303 since 2006
Last event
13 Aug 2026

Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

29 Apr 2016annual report● Neutral

Annual corporate governance statement for the year to 30 June 2016, setting out compliance with ASX governance recommendations. Administrative disclosure with no new operational or financial information.

Discuss in chat

28 Apr 2016investor presentation▲ Good

Otto says Great Bear's work, with 3D seismic 90% acquired, supports a multi-well conventional drilling campaign on the Alaskan North Slope in 1H 2017. A nearby well partly de-risks shale potential. Otto holds 8–10.8% and is free-carried on seismic.

Discuss in chat

27 Apr 2016drilling result▲ GoodMajor

Porosity logs show 132 feet of net oil pay in SM-71 #1 (I3 17ft, J 24ft, D5 91ft). The partners will deepen the well about 600 feet to test the D6 sand, expected within the original budget. Firms up the earlier gross-thickness discovery.

Value this in the calculator →Discuss in chat

22 Apr 2016quarterly activities report● Neutral

March quarter report: cash fell to US$26.73m. It records the failed SM-6 #2 well and the SM-71 #1 option, with the discovery announced after quarter end. Tanzania farm-down and Alaska seismic continue. Largely restates known events.

Discuss in chat

20 Apr 2016drilling result▲ GoodMajor

Byron reports an oil and gas discovery at SM 71 #1, drilled to 2,086m, with three hydrocarbon zones totalling 150 feet gross thickness. Byron plans to complete it for production. Net pay is not yet confirmed. Having drilled to earning depth, Otto can elect a 50% interest, offsetting the SM 6 #2 failure.

Value this in the calculator →Discuss in chat

20 Apr 2016drilling result▲ Good

Otto confirms the SM-71 #1 Gulf of Mexico discovery: three oil and gas zones totalling 150 feet gross, to 2,086m. Otto has earned a 50% interest in SM 70/71 and says it can fund the work from cash. Net pay is not yet confirmed.

Value this in the calculator →Discuss in chat

13 Apr 2016drilling progress report● Neutral

Byron says SM 71 #1 has set surface casing at 3,462 feet and is drilling ahead at 3,976 feet, with total depth and evaluation expected within about 10 days. Routine progress with no result yet.

Value this in the calculator →Discuss in chat

4 Apr 2016drilling spud● NeutralMajor

Byron spudded SM 71 #1 on 3 April 2016, the second well of the Otto farm-in, with about 20 days to drill and evaluate. Otto has paid US$903,610 in back costs and pays 66.67% of the US$4.5m well cost.

Value this in the calculator →Discuss in chat

30 Mar 2016drilling result▼ BadMajor

Byron said SM 6 #2 was temporarily abandoned before reaching the G20 sand after stuck drill pipe, so Otto earned no SM 6 interest and owed no back costs. Otto elected to join SM 71 #1, paying 66.67% of the US$4.5m estimated dry-hole cost (capped at US$3.0m) plus US$0.9m of past costs.

Value this in the calculator →Discuss in chat

30 Mar 2016drilling scheduled● NeutralMajor

Otto exercised its option to join the SM-71 #1 well, to spud within a week and take about 20 days. Otto pays about US$3.0m for 50% plus US$0.9m back costs and assigns a 70% chance of success. Follows the SM 6 #2 failure.

Value this in the calculator →Discuss in chat

30 Mar 2016drilling result▼ BadMajor

Otto confirms SM-6 #2 was plugged and abandoned at 2,464m after stuck pipe in an impenetrable shale, never reaching the G20 target. Otto earns no SM 6 interest, owes no back costs, and about US$100,000 of abandonment cost remains. Spend stays within US$5.3m.

Value this in the calculator →Discuss in chat

21 Mar 2016drilling progress report▼ Bad

Byron says attempts to free the stuck pipe in SM 6 #2 failed over three days, so it is starting a side-track from 2,423m to the same 2,900m target depth. Drilling is due to resume later in the week.

Value this in the calculator →Discuss in chat

18 Mar 2016drilling progress report▼ Bad

Byron reports SM 6 #2 got stuck drill pipe at 2,451m, about 400 feet above the G20 target, after the casing was run. Recovery attempts were under way. A setback for the Otto-funded well.

Value this in the calculator →Discuss in chat

14 Mar 2016joint venture update▲ GoodMajor

Swala, Otto's Tanzania partner, says an independent review lifted gross Kito prospective resources from 151 to 184 million barrels, with Kito-1 still on track for Q3 2016. The Pangani licence showed nothing of commercial interest and is to be relinquished.

Discuss in chat

11 Mar 2016other● Neutral

S&P Dow Jones index rebalance notice listing additions and removals from the S&P/ASX indices. The excerpt shown does not mention Otto Energy. No substance for Otto shareholders.

