Stockle - the stock oracle

State GAS Ltd

ASX:GAS
A$0.009Close 7 Oct 2026 · delayed

Past year: ▼ 68%(0.90c – 3.10c AUD)

Market cap
A$4.9m
Shares on issue
547m
In-ground value
A$325m
Risked multiple
under review
Story beats
93 since 2017
Last event
13 July 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

30 July 2021quarterly activities report▼ Bad

Appendix 5B: cash fell from $6.27M to $3.16M over the June quarter, with $2.76M spent on capitalised exploration. The company itself gives about 1.03 quarters of funding, and says exploration intensity eases from end of August. No debt facilities. Funding is the pressing issue.

Discuss in chat

30 July 2021quarterly activities report▲ Good

June quarter: Nyanda-4 stabilised near 140,000 cf/d and a log confirmed output from 1,150m. Rougemont-1 and -2 each found 8m net coal. Infrastructure providers are willing to build and own the pipeline, cutting State Gas's capital needs; a reserves certification is expected next quarter.

Discuss in chat

16 July 2021investor presentation● Neutral

Noosa conference presentation, stated to repeat material previously released to ASX. Reiterates the two-project strategy and a 2023 first-gas target, and lists funding options (gas presales, purchaser equity or debt, equipment supplier funding). No new information; text truncated.

Discuss in chat

24 June 2021well test result▲ GoodMajor

A production log at Nyanda-4 shows gas coming from below 1,150m as well as from 400-600m, which the company says supports its view that deep coals can produce unaided. Nyanda-4 is at 138,000 cf/d; Nyanda-8 at 38,000, Nyanda-7 at 7,000.

Discuss in chat

9 June 2021drilling result▲ GoodMajor

Rougemont-2 drill-stem tests show permeability that exceeded all expectations, and initial gas analysis suggests near-pipeline quality. The well is suspended pending production testing, and appraisal drilling is being planned. Reid's Dome wells flow over 220,000 cf/d combined, Nyanda-4 at 140,000.

Value this in the calculator →Discuss in chat

7 June 2021drilling result▲ GoodMajor

Rougemont-2 reached 540m, with coals from about 295m (roughly 200m shallower than Rougemont-1) and 8m net coal, gas bubbling from cores. Field values suggest commercial gas content, matching Rougemont-1's 8m. Lab gas contents and further tests still to come.

Value this in the calculator →Discuss in chat

2 June 2021drilling progress report● Neutral

Rougemont-2 has reached 324m, just above the top of the Bandanna coals. Coring starts later this week after steel casing is run. A short progress update with no new result.

Value this in the calculator →Discuss in chat

31 May 2021drilling spud● Neutral

Rougemont-2 spudded 29 May, the second Rolleston-West well, 3.7 km northeast of Rougemont-1 and at 75m by release time. Coals are expected up to 100m shallower than Rougemont-1. (The release's '2014' spud date appears to be a typo; text elsewhere says 2021.)

Value this in the calculator →Discuss in chat

27 May 2021investor presentation● Neutral

May 2021 investor presentation pitching Reid's Dome and Rolleston-West (1,593 km2 combined, both 100% owned) as a response to east coast gas shortages. Shows indicative first gas for Reid's Dome in H1-23 (from the timeline chart). Largely repeats known facts; text truncated.

Discuss in chat

24 May 2021drilling result▲ GoodMajor

Rougemont-1 reached 800m on 23 May, intersecting 8m of net coal with top coal at 495m and gas bubbling from cores. Early field readings are in line with the nearby Arcadia Valley and Mahalo Bandanna projects. Gas content and permeability testing is still under way.

Value this in the calculator →Discuss in chat

17 May 2021drilling spud▲ GoodMajor

Rougemont-1 spudded 14 May, the first well on the new Rolleston-West permit (ATP 2062), targeting Bandanna coals at a planned 800m. Serocold-1 reached 35,700 cu ft/day, and Nyanda-4 is back up to 114,000. The first drilling on the new acreage.

Value this in the calculator →Discuss in chat

30 Apr 2021quarterly activities report● Neutral

March quarter: Nyanda-4 peaked near 700,000 cu ft/day before settling around 100,000; Nyanda-8 is approaching 50,000 and Nyanda-7 about 5,000. Serocold-1 restarted 7 April. Cash was $6.27M. Rougemont civil works started 29 April, with results expected in June.

Discuss in chat

16 Apr 2021well test result● Neutral

Serocold-1 workover finished 6 April with the pump set 330m deeper. Nyanda-4 has settled back to about 100,000 cu ft/day after the high rate, which the company attributes to draining of free gas in near-well fractures. Nyanda-7 is at 6,000 and Nyanda-8 at 42,000.

