History
NexGen turned its Arrow uranium discovery into a feasibility-studied project, won provincial approval, funded itself through rising-price raisings, and found a promising new zone 3.5 km away.
2017-2018: Proving up Arrow
When the record begins in July 2017, NexGen Energy already held the Arrow uranium deposit in Saskatchewan's Athabasca Basin, found in 2014 with hole RK-14-21. The standing estimate was 179.5 million pounds of uranium oxide (U3O8) in the "indicated" confidence category. Winter drilling returned strong results, and a step-out hole cut 13.5 m at 9.58% U3O8, forty metres outside the resource boundary. The company then began a 25,000 m summer program.
In July 2017 NexGen closed a US$110 million financing with CEF Holdings. US$50 million bought shares at C$2.70, and US$60 million was five-year 7.5% convertible debentures (loans that can turn into shares). CEF's chairman, Warren Gilman, joined the board. Days later came the first economic study, which put the after-tax net present value at C$3.49 billion on C$1.19 billion of upfront capital, at US$50 a pound uranium. The summer program also found a new zone of off-scale radioactivity about 400 metres south of Arrow, called South Arrow.
In January 2018 South Arrow proved to be a real zone, with shallow, stacked intercepts outside the Arrow resource. Other holes pushed mineralisation beyond the resource boundary, one with 13.0 m at 20.74%. In November 2018 a prefeasibility study came with an update that lifted indicated resources 43% to 256.6 million pounds. It used indicated material only, so mine life fell from 15 years to 9, while it showed an after-tax value of C$3.7 billion on C$1.25 billion of capital. A 125,000 m program, the largest in the company's history, was launched to reach feasibility.
2019-2021: Feasibility and a change of fortune
The feasibility drilling began in January 2019, with tighter spacing so indicated resources could be reclassified as "measured", the highest confidence category. By August, Phase I had drilled 117 holes for 50,968 m on the resource. Three batches of assays followed, including 12.0 m at 33.78% and 8.0 m at 32.88%. Each hole sat close to an earlier one with similar grades, which was the point: proving continuity rather than finding more.
In April 2019 Canadian and Saskatchewan regulators accepted NexGen's Project Description for the Rook I project, starting a joint environmental assessment, and the company filed an initial licence application with the Canadian Nuclear Safety Commission (CNSC).
Financing was harder in 2020. In May, Queen's Road Capital put in US$30 million on the same structure as CEF's, but shares were priced at C$1.80, a third below 2017, and cash stood at about C$78 million.
The February 2021 feasibility study declared the company's first reserves: 239.6 million pounds probable. It also showed 209.6 million pounds measured, the payoff from the conversion drilling. After-tax value was C$3.47 billion on C$1.3 billion of capital, with a 10.7-year life. Seventeen days later NexGen closed a C$150 million bought deal at C$4.50 a share, 33.4 million shares through a nine-bank syndicate.
2022-2023: Permitting
The story shifted from drilling to approvals. In June 2022 NexGen submitted its draft Environmental Impact Statement. It carried support letters from three Dene Nations that had signed Benefit Agreements. Federal and provincial comments arrived in late 2022, and the company said it had started detailed engineering.
In January 2023 it set up a C$250 million at-the-market program, which lets a company sell shares into the market when it chooses. In December it was doubled to C$500 million and extended to January 2026.
The revised provincial statement, due in the first quarter of 2023, was filed in July, later than planned; the filing gave no reason. On 9 November 2023 NexGen received Saskatchewan Ministerial approval, which the company said was the first full provincial approval for a Saskatchewan uranium project in over 20 years. Federal approval and the CNSC licence were still outstanding, and no financing for the C$1.3 billion build was mentioned.
2024-2025: A second discovery
In March 2024 hole RK-24-183 found mineralisation 3.5 km east of Arrow at Patterson Corridor East, with peaks above 61,000 counts per second. In April NexGen placed C$224 million of shares into Australia at C$11.11, 20,161,290 shares, as ASX depositary interests. It closed on 14 May and was aimed at deepening the ASX listing's liquidity rather than a specific project cost.
On the federal side, NexGen answered the last 49 of the CNSC's 274 technical comments on 21 May and filed a revised federal statement. The completeness check ended on 21 June, and a 60-day technical review began. As of 24 June 2024 no federal approval had been granted, and the filing mentioned no construction financing. The company said it was ready to start major construction once the remaining approvals came.
Exploration continued. By November 2024, 34,000 m had been drilled at Patterson Corridor East, 19 of 30 holes were mineralised, and the zone covered 600 m along strike and 600 m vertically. A 43,000 m program began in January 2025. In March, RK-25-232 cut 3.9 m above 61,000 counts per second, which the company called its best discovery-phase hole at any property, Arrow included. Shares on issue stood at 569.1 million at the end of 2024.
Written from the 31 story beats below (2017 to 24 Mar 2025), which come from the company's own announcements and filings.