19 Apr 2017drilling progress report▲ Good
The Ophir wellhead platform has been installed in the field, with drilling conductors driven 80m below the seabed. It is now ready for the NAGA 2 rig, due shortly, to drill three horizontal production wells ahead of 2H 2017 first oil.
The regulators have declared their earlier refusal of Ascalon retention leases null and void, because Octanex was not told of the recommendation to reject or given a chance to respond. Applications will be re-assessed; reverses the 10 March setback, though outcome is open.
The Ophir wellhead platform (350-tonne topsides on a tri-legged jacket) has been loaded onto barges at Port Klang and will be towed to the field for installation. Follows the platform fabrication flagged earlier; a step toward drilling and 2H 2017 first oil.
Regulators advised they are not prepared to grant retention leases for Ascalon (3.2 TCF P50 contingent gas), saying it is unlikely to become commercially viable within 15 years. This contradicts the application pending since early 2016. Octanex is seeking clarification.
Half-year loss to 31 December 2016 was $1,439,107, versus $1,172,430 a year earlier. Strategy unchanged: Ophir first oil in 2H 2017, platform complete awaiting Q2 installation. Text truncated.
FPSO secured for Ophir: MTC Engineering is converting the tanker Puteri Bangsa into the MTC Ledang FPSO, with 350,000 barrels storage, on a three-year term plus one-year option. Completes the rig and FPSO contracts flagged earlier, a step toward 2H 2017 first oil.
December quarter report: cash $6.1M and debt US$4M; shares on issue 272M after capital modification completed. Ophir platform near-complete with drilling due Q2 2017; NAGA 2 rig contract executed; FPSO procurement continuing. Ascalon lease application still in process. Text truncated.
Following shareholder approval, the change from no liability to limited liability status took effect, and the company is now Octanex Limited. ASX code OXX unchanged.
Updated Ophir presentation: first oil still 2H 2017, with most-likely production now 6.7M barrels from three wells over about three years, versus 5.2M in the approved plan. Wellhead platform complete; capex USD90M. Funding stated as fully funded.
Director interest notices after the AGM. Willis received 1,250,000 unlisted options (expiring 24/11/2019) on 19 December, approved at the AGM, with ordinary shares unchanged at 3,117,382. Further notices for other directors, including Clark, are truncated.
Director interest notices for Chairman Albers and associates: partly paid shares converted to fully paid on 14 December under the approved consolidation. His fully paid holding rises from 122,005,841 to 148,788,259. No cash trade.
ASX suspends the partly paid shares (OXXCB) from close of trade on 5 December 2016 ahead of their consolidation into fully paid shares. Other securities are unaffected. Procedural step in the announced capital change.
30 Nov 2016security holder rights change● NeutralMajor
Timetable for cancelling the unpaid 10c per share on the 67,078,910 partly paid shares and consolidating them into fully paid shares at 3 for 5, effective 12 December 2016. Change to limited liability status is estimated for 25 January 2017.
All resolutions were passed on a show of hands at the 2016 AGM. Resolution 13 (reduction and consolidation) drew only 800 votes against, with most votes abstained or invalid because partly paid holders were involved. Several resolutions still needed written approval from SIP.
AGM address: Ophir first production still expected 2H 2017, platform nearly complete, rig and platform contracts below budget. Proposes converting to a limited-liability company, cancelling uncalled capital on partly paid shares and consolidating 3 for 5. Directors forgo fees; SIP extended convertible note dates.
Ophir joint venture awarded the jack-up drilling rig contract to UMW Offshore Drilling; the NAGA 2 rig mobilises in Q2 2017 to drill three production wells. This delivers one of the rig contracts expected in earlier reports; the COO says it locks in significant cost savings.
September quarter report: Ophir platform fabrication is 85% complete, with drilling rig and FPSO contract awards described as imminent. Cash fell to $2.6M from $3.1M. The Ascalon retention lease application remains under assessment. 2D seismic reprocessing began on WA-362-P/363-P.
Appendix 4G corporate governance checklist for the year to 30 June 2016, lodged by Rae Clark on 7 October 2016. Administrative, no new business information.
2016 annual report. The chairman says Ophir production is expected in the second half of 2017 and rig and platform contracts came in below budget. Cornea economics shifted negatively at current oil prices; the PEP51906 permit was exited. Text truncated.
Link Market Services, Octanex's share registry, changes its Melbourne address to Tower 4, 727 Collins Street, Docklands from 12 September 2016. Administrative, no business content.
June quarter report: Ophir first oil deferred to second half of 2017 (from late 2016), reportedly to avoid monsoon risk and chase higher oil prices. Cash $3.1M. Cornea economics studied at current oil prices. Text truncated.
March quarter report: cash $4.5M. Ophir platform construction began and the Ascalon retention lease application was lodged. Cornea Year-2 work continued, with a production test well now described as Year-4. Text truncated.
First steel cutting ceremony in late February marked the start of Ophir wellhead platform construction at Muhibbah's Klang yard. Octanex's share is stated as fully funded. Construction under way, as planned.
Half-year loss to 31 December 2015 was $1,172,430, versus $4,066,853 a year earlier. Strategy unchanged: Ophir development, two appraisal assets, five exploration permits. Text truncated.
Director Guglielmo's entity bought 3,000,000 shares at $0.10 each (about $300,000) via the trustee share scheme, a premium to market. This adds cash to Octanex.
December quarter report: cash $4.5M (down from $6.3M). Ophir wellhead platform contract awarded and Ascalon location extended; Octanex now lists five exploration permits. Ascalon P50 contingent gas remains 3 TCF, too small for standalone LNG. Text truncated.
A company associated with chairman Albers paid $720,000 to fully pay 7.2M partly paid shares (10c each). Partly paid shares fall to 67,078,910; fully paid rise to 232,465,561. No call before Ophir first oil or 31 Dec 2018.
Ophir's joint venture awarded the wellhead platform contract to Muhibbah Engineering, with installation in Q3 2016 and oil production in late 2016. Octanex's share is stated as fully funded. A concrete step toward first oil at Ophir.
Chairman's AGM address restates that Ophir is fully funded and the cornerstone of the new strategy, with Cornea and Ascalon as appraisal assets. It notes costs held to a bare minimum, unfavourable acreage surrendered, and directors reinvesting fees in shares at $0.10. Nothing new.