29 Jan 2019quarterly activities report▼ Bad
December quarter net revenue was about US$7.7m on 110,056 barrels of oil net, down from US$9.6m in the September quarter. Cash fell to US$6.1m from US$11.6m. Market capitalisation was A$148.5m (A$0.215 per share), against A$230.7m at 30 September. A$2m of Metgasco notes remain.
Byron appointed Skip Erwin, a consultant for the past year, as Senior Reservoir Engineer. He and a regulatory consultant received 1.25m unlisted options at A$0.40 expiring 31 December 2021. Minor staffing change.
Byron received final reprocessed WesternGeco seismic covering 22 South Marsh Island blocks and has identified new low-risk development opportunities and prospects. The data lowers the geological risk of the SM74 Raptor prospect, due to be drilled with Metgasco's 30% interest.
SM71 passed 1 million barrels of gross oil production on 15 January 2019, with no water produced. Byron says the initial capital cost of the platform, wells, pipelines, seismic and leasing has been recovered.
SM71 pressure testing shows water support from the aquifer, and F1 and F3 appear connected in one reservoir. F2 is stable at 165 bopd after a gas-lift change, which resolves the earlier instability. The field makes 2,900 bopd and 7.25 mmcf/d gross; payout is expected within a year of first production.
Byron issued 9.5m unlisted options at A$0.40, expiring 31 December 2021, for nil consideration to executive directors, senior managers and consultants. This completes the grants approved at the 22 November AGM.
All resolutions at the 22 November 2018 AGM passed, including the remuneration report, re-election of Sands and Battersby, and the option grants to Smith, Kallenberger, Sack and senior managers. The option grants drew about 50m votes against.
September quarter net sales were 131,867 barrels of oil, with net revenue about US$9.6m. Cash was US$11.6m at 30 September (US$2.26m at 30 June). Weiss-Adler No. 1 was plugged; SM74 is now expected to drill in the March 2019 quarter.
The SM71 F2 recompletion to the B55 sand is finished. It flowed 382 bopd initially, but after sand control the well is struggling to unload fluids and is now flowing an unstable 150-200 bopd. Byron expects it to stabilise over a couple of weeks.
Byron signed a drilling contract for the White Fleet Drilling 350 rig to drill SM74 D-14 from the SM73 D platform. The rig is expected in early February, so spud is on track for February 2019. Metgasco pays 40% of the roughly US$11m cost.
Corporate governance statement for the year to 30 June 2018, measuring practices against ASX recommendations. Administrative; no new business information.
The 2018 annual report repeats known facts: SM71 producing about 3,600 bopd, 2P reserves of 29.3 MMboe, and net revenue of US$9.5m for the year. The chairman cites a market value of A$243m at 30 June.
Partner Metgasco repeats Byron's news that the White Fleet Drilling 350 rig is contracted for a February 2019 SM74 spud. Metgasco holds 30% WI (24.37% NRI) and pays 40% of the roughly US$11m dry-hole cost. Nothing new.
Partner Otto repeats Byron's report that Weiss-Adler No. 1 was non-commercial and is being plugged. Otto holds 40% and funds 53.33% of the first US$10m of costs. Cost is under US$7.5m. Nothing new on Byron.
Weiss-Adler No. 1, Byron's first Bivouac Peak well, reached 17,766 ft MD and is a dry hole: one objective was water-bearing, the other had under 5 net feet of hydrocarbons. It is being plugged. Cost is under US$7.5m versus US$10.8m budgeted.
Weiss-Adler No. 1 at Bivouac Peak has a 9 5/8-inch liner cemented at 14,422 ft and is drilling ahead at 14,856 ft MD, toward the 18,294 ft target. Byron holds 43%. No result yet.
Partner Metgasco repeats Byron's update: Weiss-Adler No. 1 is drilling ahead at 14,856 ft, with the liner set at 14,422 ft, and on target for about 75 days. Metgasco holds 10%. No new Byron information.
Recompletion of the SM71 F2 well to the B55 sand has begun, with a liftboat on site from 25 September. Permits were approved. Work is expected to take up to three weeks and cost about US$1.1m gross, as previously flagged.
26 Sept 2018security holder rights change● Neutral
Metgasco received 3,766,479 Byron shares from converting A$1m of its convertible notes, as announced on 19 September. It now holds 41,663,479 Byron shares, or 6.05%, and A$3m of notes remain.
Full-year statutory accounts for the year to 30 June 2018 are lodged. The visible text is the contents page and director biographies; the financial figures are truncated, so no results can be stated here.
Weiss-Adler No. 1 has 11 7/8-inch casing cemented at 11,890 ft MD and is drilling ahead at 13,918 ft toward 18,294 ft. Byron holds 43%. Still on track, with no result yet.
Partner Metgasco repeats Byron's update: Weiss-Adler No. 1 is drilling ahead at 13,918 ft with casing cemented at 11,890 ft, on target for about 75 days. Metgasco holds 10% WI. No new Byron information.
BOEM accepted Byron's bids and awarded Main Pass 293, 305 and 306 at 100% WI, about US$0.4m gross bonus. The blocks sit on a salt dome that produced 96 million barrels of oil. This resolves the 16 August high-bidder status.
Byron signed the final platform-use and production-handling agreements on 9 September for drilling SM74 from the SM73 D platform. Spud has slipped from October/November 2018 to February–April 2019, depending on rig availability and BOEM permit. Metgasco holds 30%.
September 2018 investor presentation. The visible text is a disclaimer and capital structure: 685 million shares, A$191.8m market cap at 18 September, US$2.26m cash at 30 June. The rest is truncated; it appears to repeat known facts.
Partner Metgasco confirms the SM73 platform agreements are executed and SM74 spud is now February–April 2019. Its cost to reach total depth is about US$4.4m for 30% WI. It expects Weiss-Adler results in Q4 2018. No new Byron information.
SM71 produced about 641,737 barrels of oil and 556 million cubic feet of gas cumulatively. Output has settled at 3,600 bopd and 6.0 mmcf/d gross, down from about 4,000 bopd in early August. F2 recompletion to the B55 sand is due late September, at about US$1.1m gross.
19 Sept 2018security holder rights change● Neutral
Byron plans to grant 2.1 million options each to the CEO and two executive directors, plus 3.2 million to other staff and consultants. These are A$0.40 options expiring 31 December 2021, subject to shareholder approval at the AGM. The exercise price is a 43% premium to the 28 cent close.
19 Sept 2018security holder rights change● Neutral
Metgasco elected to convert A$1m of its remaining A$4m Byron convertible notes into Byron shares at a 10% discount to the 30-day VWAP. The rest of the notes stay in place. It also reports Weiss-Adler casing set at 11,890 ft.