27 July 2016resource reserve update▲ GoodMajor

At 30 June 2016, 2P reserves rose 15% to 83.4 mmboe (net of Maisey sale) and 1P to 12.1 mmboe, with first Surat Basin 1P booking after the GLNG gas deal. Cooper contingent resources were cut 39% to 208 mmboe, mainly unconventional gas, after weak Hornet-1 and Kingston Rule-1 tests.

Value this in the calculator →Discuss in chat

2 Mar 2016drilling progress report▼ Bad

No wells were spudded in February. Senex says it will do no drilling in the near future because of the subdued oil price outlook, and will stop monthly drilling reports until drilling resumes.

Value this in the calculator →Discuss in chat

3 Feb 2016drilling progress report● Neutral

No wells were spudded in January, in line with the reduced capital program. Further drilling depends on the oil price outlook; a market update is promised with the half year results on 23 February 2016.

Value this in the calculator →Discuss in chat

13 Jan 2016drilling result▲ Good

Ethereal-1, the second Origin joint venture gas well (PEL 637, Senex 60%), reached 3,234 m on 2 January, on prognosis and matching Efficient-1's hydrocarbon zones. It is cased and suspended for fracture stimulation and testing; Senex is free-carried.

Value this in the calculator →Discuss in chat

2 Dec 2015drilling result▲ Good

Martlet-2 development well (Senex 60%) reached 1,535 m, found 4.5 m of net Namur oil pay, and was cased and suspended as a future producer, online early 2016. It adds to the Martlet field after Martlet-1 and Martlet North-1.

Value this in the calculator →Discuss in chat

4 Nov 2015drilling result▲ Good

Efficient-1, the first Origin JV gas well (PEL 637, Senex 60%), reached 3,196 m with hydrocarbon shows; it will be cased and suspended for fracture stimulation and testing. Spitfire-7 began producing in late October, in line with expectations.

Value this in the calculator →Discuss in chat

7 Oct 2015drilling result▲ Good

Spitfire-7 reached 1,827 m with 6.6 m of net Birkhead pay, on prognosis; cased and suspended, online expected November. Martlet North-1 began production at end September. Efficient-1, the first Origin JV gas well (Senex free-carried), spuds mid-October.

Value this in the calculator →Discuss in chat

2 Sept 2015drilling result● Neutral

Fulcrum-1 (PRL 136, Senex 60%) reached 1,815 m, found Birkhead oil shows but poor reservoir, and was plugged and abandoned. Spitfire-7 was spudded. Growler-14 is online at 350 bbl/d. Martlet North-1 is expected online in October.

Value this in the calculator →Discuss in chat

25 Aug 2015resource reserve update▲ GoodMajor

Net 2P reserves rose 137% to 94.6 mmboe at 30 June 2015 (from 39.9), mostly from the QGC gas swap, with gas 83.3 mmboe. Oil 2P fell to 11.3 mmbbl (from 13.3). 1P fell to 4.3 mmboe. Some Murta reserves were reclassified as contingent because of low oil prices.

Value this in the calculator →Discuss in chat

3 June 2015drilling progress report● Neutral

Senex finished its FY15 drilling at 13 wells, against an original 26, with none spudded in May. The cut followed the lower oil price. FY16 work program is being finalised, with a market update due by the 25 August results.

Value this in the calculator →Discuss in chat

6 May 2015drilling result● Neutral

Dunoon-3 (1,268 m) and Morris-1 (1,486 m), both Senex 100% on the Dunoon Ridge, showed oil but no movable hydrocarbons in the McKinlay at Dunoon-3. Both were cased and suspended as future Murta tight oil producers. Thirteen FY15 wells are now drilled.

Value this in the calculator →Discuss in chat

8 Apr 2015drilling scheduled● Neutral

No drilling in March; eleven FY15 wells are done. Senex plans to spud the twelfth, Dunoon-3 (PRL 161, 100%), in April, a low-risk oil target on the producing Dunoon Ridge, in line with the shift to lower-risk spending.

Value this in the calculator →Discuss in chat

4 Mar 2015drilling result▲ Good

February report: Martlet North-1 confirmed with 3.2 m net Namur pay. Growler-14 (PPL 242, Senex 60%) reached 1,890 m with about 6 m net porous sand above the oil-water contact and was cased as a future Birkhead producer, pending testing. Eleven FY15 wells drilled.

Value this in the calculator →Discuss in chat

4 Mar 2015drilling progress report● Neutral

Beach's February report repeats the Martlet North-1 result (3.2 m net Namur oil pay, cased and suspended, tie-in timing to be determined) and Growler-14 (cased and suspended, cased-hole test later). Senex is the 60% partner; no new Senex results.

