Announcements, explained

Each one in plain English, with the numbers worked through for a shareholder.

12 Nov 2007drilling progress report▲ Good

Pilot production drilling has started at North Casino: pre-collars are done on four wells and the ADR 100 rig is drilling Corella-P11 at 215m. Permeability testing at Corella-E7 is complete, with testing at E10 under way.

Value this in the calculator →Discuss in chat

5 Nov 2007production update▲ Good

The ADR 100 rig has reached Casino after the approval delay, with pilot drilling due to start within a week. Each of the eight wells should take about ten days to drill, then be dewatered and production tested.

Discuss in chat

1 Nov 2007investor presentation● Neutral

Mining 2007 conference presentation repeating known facts: 194 PJ 2P, 660 PJ goal, 385 PJ of gas sale agreements. It adds that the rig awaits transport approvals and a conventional well is planned around Q1 2008. Share price $0.81.

Discuss in chat

30 Oct 2007quarterly activities report● Neutral

September quarter: PEL 16 2P reserves 194 PJ, 17 core holes drilled. The ADR 100 rig is delayed by slow government approvals. CS Energy paid a further $5.52m toward its next 7.5%. Another reserve upgrade is expected before year end.

Discuss in chat

23 Oct 2007director officer appointment▲ Good

Peter Stanmore, 29 years in exploration and formerly Santos's onshore exploration evaluation team leader, joins as General Manager of Exploration. This supports the expanding conventional exploration work in the Clarence Moreton basin.

Discuss in chat

22 Oct 2007annual report● Neutral

Re-release of the 2007 annual report already lodged on 18 September, with the same content (113 PJ 2P). No new information.

Discuss in chat

18 Oct 2007investor presentation● Neutral

Notice of an audio broadcast of an Operations Update by the Managing Director on 18 October 2007. It carries no new information itself.

Discuss in chat

17 Oct 2007drilling progress report● Neutral

Pilot drilling to start this month: 5 surface-to-inseam wells in the CS Energy joint venture and 3 at South Casino. The core drilling program is complete; testing is due by year end, and more data goes to MHA within a month.

Value this in the calculator →Discuss in chat

10 Oct 2007drilling spud● Neutral

Pilot well Corella-P16 spudded 8 October, the first surface-to-inseam pilot well, with pre-collar drilling at 29m before the ADR 100 rig arrives. The MSC-06 deepening is postponed so equipment can be redeployed to the pilot program.

Value this in the calculator →Discuss in chat

3 Oct 2007drilling progress report● Neutral

Weekly report: MSC-06 is awaiting fishing tools to retrieve a parted downhole liner. All other wells remain suspended pending testing. No new results.

Value this in the calculator →Discuss in chat

26 Sept 2007drilling result● Neutral

Riflebird-E5 reached 810m total depth with 13m of coal core and is suspended pending testing. MSC-06 is circulating before drilling resumes. No new results.

Value this in the calculator →Discuss in chat

24 Sept 2007production update▲ Good

The ADR 100 rig from Canada has arrived at the Port of Brisbane and will go to Casino next month for the up-to-eight-well pilot production program. This fulfils the earlier rig arrival timetable; the rig can also test deeper conventional targets.

Discuss in chat

18 Sept 2007annual report▲ Good

2007 annual report: 2P reserves up 480% to 113 PJ (the July figure, before the later lift to 194 PJ), 18 core holes drilled, $19m raised in the year. Lists the CS Energy gas sale (18 PJ/yr) and 660 PJ target as goals.

Discuss in chat

17 Sept 2007resource reserve update▲ GoodMajor

MHA lifted PEL 16 2P reserves a further 50% to 194 PJ (182 PJ net to Metgasco), from 129 PJ in July. Management says it is on track for the 660 PJ 2P target within six months; more data is still to go to MHA.

