the annual broad-based black economic empowerment compliance reports for Renergen and Tetra4 are published on the website. Administrative only.
Appendix 4G corporate governance disclosure for the year to February 2020, pointing to the governance statement on the company website. Administrative, with no new business information.
Appendix 5B for the quarter to 31 May 2020: cash fell to R82.5m from R141.0m, with R55.2m of investing outflows. Operating outflow was R4.3m. Loan facilities total R700.7m, with R350.3m drawn.
Second US$12.5m tranche of the US development finance loan drawn on 15 June. Inclined-well spud is expected within days, slightly behind schedule. Total LNG marketing deal noted; next milestone, plant design, expected 18 August.
Renergen signed a joint LNG marketing and distribution agreement with Total South Africa, selling through Total service stations, starting on the N3 Johannesburg–Durban route. The plant is expected to turn on around Q3 2021, a little later than the earlier mid-2021 target.
Lodgement of the 2020 Integrated Annual Report for the year to 29 February 2020, with notes that Australian takeover rules do not apply and South African law limits share acquisitions. The cover note adds no new results beyond the preliminary report.