Each one in plain English, with the numbers worked through for a shareholder.
4 Dec 2018investor presentation● Neutral
December roadshow presentation repeating known points: about 850 bopd capacity, a two-well drilling plan and acquisition strategy. It adds that 60 opportunities were screened, 5 shortlisted and 2 heads of agreement signed, with North Madura in final due diligence. Text truncated.
October production was a record 27,795 bbl (100%), 15,287 net, with sales of 15,422 bbl net at US$76.69. Bunian-5 site construction has begun and the drilling contract is out to tender. Repeats the record already announced on 8 November.
13 Nov 2018asset acquisition disposition▲ GoodMajor
Bass signed a heads of agreement to acquire 100% and operatorship of the North Madura PSC, offshore east Java, in under 50m of water. The PSC requires one well; the Reog prospect is the lead candidate. Completion needs a sale agreement and regulatory approval. Price not stated; farm-out is planned.
October production hit a record 27,795 bbl (100%), 15,287 net, averaging 896 bopd, 7% above the October 2015 record of 26,077 bbl. Resolves the scale and pump problems that cut output in June to August. The field is now producing about 850 bopd.
Construction of the Bunian-5 well site began. It will be drilled vertically from the Bunian-4 pad to save cost and time. The rig contract is expected to be awarded in December 2018, with spud soon after.
Bass signed a further MoU with Bandung Institute of Technology and Sejong University to study CO2 enhanced oil recovery for its current and future fields. It extends the earlier low-salinity waterflood MoU. It is research only; no costs or results are given.
October production is averaging almost 900 bopd (100% JV), putting the field on track to challenge the KSO record of about 26,000 bbl set in October 2015. Completed scale remediation and optimisation are credited; Bunian-5 is still expected in December.
September production rose 53% to 17,081 bbl (100%), 9,395 net, after the scale remediation, reaching 850-950 bopd by month end. Sales were 8,537 bbl net at US$73.50. Two-well drilling is still expected from December 2018.
Bass settled a royalty dispute with one unnamed party, which ends that royalty, in return for a confidential cash payment based on estimated royalty value. The amount and the royalty are not stated, so the effect on shareholders is unclear. Other parties to the dispute are not mentioned.
Company released two videos, an interview and the RIU Good Oil conference presentation, by the Managing Director. No new operating, financial or reserve information.
RIU Good Oil Conference presentation repeating known points: 2,606m shares, cash US$0.99m, no debt, 650 bopd capacity, Bunian-5 drilling in December quarter without raising capital, and 0.893 MMbbl net unrisked prospects. Text is truncated; nothing new.
August production was 11,156 bbl (100%), 6,136 net, down 2% on July, with sales at US$67.64/bbl. Scale remediation finished in early September and output is expected to return to May levels. Resolves the pending scale clean-outs; Bunian-5 drilling procurement has started.
Half-year report to 30 June 2018: net production 52,770 bbl and sales 53,612 bbl, with cash of US$0.99m. Repeats the scale problems, the Cooper payment deferrals and the planned drilling. Text is truncated; no financial statements are shown.
Pertamina approved the budget for the Bunian-5 and Tangai-5 development wells, a prerequisite to procuring drilling services. Bunian-5 is intended first, in December 2018. This resolves the pending budget approval for the drilling program.
July production was 11,350 bbl (100%), 6,243 net, still held back by scale. The Bunian-1 pump failed and a workover rig was mobilised in August; a coiled tubing unit is also due for Bunian-3. Bass expects production to return to May levels.
June production fell 40% to 11,010 bbl (100%), 6,055 net, from scale in the wells and Bunian-1 pump wear. Bunian-3 was offline a week. Sales were at US$68.54/bbl. Drilling is still expected in the December quarter.
Noosa conference presentation repeating known points: 650 bopd capacity, UNPAD prospects (0.893 MMbbl net unrisked), acquisition strategy, and a claim that cash flow is expected to pay the deferred acquisition costs. Text truncated; nothing new.
Cooper Energy agreed to defer the A$500k payment due 30 Sep 2018 to 31 Mar 2019, and the final A$770k due 31 Dec 2018 to 30 Jun 2019, with 7.5% interest on the A$1.27m outstanding. Bass says this avoids raising capital.
May production rose 9% to 18,500 bbl (100%), 10,175 net, with sales at a multi-year high US$70.51/bbl. Pump upgrades at Bunian-1 and Tangai-1 are planned for the September quarter; the two-well drilling program is now expected in the December quarter.
AGM presentation in Adelaide repeating known points: 2,606m shares, A$2.35m cash, no debt per the slide, 650 bopd, and options worth up to about A$2.2m if exercised. Text is truncated; no new information.
Dr Simon Brealey, formerly Cooper Energy's staff geologist for Indonesia and Australia, joins as Staff Geologist – New Ventures to find and negotiate acquisitions near Tangai-Sukananti. Advances the stated acquisition strategy; no deal is announced.
April production was 16,994 bbl (100%), 9,347 net, 14% below March's record, after scale in pipework forced Tangai-1 and Bunian-3 shut-ins. Sales were 9,877 bbl net at US$65.57, the highest price since late 2014. Drilling is now expected late in 2018.
Singapore roadshow presentation restating known points: Tangai-Sukananti 55% operator interest, about 650 bopd (100%), and acquisition focus near existing infrastructure. Text is truncated; no new results or figures beyond earlier releases.
March production was a post-acquisition high of 19,883 bbl (100%), 10,936 net, up about 21% on February. Sales realised US$59.83/bbl. Bunian-3 is at 450 bopd and rising. Drilling is now stated for the September quarter; 2P reserves at 31 Dec 2017 are 1.28 MMbbl gross.
Field output rose 20% to 650 bopd (100%) at Tangai-Sukananti, mainly from the larger Bunian-3 flowline, which doubled that well's capacity to about 700 bopd. A further 150-250 bopd is expected over coming weeks. Follows the January-February bottleneck work.
Appendix 4G and corporate governance statement lodged with the annual report, saying governance disclosures are in the annual report and on the website. Compliance paperwork with no new business information.
Annual report for the transitional period to 31 December 2017. Chairman and Managing Director highlight the Tangai-Sukananti strategy, 95% option exercise and optimisation work. Text provided is truncated and no financial figures are shown. Reserves at 31 Dec 2017 appear as 1.28 MMbbl gross 2P in later releases.
February production recovered to 16,403 bbl (100%), 9,021 net, up about 24% on January after scale removal. Sales realised US$59.82/bbl. The Bunian-3 flowline is installed and awaiting hydro-testing; drilling still expected in Q3 2018.
First UNPAD study results identify two new near-field prospects, Sukananti Updip and Bunian West, with 1.62 MMbbl best-estimate unrisked prospective resource (0.893 net to Bass), at 30% and 32% chance of success. Added to the 2018/19 drilling plan, subject to regulator approval.