Value this in the calculator →Discuss in chat

12 Sept 2007drilling progress report● Neutral

Weekly report: old well MSC-06 is being deepened from 670m to about 820m to test deeper coal. Riflebird-E6 finished at 827m with 18m of coal and is suspended. Riflebird-E5 is at 400m.

Value this in the calculator →Discuss in chat

10 Sept 2007investor presentation● Neutral

Conference presentation largely restating known facts: 113 PJ 2P, a 660 PJ goal, pilot production from October and a 115 km seismic program. It gives a share price of $0.83, market cap $100m, 121m shares and $16m cash.

Discuss in chat

5 Sept 2007drilling progress report● Neutral

Weekly report: Riflebird-E6 is coring at 724m with 13.5m of coal so far. Riflebird-E5 is suspended awaiting a coring rig. Riflebird-E7 is suspended. No new results.

Value this in the calculator →Discuss in chat

5 Sept 2007material agreement▲ Good

Metgasco allied with US firm Vectra CBM to advise on drilling and completing the planned 8-well pilot program in the fourth quarter of 2007. Vectra has drilled over 250 similar wells in the Arkoma basin. Aims to speed the pilot.

Discuss in chat

4 Sept 2007drilling scheduled▲ Good

With Molopo, a 115 line-km 2D seismic program was approved for PEL 13 and 426, to run October–November with results due in the first quarter of 2008. Reprocessing flagged structures with conventional oil and gas potential. Metgasco has taken PEL 13 coal seam rights to 75% (option exercised).

Value this in the calculator →Discuss in chat

29 Aug 2007drilling progress report● Neutral

Weekly report: Riflebird-E5 spudded 22 August and is at 150m. Riflebird-E6 is coring at 456m. Riflebird-E7 finished at 825m with 21m of coal and is suspended. No new results.

Value this in the calculator →Discuss in chat

28 Aug 2007joint venture update● Neutral

A further data package has gone to MHA, with its view expected within a month. The ADR 100 rig is en route from Canada, due at Casino in the third week of October. A seismic survey is planned at Corella-E6 before any conventional well.

Discuss in chat

23 Aug 2007investor presentation● Neutral

CFO conference presentation restating known facts: 113 PJ 2P, 1,156 PJ 3P, a 640 PJ 2P goal by early 2008, and 385 PJ of gas projects. It carries no new announcement.

Discuss in chat

22 Aug 2007drilling progress report● Neutral

Weekly report: Riflebird-E7 is coring at 738m with 10m of coal taken so far. Riflebird-E6 is cased at 288m awaiting a coring rig. No new results.

Value this in the calculator →Discuss in chat

15 Aug 2007drilling progress report● Neutral

Weekly report: Riflebird-E6 spudded 10 August and is at 125m. Riflebird-E7 is coring at 450m. Riflebird-E3 is suspended again. No new results.

Value this in the calculator →Discuss in chat

2 Aug 2007investor presentation● Neutral

Notice of an audio broadcast of the managing director's June 2007 quarterly presentation. The content is not in the text provided.

Discuss in chat

2 Aug 2007drilling progress report● Neutral

Weekly report: Riflebird-E7 reached 146m and casing is being set. Riflebird-E4 is logged and suspended. Riflebird-E3 is cored to 711m and fishing for lost tools. No new results.

Value this in the calculator →Discuss in chat

31 July 2007quarterly activities report▲ Good

June quarter report repeats the reserve rise to 113 PJ net 2P (3P 1,156 PJ). Goal now 640 PJ 2P by early 2008. Stratheden's 10-well core program is done; pilot wells follow, and CS Energy would fund $5.5m for another 7.5%. Cash $17.5m.

Discuss in chat

31 July 2007quarterly activities report● Neutral

June quarter Appendix 5B: cash at quarter end was $17.5m, no debt. Quarter included $3.5m from CS Energy; its earned interest is 7.5% of coal seam rights in 3 blocks. Next-quarter outflow estimated at $2.6m. PEL 13 interest is 51% of coal seam rights.

Discuss in chat