2 June 2011drilling progress report● Neutral

Partner AWE's report repeats the Arrowsmith-2 update: 13-3/8 inch casing cemented at 600m, about to drill ahead. No new information beyond Norwest's own report.

Value this in the calculator →Discuss in chat

2 June 2011drilling progress report● Neutral

Arrowsmith-2 has run and cemented 13-3/8 inch casing at 600m and is drilling out the shoe to continue in the 12-1/4 inch section. No results yet; target depth still about 3,400m.

Value this in the calculator →Discuss in chat

30 May 2011drilling spud▲ GoodMajor

Arrowsmith-2 spudded on 29 May 2011 in EP413, drilling at 580m on a day-one report. Target depth is about 3,400m in roughly 37 days, with fracture stimulation and flow testing to follow in Q3. Norwest holds 27.945%.

Value this in the calculator →Discuss in chat

24 May 2011investor presentation● Neutral

CEO newsletter ahead of Arrowsmith-2, the first dedicated shale gas well in Western Australia. Norwest holds 27.945% of EP413; the campaign of coring, fracture stimulation and flow testing runs to end September 2011, with early indications expected from late June. Repeats known plans.

Discuss in chat

23 May 2011drilling scheduled● Neutral

Weatherford Rig 826 is being moved to Arrowsmith-2, with spud expected on 28 May 2011. The well is to reach about 3,400m in roughly 37 days, then be fracture stimulated and flow tested. Weekly reports each Thursday.

Value this in the calculator →Discuss in chat

4 May 2011contract award▲ GoodMajor

Norwest signs a drilling contract with Weatherford for Rig 826 to drill Arrowsmith-2, resolving the open rig question. Spud is expected towards end of May, to about 3,400m in roughly 36 days, followed by fracture stimulation. Stakes: Norwest 27.945%, AWE 44.252%, Bharat 27.803%.

Discuss in chat

29 Apr 2011quarterly activities report● Neutral

March quarter report: Red Hill South-1 drilled and abandoned. Terms agreed with Weatherford for Rig 826, with Arrowsmith-2 spud expected end of May. EP413 stake now 27.945%; new shale gas authority area added; UK 2D seismic planned for Q3. Text truncated.

Discuss in chat

18 Apr 2011security holder rights change● Neutral

250,000 unlisted employee options, issued in 2006 at an exercise price of $0.11875, have expired. Administrative.

Discuss in chat

7 Apr 2011regulatory community update▲ GoodMajor

Norwest is awarded a Special Prospecting Authority over 21 onshore blocks (about 860 km², 212,522 acres) between Cervantes and Eneabba. It will fly a gravity survey over six months, then has six months to apply for a permit. Extends its shale gas footprint.

Discuss in chat

5 Apr 2011asset acquisition disposition▲ Good

Norwest agrees to buy John Geary's 0.142% of EP413 for 459,184 shares plus $3,085.80 of arrears. This lifts its stake from 27.803% to 27.945%. Subject to documentation and WA approval.

Discuss in chat

22 Mar 2011drilling scheduled● Neutral

After the Red Hill South dry hole, Norwest calls it a technical success and turns to shale gas. Arrowsmith-2 is now planned for mid May, with the Weatherford rig 826 still being negotiated, after the earlier April target.

Value this in the calculator →Discuss in chat

21 Mar 2011drilling result▼ BadMajor

Red Hill South-1 reached 1,896m. Logs show hydrocarbons at three intervals (1,650.6-1,657.5m, 1,710m and 1,767m), but saturations are considered too low to be commercial. The well is being plugged and abandoned, ending the 9 MMbbl prospect hopes.

Value this in the calculator →Discuss in chat

18 Mar 2011drilling progress report● Neutral

Red Hill South-1 at 1,880m in the Highcliff Sandstone, with trace moderately good hydrocarbon fluorescence at 1,710-1,716m and 1,766-1,780m. Total depth expected that morning, with logs to follow.

Value this in the calculator →Discuss in chat

17 Mar 2011drilling progress report● Neutral

Red Hill South-1 drilling at 1,729m in the Irwin River Coal Measures with no significant gas shows. Total depth expected that evening, then wireline logging.

