8 Jan 2008drilling progress report▼ Bad
Kiliwani-1 at 1,977m, with progress slower than expected after several rig shutdowns for mud pump and generator problems. Echoes the rig's earlier mechanical troubles but no result yet.
Past year: ▼ 19%(5.10c – 10.0c AUD)
Each one in plain English, with the numbers worked through for a shareholder.
8 Jan 2008drilling progress report▼ Bad
Kiliwani-1 at 1,977m, with progress slower than expected after several rig shutdowns for mud pump and generator problems. Echoes the rig's earlier mechanical troubles but no result yet.
4 Jan 2008drilling progress report● Neutral
Bounty reports Kiliwani-1 at 1,892m, drilling ahead. Plan is to set 9⅝-inch casing near 1,900m, with the main target around 2,340m. Routine update.
24 Dec 2007drilling progress report● Neutral
Bounty reports Kiliwani-1 drilling ahead at 1,509m after cementing casing at 1,315m. Routine update, no result.
18 Dec 2007drilling progress report● Neutral
13⅜-inch casing set at 1,322m on Kiliwani-1; the blow-out preventer is being installed. Drilling continues to about 2,285m next. Routine update.
17 Dec 2007drilling progress report● Neutral
Bounty reports Kiliwani-1 running 13⅜-inch casing at 1,322m, hole condition good. Main target around 2,340m. Routine update.
11 Dec 2007drilling progress report● Neutral
Kiliwani-1 still at 1,322m, opening the pilot hole and preparing to run 13⅜-inch casing, with mud pump maintenance. Routine update.
7 Dec 2007drilling progress report● Neutral
Key relays an Aminex statement that, contrary to reports, Kiliwani-1 has not encountered any significant hydrocarbon shows so far. It contradicts Bounty's 5 December 'encouraging gas shows' claim; Aminex says it is far too early to judge.
5 Dec 2007drilling progress report▲ Good
Bounty reports encouraging gas shows at 1,163-1,241m in Kiliwani-1, suggesting hydrocarbons in the structure. The main target is around 2,340m. This was later disputed by the operator.
4 Dec 2007drilling progress report● Neutral
Kiliwani-1 at 1,322m, preparing to run in with a 17½-inch hole opener. Routine update with no result.
27 Nov 2007drilling progress report● Neutral
Kiliwani-1 at 340m, making up the 17½-inch drilling assembly. Routine update, no result.
23 Nov 2007drilling progress report● Neutral
Bounty reports Kiliwani-1 reached the 340m surface casing point and is preparing to run 20-inch casing. Routine progress, no result.
20 Nov 2007drilling progress report● Neutral
Kiliwani-1 at 318m, rigging up to run 20-inch casing. Routine early-stage drilling update with no result.
19 Nov 2007drilling spud● Neutral
Partner Bounty re-announces the 15 November Kiliwani-1 spud, planned depth 2,548m. It cites a potential 100 bcf recoverable (Bounty's own target figure), unlike Key's 250 BCF unrisked estimate. No new Key information.
16 Nov 2007drilling spud▲ GoodMajor
Kiliwani-1 spudded on 15 November 2007, ending the rig delays that began in June. It is a directional well to about 2,500m testing the Songo Songo gas reservoir, about 40 days to drill. Key holds 20%.
6 Nov 2007drilling scheduled● Neutral
Partner Bounty reports the operator took delivery of the Caroil-6 rig on 2 November. Kiliwani-1 targets Lower Cretaceous sandstone at 2,500m depth, with 2-3 weeks of rig-up expected. Repeats Key's own news.
5 Nov 2007drilling scheduled▲ Good
Caroil #6 rig has been transferred to the Nyuni joint venture, ending the months-long delay. Kiliwani-1 is expected to start in about 12 days and take 45 days. Kiliwani North-1 targets a shallower oil play interpreted at 10 million barrels recoverable.
8 Aug 2007drilling scheduled● Neutral
Aminex now expects Caroil-6 delivered to the Nyuni partners in late September, with Kiliwani-1 spudding in the first half of October 2007. The delay since June continues but an end is in sight.
3 Aug 2007drilling result▲ GoodMajor
Operator Tullow reports oil encountered in the first two shallow (about 500m) Uitkijk wells in Suriname. Commercial viability is unproven and needs further drilling and possibly testing; Key's 1.75% interest is free-carried.
26 July 2007drilling spud▲ GoodMajor
Drilling began on 23 July in a 10-well programme in Suriname's Uitkijk permit with Tullow Oil. Key holds a 1.75% free-carried interest in Uitkijk and Coronie, carried for up to 25 wells or US$8.5 million.
19 June 2007drilling scheduled▼ Bad
The Caroil-6 rig will not be handed to the Nyuni joint venture in June because of mechanical repairs, a delay of several weeks. Key's first Tanzanian well is pushed back; management called it disappointing.
31 May 2007farm in farm out completion▲ Good
Tanzanian authorities approved Aminex's 25% farm-out of the Nyuni licence to RAK Gas, which pays 37.5% of two wells' cost. Key stays at 20% and gains a larger partner.
22 May 2007drilling scheduled▲ Good
First Tanzanian well, Kiliwani #1 in the Nyuni permit, is scheduled for about mid-June 2007, taking roughly 40 days. Aminex farmed out 25% to Rakgass; Key's interest stays at 20%.