Value this in the calculator →Discuss in chat

24 Feb 2015drilling result▲ GoodMajor

Martlet North-1 (PRL 148, Senex 60% operator, Beach 40%) found a Namur oil discovery with 3.2 m net pay, 1.1 km from the producing Martlet-1. It is cased and suspended as a future producer, with tie-in timing subject to field development planning.

Value this in the calculator →Discuss in chat

4 Feb 2015drilling spud● Neutral

Martlet North-1 (PRL 148, Senex 60% operator, Beach 40%) spudded in late January, targeting the Namur about 1.1 km northwest of the Martlet-1 producer. Planned depth 2,028 m. Drilling had reached 1,127 m at the report date.

Value this in the calculator →Discuss in chat

14 Jan 2015drilling result▼ BadMajor

Senex confirms Sheerkhan-1 was plugged and abandoned (uneconomic oil volume, poor reservoir) and Jenners-1 abandoned at 2,525 m with poor shows. The six-well northern Cooper campaign found no commercial reserves. Rig moves to Martlet North-1, near the Martlet-1 discovery.

Value this in the calculator →Discuss in chat

2 Jan 2015drilling result▼ BadMajor

Jenners-1 (PEL 100, Senex 55% operator) was plugged and abandoned at 2,525 m in pre-Permian basement, a dry hole. It ends the exploration campaign in the northern Cooper that began in late 2014.

Value this in the calculator →Discuss in chat

24 Dec 2014farm in farm out agreement● Neutral

Tellus says it amended its PRL 108-110 farm-in with Senex: instead of a carried well, Senex funds about 42 sq km of 3D seismic, starting Q1 2015, and earns another 7% (Tellus left with 43%). Replaces the well commitment noted earlier.

Value this in the calculator →Discuss in chat

23 Dec 2014resource reserve update▲ GoodMajor

Partner Beach estimates Martlet field (PEL 104/111, Senex 60% operator) gross 2P oil reserves at 589 kbbl (1P 214, 3P 1,634), the first Namur reserves in the permit. Facilities cost about $4.1m and are complete; Martlet-1 began producing in December.

Value this in the calculator →Discuss in chat

15 Dec 2014drilling spud● Neutral

Cooper Energy reports Jenners-1 spudded 15 December in PEL 100 (Senex 55% operator, Santos 25.835%, Cooper 19.165%), targeting to 2,608 m, about 14 days including testing. It is the next well in the northern Cooper campaign.

Value this in the calculator →Discuss in chat

3 Dec 2014drilling progress report● Neutral

November drilling report: seven FY15 wells drilled, eighth spudded. Akela-1 confirmed as trace to poor shows, cased and suspended. Sheerkhan-1 (PEL 182, Senex 57%) reached 2,350 m on 30 November with good Birkhead oil shows; testing under way, result not yet known.

Value this in the calculator →Discuss in chat

12 Nov 2014drilling result▼ BadMajor

Cooper Energy reports Akela-1 (PEL 110, Senex 60% operator) reached 2,676 m with trace to poor oil shows and was cased and suspended for possible later evaluation of the Birkhead. Not a discovery; the rig moves to Jenners-1 in PEL 100 in December.

Value this in the calculator →Discuss in chat

5 Nov 2014drilling result▼ Bad

Bagheera East-1 (PEL 514) was plugged and abandoned as non-commercial, though hydrocarbon shows confirm oil migration. Akela-1 is drilling. Martlet-1 flowed 2,596 bopd and starts production in December; Hornet-1 is being completed for extended testing, with production expected in the December quarter.

Value this in the calculator →Discuss in chat

29 Oct 2014drilling spud● Neutral

Cooper Energy reports Akela-1 spudded 29 October in PEL 110 (Senex 60% operator, Cooper and Orca 20% each), targeting oil to about 2,686 m, with about 17 days planned including testing. Part of Senex's northern exploration campaign.

Value this in the calculator →Discuss in chat

20 Oct 2014drilling result▼ BadMajor

Planet Gas reports two drill stem tests at Bagheera East-1 (PEL 514) found no moveable hydrocarbons; the well is being plugged and abandoned. Despite earlier oil shows, it is the second dry hole in a row in PEL 514 after Hathi-1.

Value this in the calculator →Discuss in chat

13 Oct 2014drilling progress report● Neutral

Planet Gas reports Bagheera East-1 reached 2,547 m with oil shows in the Birkhead, Poolowanna and Hutton formations; wireline logging is being prepared. An early positive sign, with no test result yet.

Value this in the calculator →Discuss in chat

8 Oct 2014drilling result● Neutral

Senex's September drilling report: five of 26+ FY15 wells drilled. Martlet-1 is due on production in November; Squire-1 had poor-reservoir oil shows and Hathi-1 (2,569 m) had only trace hydrocarbons, both plugged and abandoned. Rig moves to Bagheera East-1.

Value this in the calculator →Discuss in chat