Discuss in chat

17 Mar 2021investor presentation● Neutral

Cottee's conference presentation sets out the company's thesis that natural fractures in the Reid's Dome coals aid gas flow. It cites Nyanda-4 rates and image logs from Nyanda-7 and -8 as support. Largely repeats known results; the text is truncated.

Discuss in chat

16 Mar 2021well test result▲ GoodMajor

Nyanda-4 produced 620,000 cubic feet in 24 hours, exceeding earlier test rates, which were cut short by pump breakdowns. Nyanda-8 is at 31,000 cu ft/day and Nyanda-7 at 5,000. Serocold-1 workover rig is on site. This is the strongest Reid's Dome flow so far.

Discuss in chat

11 Mar 2021half year report● Neutral

Interim report to 31 December 2020 covering the $14.5M October raising (placement and SPP at $0.55) and the Nyanda-7/-8 drilling. Its review of operations repeats the Chairman's letter. The financial statements were truncated in the text, so no figures beyond the raising are confirmed.

Discuss in chat

10 Mar 2021investor presentation▲ Good

Chairman Cottee's letter says testing has beaten his expectations: Nyanda-4 at 252,000 cu ft/day, Nyanda-7 6,000 and Nyanda-8 26,000, against a commonly cited 100,000 economic threshold. Rougemont approvals are expected by late April. Largely a recap with updated rates.

Discuss in chat

8 Mar 2021investor presentation● Neutral

March progress presentation largely repeating known results: Nyanda-4, -7 and -8 on production test, with Nyanda-7 water output three times Nyanda-4's. Shows Nyanda-4 at 249,000 cu ft/day. Rolleston-West drilling now targeted mid-late April, after the wet season.

Discuss in chat

8 Mar 2021investor presentation● Neutral

Amended re-release of the same March progress presentation; the text provided is identical to the original, so no change is visible. No new information.

Discuss in chat

18 Feb 2021well test result▲ Good

Nyanda-4 holds around 100,000 cubic feet a day, ahead of earlier tests. Water is now below the top of the coals in Nyanda-7 and -8, both showing gas flow and good recharge. Rolleston-West drilling planning is under way.

Discuss in chat

11 Feb 2021well test result▲ Good

Nyanda-4 is now producing 100,000 cubic feet a day and rising, higher than at similar stages in earlier testing. Nyanda-8 is making about 5,000 cubic feet a day; Nyanda-7 is nearly at the top of the coals, with gas expected shortly.

Discuss in chat

3 Feb 2021well test result▲ Good

Weekly update: Nyanda-4 is flowing at a reported 78 cubic feet per day (the figure as written, likely an error given earlier rates), which the company says is at least as good as earlier testing. Nyanda-7 began producing gas on 1 February; Nyanda-8 dewatering started.

Discuss in chat

29 Jan 2021quarterly activities report▲ Good

December quarter: ATP 2062 was granted, the SPP closed bringing about $14.5M raised, and Nyanda-7 and -8 were drilled. All three Nyanda wells are in testing. Remaining wells wait for the wet season to ease (mid to late March); environmental studies for development have started.

Discuss in chat

27 Jan 2021well test result▲ Good

Production testing began: Nyanda-4 restarted on 19 January and was flowing 57,500 scf/d by 27 January; Nyanda-7 began testing on 25 January and Nyanda-8 is getting its pump. Remaining north and central wells are delayed by La Nina rain.

Discuss in chat

6 Jan 2021drilling result▲ GoodMajor

Nyanda-8 reached 1,200m on 3 January with 19.7m net coal and open fractures. With Nyanda-7, results are within the range expected from Nyanda-4. The rig stands down for the wet weather; all three wells should be dewatering by end January.

Value this in the calculator →Discuss in chat

24 Dec 2020drilling result▲ GoodMajor

Further evaluation puts Nyanda-7 at 38.2 m net coal, with seams and gas shows similar to Nyanda-4 and numerous open natural fractures. The well is cased and suspended awaiting completion; the rig is moving to Nyanda-8.

Value this in the calculator →Discuss in chat

22 Dec 2020drilling result▲ Good

Nyanda-7 reached target depth of 1,212m on 19 December with over 30 m of net coal and encouraging gas readings. The rig moves to Nyanda-8 next, with pumps and production testing planned for early in the new year.

Value this in the calculator →Discuss in chat

15 Dec 2020drilling spud▲ GoodMajor

Nyanda-7 spudded on 15 December, the first Phase 2 well, a step-out about 2.6 km north of Nyanda-4 with planned depth of 1,200m. At least three more wells follow, weather permitting; two Rolleston-West coreholes are planned for the New Year.

Value this in the calculator →Discuss in chat

10 Dec 2020drilling scheduled▲ Good

Silver City Rig 25 is mobilising to Reid's Dome to start Phase 2, which will drill at least four production wells around Nyanda-4. Nyanda-7 is first, spud expected next week. The aim is two wells drilled and three testing before the wet season.

Value this in the calculator →Discuss in chat