Each one in plain English, with the numbers worked through for a shareholder.
30 May 2008investor presentation● Neutral
AGM presentation says the surface plant is 50% complete and regulatory approval remains the bottleneck. Of 16 gas bid packs issued, 11 non-binding bids came in and four bidders are shortlisted, with binding contracts targeted July/August. This is later than the earlier June target for contracts.
The chairman says the hoped-for May (Sillaro) and July (Castello) approval dates have slipped. Final approvals are now targeted for late September, and plant installation is delayed towards the end of Q1 2009. Surface plant is about 50% complete. Doug Colkin was appointed COO in March.
The 2007 annual report restates known progress: Sillaro and Castello preliminary concessions and environmental clearances, surface plant 38% complete, a A$7.88m placement and a €25m bank facility. Bezzecca 1, Fantuzza 1 and Sillaro 2 drilling is planned. No new figures.
ANZ's daily update as at 15 April showed an interest in 8,061,961 Po Valley shares (8.917%), unchanged from the previous day. ANZ noted the figures may include shares sold but not yet settled; there was no company news.
ANZ says its Opes Prime-related holdings were unchanged at 11 April close, and corrects the Citadel Resources share count. Nothing specific to Po Valley.
ANZ's daily update on Opes Prime-related holdings as at 9 April. Po Valley shown at 8,061,961 shares (8.917%), little changed. Administrative, no company news.
ANZ's daily update on Opes Prime-related holdings, as at 8 April. The Po Valley figure is not readable in the extracted text. Administrative, no company news.
ANZ's daily update on its Opes Prime-related shareholdings. Po Valley is listed with ANZ holding 8,070,872 shares (8.926%) at 7 April 2008. Administrative disclosure, no company news.
ANZ disclosed it holds shares in many ASX companies via Opes Prime lending arrangements and has started selling them. The schedule includes Po Valley; its figure is not shown in the readable text. Follows the director margin loan disclosure.
Director Byron Pirola disclosed a margin loan of about $2m with Opes Prime, with about 7.8m company shares pledged. No margin call has been made and he says he can repay immediately. The company is monitoring.
31 Mar 2008regulatory community update● NeutralMajor
Castello received its Lombardia environmental approval, following Sillaro's in January. But first gas is now targeted for about December 2008 (Sillaro) and two months later for Castello, possibly two months more after the April election. Management says regulatory slowness delayed production by up to a year.
March 2008 presentation recaps known items: Edison Ossola 50/50 deal, Sillaro and Castello plant 30% complete, A$34m Bank of Scotland facility, gas storage JV. Cites Sillaro 1P reserves 10.4 bcf and ~A$38m annual revenue at full rate. Mostly repeats earlier news.
Statutory accounts for 2007: loss per share was 3.12 cents (2006: 3.41 cents). Directors' report lists the board unchanged since Greil's May resignation. Remaining content truncated; nothing new on operations.
Po Valley and Edison settle the Ossola dispute: Ossola will be a 50:50 JV, subject to final licence grant, with Po Valley operating until the first well. Edison's 50% in Sant'Alberto and San Vincenzo converts to a 3.75% royalty, giving Po Valley 100%.
Po Valley completed its €25m facility with Bank of Scotland: €5m is available now, and up to €20m more after production concessions are formally granted, now expected in the June quarter (slipped from March). Completes the facility announced in December.
Sillaro received its environmental decree from the Emilia Romagna region, one of the last steps before the production concession. Castello's decree is expected soon. Surface plant is over 20% complete. Company says first revenue is expected this year.
Shareholder letter with a company brochure, recapping the rig and surface plant contracts, preliminary concession award, new applications and the Bank of Scotland facility. No new information.
Bank of Scotland Corporate will provide up to A$34m (€20m) of finance: A$8m initially, the rest once the production concession is formally granted. It is Po Valley's first debt and funds plant construction and 2008 wells. Final approvals expected March 2008.
The Ministry confirmed Po Valley's application for a 526 km2 licence in the northern Adriatic, its first offshore bid, covering three gas targets drilled by ENI. Recoverable reserves are expected around 45 bcf. One competing application exists; decision at next Commission.
The Ministry formally gave preliminary award of production concessions for Sillaro and Castello, resolving the long-awaited April Commission outcome. Full grant still needs environmental decrees, expected in November. Company's timetable shows final award around January 2008.
The Italian Ministry confirmed acceptance of the Po Valley and Star Energy gas storage bid lodged in September. It is a competitive tender, with a decision scheduled for January 2008. Continues the storage thread opened in June.
Po Valley awarded SEMAT Spa a A$9.6m contract to build and install surface plant for Castello and Sillaro. Equipment is due on site May 2008, with first gas targeted early in Q3 2008. Castello is expected first, Sillaro after Sillaro 2 is drilled. Resolves the pending surface plant award.