Discuss in chat

8 Mar 2016drilling progress report▲ Good

Otto says SM-6 #2 reached 2,389m, with oil and gas shows in three shallower F sands consistent with or better than nearby wells. Possible reserve additions, but the G20 primary target is still undrilled and no final result yet.

Value this in the calculator →Discuss in chat

8 Mar 2016joint venture update▲ Good

Byron says SM 6 #2 reached 2,389m with three hydrocarbon-bearing F-zone sands seen on logs, and is running casing before drilling to the G20 target. Operator version of Otto's own update on the Otto-funded well.

Discuss in chat

4 Mar 2016half year report▼ Bad

Half-year to 31 Dec 2015: net loss of $8.6m versus a $10.2m profit a year earlier. Hawkeye-1 cost US$23.7m but Otto was fully carried by BHP, and it found no economic hydrocarbons. Confirms the Philippines exit and the moratorium request.

Discuss in chat

26 Feb 2016drilling progress report● Neutral

Byron reports SM 6 #2 has reached 1,058m with surface casing cemented. Next casing point is 2,403m, above the primary target; drilling resumes shortly. Routine progress with no result yet.

Value this in the calculator →Discuss in chat

16 Feb 2016drilling spud▲ GoodMajor

SM-6 #2 spudded on 15 February 2016, Otto's first Gulf of Mexico well, drilling at 146m. About 40 days to drill and evaluate. Otto pays about US$5.3m to earn 50% of the lease, with a 70% chance of success it assigned.

Value this in the calculator →Discuss in chat

11 Feb 2016drilling scheduled● Neutral

Otto confirms the rig is on location for SM-6 #2, with spud in days and about 40 days to drill. Otto puts the chance of success at 70% and its share of cost at about US$5.3m; success could mean first oil in 2017.

Value this in the calculator →Discuss in chat

11 Feb 2016drilling scheduled● Neutral

Byron says the Hercules 205 rig is on location and SM 6 #2 should spud within about a week, with roughly 40 days to drill and evaluate. It targets the G20 sand to about 2,900m. Operator version of Otto's own announcement.

Value this in the calculator →Discuss in chat

8 Feb 2016joint venture update● Neutral

Byron reports the Hercules 205 rig, released by its previous operator, should mobilise to the SM 6 #2 well when weather allows. This is the first well of the Otto farm-in. Note the rig differs from the Hercules 264 named in December.

Discuss in chat

14 Jan 2016quarterly activities report● Neutral

December 2015 quarter: cash US$33.56m (about A$47.95m, ~4 cents a share). Byron farm-in secured, Alaska 3D seismic of 1,170 km2 contracted for Q1 2016, Tanzania drilling targeted Q3 2016, and Otto began a structured exit from the Philippines, requesting a two-year SC55 moratorium.

Discuss in chat

8 Jan 2016joint venture update● Neutral

Byron says US regulators granted a suspension of production keeping the SM 6 lease alive from 28 December 2015 to 31 December 2016. Byron still expects to spud SM 6 #2, the well Otto is funding, in Q1 2016. Removes a lease-term risk for the farm-in.

Discuss in chat

23 Dec 2015regulatory community update● Neutral

Partner Red Emperor (15% in SC55) says Otto has asked the Philippines Department of Energy for a two-year moratorium on SC55, since the Hawkeye-1 work obligation was met. Studies would continue meanwhile; a response is expected early 2016. Advances the open SC55 forward-plan thread.

Discuss in chat

11 Dec 2015farm in farm out agreement▲ GoodMajor

Otto agreed a staged farm-in with Byron Energy to earn up to 50% of two Gulf of Mexico leases and 45% of an onshore Louisiana lease, with drilling from Q1 2016. Otto cites about US$34m cash and first oil in 2017. Fulfils the acquisition-seeking strategy.

Value this in the calculator →Discuss in chat

11 Dec 2015investor presentation● Neutral

December 2015 investor update on the Byron deal, Tanzania and Alaska, claiming 6+ wells fundable from US$34m cash (A$47m, about 4 cents a share versus a 2.3 cent share price). Terms: Otto pays US$5.3m, US$3.0m and US$6.0m toward the three wells. Mostly repeats the Byron announcement.

Discuss in chat

11 Dec 2015farm in farm out agreement● Neutral

Byron's side of the Otto deal: Otto can contribute up to US$17.3m (US$14.3m drilling, about US$3.0m past costs) across three projects. If Otto declines further wells after SM 6 #2, the agreement ends. Confirms terms already announced by Otto.

Value this in the calculator →Discuss in chat

25 Nov 2015investor presentation● Neutral

Managing Director's presentation to the 25 November 2015 AGM, restating Otto's high-impact exploration strategy, the Galoc exit and officer list. The text shown has no new figures or results; it repeats points already announced.