Finder Resources listed in 2022 as a UK and Australian explorer, then, after a dry first well, became a Timor-Leste developer with a approved field plan and FID targeted.
2022-2023: Listing and a dry first well
Finder Energy Holdings was admitted to the ASX on 6 April 2022, with trading starting on 8 April. Its IPO raised $15 million by issuing 75 million shares at $0.20, giving a base of 157.5 million shares. The pitch centred on Kanga-1 in WA-412-P, where Finder held 15% and its cost was capped at US$0.94 million. The prospect carried a Best Case estimate of 170 million barrels gross.
The well reached 3,400 metres on 27 May 2022 and found no commercial hydrocarbons. It was plugged and abandoned, ending the prospect Finder had promoted at listing. The loss stayed at the capped amount, and the company said it remained fully funded and would pursue farm-outs, where partners pay to join a project.
Finder then built a UK North Sea portfolio. In April 2022 it agreed to acquire licence P2527 from Talon Energy. In November 2022 it farmed out 40% of P2527, P2528 and P2530 to Dana Petroleum, keeping 60% and operatorship, for £1.3 million plus Dana's share of work costs, which extended its cash runway by over 12 months. It also reported a maiden estimate for P2524, where it held 40%. In March 2023 it agreed to buy Fugro's 50% of the AC/P 61 permit, taking it to 100%, in return for a 1.5% royalty. In June 2023 reprocessed seismic on P2530 identified the Wagtail oil discovery (19 million barrels gross) and two prospects.
2023-2024: Building the UK and Australian portfolio
The late 2023 record is mostly about acquiring and describing acreage. Finder won a priority licence with Equinor in the UK 33rd Licensing Round, holding the Boaz gas and condensate prospect, and in May 2024 won two more licences. In December 2023 it booked a Whitsun estimate of 150 million barrels gross in P2528 and released Boaz estimates, saying total UK prospective resources had grown four-fold that month. In February 2024 WA-547-P received a three-year suspension, extending its term to 4 January 2027. Finder was seeking partners to fund drilling on several of these, but the record shows no drilling in this period.
2024-2025: The Timor-Leste pivot
In August 2024 Finder agreed to buy a 76% interest and operatorship of PSC 19-11 offshore Timor-Leste from Eni and Inpex, for US$2 million upfront, up to US$6.5 million more on a final investment decision (FID, the formal go-ahead to build), and a 5% royalty. The field held 45 million barrels gross of contingent oil, and management described the move as a shift from explorer toward developer. The deal completed on 29 August 2024, with TIMOR GAP holding the rest.
To fund it, Finder launched a 1-for-1.26 entitlement offer at $0.048 a share, aiming for about $6 million. Longreach committed to its full share, and take-up was about 65%. In September the shortfall was placed with institutions, bringing the total to about $6 million. In November 2024 Finder dropped its WA-542-P option, removing a $9.25 million work-program liability, and the Whitsun permit P2528 was set to expire without a well.
In June 2025 ASX suspended the shares for several days after an announcement could not be released in a proper form. It was resolved when Finder signed a development alliance with SLB to bring drilling and subsea design forward. A July 2025 placement raised $6.0 million at $0.065, taking Longreach to 51.1% and shares to 376 million.
In September 2025 TIMOR GAP agreed to lift its interest to 34% and fund half of development costs from FID, up to a gross US$338 million; this completed on 21 October. In October an independent review lifted the Kuda Tasi and Jahal 2C estimate by 14% to 25.5 million barrels gross.
2025-2026: Funding the development
In November 2025 Finder farmed 40% of P2530 out to Serica, keeping 20% and operatorship. In December it bought the Petrojarl I floating production vessel from Amplus for US$15 million, paid as US$6 million cash plus 37.2 million shares at $0.37, and raised A$25 million at $0.37. The purchase completed on 15 December.
Engineering design was completed in February 2026, and in March the regulator approved a Development Area of about 88 square kilometres. In April a bridging agreement with SLB, with the TIMOR GAP farmin amended, funded up to US$20 million of early equipment purchases, split 50/50. Finder raised A$27 million at $0.50, which was completed in two tranches by 18 June. A share purchase plan raised nothing. First oil moved to late 2027 or early 2028.
The regulator approved the field development plan on 9 July 2026, for three subsea wells tied to Petrojarl I. On 20 August a RISC report booked maiden 2P reserves, the more certain category, of 22.2 million barrels gross, with Finder's net share 14.4 million. At that date Finder had about 554 million shares, cash of $32.4 million at 30 June and no debt. FID was targeted for the September quarter 2026, while environmental approval, a rig, and project debt via Barrenjoey remained open.
Written from the 35 story beats below (2022 to 20 Aug 2026), which come from the company's own announcements and filings.