Value this in the calculator →Discuss in chat

16 Mar 2011drilling progress report● Neutral

BOP testing passed and Red Hill South-1 is drilling the 8-1/2 inch section at 1,369m, having crossed the Beagle Fault at 1,314m. Target reservoir about 1,580m. No results yet.

Value this in the calculator →Discuss in chat

14 Mar 2011drilling progress report▼ Bad

Red Hill South-1 has cased the 12-1/4 inch section at 1,304m, but equipment problems have delayed pressure testing of the BOP. CEO calls it a frustrating weekend and expects drilling to resume once the test passes.

Value this in the calculator →Discuss in chat

11 Mar 2011half year report▼ Bad

Half-year to 31 December 2010: loss of $1,733,357 (prior year $1,162,105). Notes the Bharat deal approval, the $1.25m placement, completion of the options issue raising $784,404, and the Red Hill South spud. Text truncated.

Discuss in chat

10 Mar 2011investor presentation● Neutral

Notice of a Boardroom Radio telecast of CEO Peter Munachen's conference talk on foreign investment and partnership. No new information.

Discuss in chat

10 Mar 2011drilling progress report● Neutral

Red Hill South-1 reached the 9-5/8 inch casing point at 1,309m, with directional drilling on target. Casing and blowout preventer (BOP) testing come next before drilling the final section. No hydrocarbon result yet.

Value this in the calculator →Discuss in chat

3 Mar 2011drilling progress report● Neutral

Red Hill South-1 drilling ahead at 550m in the 12-1/4 inch hole section on 3 March. Target reservoir about 1,580m, total depth about 1,910m. No new result.

Value this in the calculator →Discuss in chat

1 Mar 2011investor presentation● Neutral

Conference presentation repeating known facts: Red Hill South drilling for 9 MMbbl recoverable, a shale gas well in late Q2, UK seismic mid-year, North Erregulla 3D in Q4. Shows 730m shares, 104m options, share price 7.4c, market cap $54m.

Discuss in chat

28 Feb 2011drilling spud▲ GoodMajor

Red Hill South-1 spudded on 28 February 2011, two weeks later than the 14 February date set in January. Targets Dongara Sandstone at about 1,587m, 9 MMbbl recoverable; total depth about 12.5 days away. Norwest and Bharat hold 50% each.

Value this in the calculator →Discuss in chat

28 Feb 2011drilling spud● Neutral

Pre-spud notice: Red Hill South-1 expects to spud 28 February, after the final drilling approval on 25 February. Targets Dongara Sandstone at 1,580m, 9 MMbbl recoverable. Spud to total depth is expected to take about 12.5 days. Superseded by the spud report the same day.

Value this in the calculator →Discuss in chat

21 Feb 2011drilling scheduled▼ Bad

Red Hill South spud slips again, to Saturday 26 February, with more than 90% of Hunt Rig 2 on site. Heavy rain is holding up the remaining equipment. This is the second delay from the original 14 February date.

Value this in the calculator →Discuss in chat

21 Feb 2011admin correction● Neutral

Confirms the 104,587,252 options were allotted on 18 February 2011. Shares on issue are now 732,409,091. Includes a top-20 optionholder list, led by Sundowner International with 16.15%. Administrative.

Discuss in chat

16 Feb 2011capital raising announcement● Neutral

Options issue closed: 48,130,291 options, the shortfall, were taken up by the directors' underwriters, who therefore took roughly 46% of the 104,587,252 offered. The issue raised A$784,404, completing the funding announced on 29 December.

Discuss in chat

16 Feb 2011investor presentation● Neutral

Notice of a Boardroom Radio audio interview with CEO Peter Munachen on Red Hill South and the shale gas projects. No new information in the announcement itself.

Discuss in chat

9 Feb 2011drilling scheduled▼ Bad

Red Hill South spud pushed from 14 to about 21 February because wet weather has delayed Hunt Rig 2's transport. Norwest gives the prospect a one-in-four chance of success; Strachan Corporate says a 9 MMbbl discovery would be worth over A$100m to Norwest.

Value this in the calculator →Discuss in chat

31 Jan 2011quarterly activities report● Neutral

December quarter report: Hunt Rig 2 contracted, Bharat deal approved, Red Hill South on track for 14 February spud, with dry-hole cost about A$5m (Norwest up to A$2m). Arrowsmith-2 still targeted for April, rig slot still being negotiated. Largely repeats known facts; text truncated.