7 June 2018material agreement termination▼ BadMajor
OPSB has terminated the Ophir risk service contract after 'economic cut-off', ending the project. PETRONAS is to take over the field and reimburse unreimbursed costs; Octanex expects this to take about 12 months. SIP note remains repayable from those proceeds.
Ophir wells are to be suspended with PETRONAS approval, and OPSB has asked PETRONAS to terminate the risk service contract. Octanex must still redeem the SIP convertible note from OPSB payments unless SIP converts. The field life was unexpectedly short.
Nitrogen lifting failed to restart Ophir production. OPSB is discussing next steps for the field with PETRONAS. This is a setback to the field that first produced in October 2017.
Half-year to 31 Dec 2017: loss of $8,552,704 versus $1,439,107 a year earlier. Post-drill studies indicate lower-than-expected Ophir oil production, and OPSB is discussing forward strategies with PETRONAS. Production remains shut in.
Wireline surveys confirmed the Ophir wells are mechanically sound and free of obstruction. Nitrogen equipment will be mobilised to try to restart production after the January shut-in. No restart yet.
11 Jan 2018asset acquisition disposition▼ BadMajor
Octanex will withdraw from permits WA-362-P and WA-363-P after Eni, which had carried it, announced its own withdrawal. Octanex cited the cost of the year-4 seismic obligation and uncertainty of finding a new partner. Closes the Eni-carried interests (33.33%).
Ophir is in a non-routine shutdown after an FPSO power trip. Restart has not yet succeeded and troubleshooting is under way. This interrupts the production that began in October 2017, with no restart date given.
Joint Company Secretary Jack Tuohy resigned with immediate effect. Rob Wright, the existing Company Secretary, continues all duties. Administrative change.
Chairman's AGM address: Ophir production began last month but has met challenges, including higher-than-predicted gas constraining oil output. Cornea JV seeks lease variation for a simpler development; Ascalon studies continue; Santos lodged Winchester Location application. Largely repeats known facts.
Ophir achieved contractual 'First Oil', with production starting 20 October 2017, capped at 3,000 bopd while de-bottlenecking continues. First crude lifting expected in December 2017. This delivers the milestone on the Ophir 2H 2017 first-oil timetable.
Ophir facilities are commissioned and hydrocarbons are being received, processed and stored on the FPSO, with performance tests under way. Next milestone is contractual 'First Oil', defined as 20 days of production out of 25.
The MTC Ledang FPSO is in final position at Ophir with moorings attached, and the flowline to the platform is installed and tested. Commissioning has begun. Exploration permits are now described as four, down from five.
Appendix 4G corporate governance statement lodged with the annual report, pointing to the company website. Administrative filing with no new substance.
FY2017 annual report: Ophir wells were completed ahead of time and under budget against the US$90M budget, with production about to start. Ascalon retention applications withdrawn; Cornea JV seeking to vary lease conditions toward a production test well.
The converted MTCE Ledang FPSO has sailed from Singapore for the Ophir field, where it will be moored and connected to the platform. Capacity is stated as 300,000 barrels of storage, versus 350,000 previously reported. First oil remains the next step.
Octanex withdrew its March 2016 Ascalon retention lease applications after NOPTA advised the technical uncertainties should be addressed under exploration permits. It has started independent studies on resources and well deliverability. Both permits are in their term ending May 2018.
Octanex changed its share registry provider from Link Market Services to Automic on 14 August 2017. Administrative notice only, with new contact details for shareholders.
The Ophir three-well drilling campaign is finished, which the company says was ahead of time and under budget, and the Naga-2 rig is being released. No further drilling updates are expected. Wells are shut in awaiting FPSO tie-in.
Ophir A2 and A3 were flowed to clean up drilling fluids and shut in for FPSO tie-in, so all wells are now cleaned up. The Naga-2 rig will be demobilised next.
Ophir A3 reached 3,332m with over 1,100m horizontal in the J20 oil reservoir, and completion and tree are installed. A1 was flowed back to clean up fluids before being shut in for FPSO tie-in. All three wells are now drilled.
A3's upper section was drilled to 2,227m, landing at the top of the target J20 reservoir; the horizontal section is now drilling. Completion is expected next week.
The Ophir A1 side-track reached 3,275m with over 1,280m of horizontal section in the J20 oil reservoir, and completion was being run, with A3 to follow. The company's footer now notes the US$12M convertible note facility is drawn to US$8M.
A2 is completed with its wellhead tree installed. On A1, oil was found in the target reservoir but the team chose to drill a side-track (A1ST) to improve alignment and trajectory.
Ophir A1 reached 1,996m with intermediate casing set, and A2 reached 1,873m; both met the reservoir sequence within 1m of prediction. A2's horizontal section is next.
Ophir A1 and A2 were each drilled to 554m and surface casing set; the rig is now installing blow-out preventers on A1. Next step is drilling A1 toward the target reservoir at 1,983m. No results yet.
Ophir A1, the first of three horizontal production wells, was spud on 2 June 2017 using the NAGA 2 rig. Target reservoirs are already proven oil-bearing, so this is development drilling, not exploration, toward 2H 2017 first oil.
The partly paid shares (OXXCB) were removed from ASX quotation at close of trade on 1 June 2017, following the consolidation into fully paid shares. Final procedural step; other securities unaffected.