Each one in plain English, with the numbers worked through for a shareholder.
22 Apr 2008drilling progress report▲ Good
Further data has gone to reserve certifier MHA, and another reserve upgrade is anticipated. All pilot wells are producing early gas while dewatering. Production flow testing of three gas zones in Riflebird-E14 is planned within weeks.
31 Mar 2008capital raising announcement● NeutralMajor
Metgasco offers eligible shareholders a Share Purchase Plan of $1,000 to $5,000 each at $0.70 a share, a 9.6% discount to the five-day average price. Funds go to expanding exploration, gas commercialisation and working capital. It closes 24 April 2008.
ASX CSM Day presentation repeating known facts: 247 PJ 2P, 640 PJ target by July 2008, MOUs of 33 PJ a year. It adds an enterprise value of $0.44 per GJ of 2P versus peers. Share price $0.77, market cap $94m, cash $12.6m.
Administrative notice: the registered office and principal place of business moved to Suite 1, Level 9, 77 Pacific Highway, North Sydney. No substantive content.
Half-year to December 2007: 2P reserves up from 22 PJ to 247 PJ in PEL 16, six pilot wells on production test. Gas sale talks with CS Energy aim at a field development decision in the second half of 2008. Financial figures not shown in the excerpt.
MHA certified PEL 16 2P reserves at 247 PJ (213 PJ net to Metgasco), up 27% from 195 PJ. 3P reserves rose about 20% to 1,389 PJ, and further upgrades were expected in coming months.
NSW declared the 145km Casino to Ipswich pipeline a Major Project, which should streamline approvals; Commonwealth treats it as a controlled action. Re-entry at Corella-E6 now points to the I/J coal sequence, not volcanics, as the source of earlier gas kicks.
Riflebird-E13 reached 1,297m with gas shows and a well-developed I/J coal sequence, but could not be tested on site; it is cased for later fraccing. The rig is heading to re-enter Corella-E6.
Gas is still being flared at Corella-P11, and pumping started at P16, P14 and Riflebird-P11. Riflebird-E14 was spudded to test the deeper I/J coal sequence and is at 754m. Rain keeps hampering access.
Riflebird-P12 drilling is complete, with pumps due next week. Dewatering continues at four wells; Corella-P16's start is delayed by heavy rain, and minor flooding restricted access to some sites.
Michael O'Brien joins as General Manager Development (ex-WorleyParsons coal seam gas group) and Jackie Geraghty as General Counsel (ex-Cement Australia). The managing director links the hires to a major development stage over the next year.
December quarter: 2P reserves 195 PJ, 3P 1,156 PJ, with a further upgrade expected within a month. Six pilot wells drilled and dewatering with encouraging early gas; Corella-P13 suspended pending fishing. BP MOU signed and pipeline environmental assessment started.
Dewatering continues at four pilot wells, with encouraging early gas flows seen but not yet stable enough to report rates. The rig is drilling the in-seam section of Riflebird-P12.
Dewatering restarted at Corella-P11 after floods halted work, and began at Riflebird-P11. Drilling at Corella-P14 is complete, and the rig has moved to Corella-P16.
January presentation restating 194 PJ 2P reserves, with further upgrades said to be imminent. It notes MOUs of 360 PJ to CS Energy and 150 PJ to BP, four pilot wells dewatering, share price $0.91 and cash $12m.
Pumps are being installed at P11, P12 and Riflebird-P11 to continue production testing. Corella-P14 is drilled to 961m and running liner; the rig moves to P16 next. P13 remains suspended.
Pilot drilling was not significantly affected by regional flooding. Corella-P14 is above flood levels and drilling in-seam at 771m. Some minor equipment was lost at low-lying sites.
Corella-P13 reached 965m, but a gas influx and loss of pressure collapsed part of the hole and stuck tools. The well is suspended awaiting fishing equipment. The rig moved to P14, and dewatering continues at P11, P12 and Riflebird-P11.
Dewatering continues at P11 (about 260 bbls/day), with gas flowing unaided but no rates reported yet. Riflebird-P11 drilled a record 470m in-seam in 24 hours. P12 dewatering has started; P13 and P14 will be drilled over the holidays.
Dewatering began at Corella-P11, with water initially 288 bbls/day, falling to 170, which the company calls substantially higher than earlier wells and very encouraging. Free gas is flowing but not yet metered. P12 drilling is complete and the rig has moved to Riflebird-P11.
Corella-P12, targeting the Tomki seam, is drilling ahead in-seam at 700m. P11 drilling is complete with production testing to start in coming weeks. Other wells unchanged.
Metgasco signed an MOU with BP Australia for a feasibility study on supplying over 15 PJ a year of coal seam gas, plus extending the planned Casino-Ipswich pipeline to BP's Port of Brisbane refinery. A second major gas customer alongside CS Energy; not yet a binding sale.
First pilot well Corella-P11 is fully drilled, with production testing due in coming weeks. Second well P12 is at 430m awaiting a replacement mud-motor. Other wells have 150m casing set.
AJM CSM conference presentation restating known facts: 194 PJ 2P, 1,156 PJ 3P, 390 PJ of gas sale MOUs, 660 PJ goal by mid-2008, trial production program started. Cash $17m, share price $0.83. No new information.
AGM presentation recapping 2007 and setting 2008 goals: continue toward 660 PJ 2P by mid-2008, a conventional test well in PEL 16, seismic in PELs 13 and 426, and power station and CS Energy project sanction. Cash $17m.
AGM chairman's address recapping the year: reserves up almost nine times, the CS Energy farm-in, new acreage and pilot drilling started. Market cap rose from $33m to $106m over the year. No new announcements.
Pilot well Corella-P11 hit the Richmond coal seam at 362m and is nearing its in-seam target. Next is P12, from the same pad, to test the Tomki seam at about 404m. Dewatering starts after both are done.
Bell Potter conference presentation restating known facts: 194 PJ 2P, over 1 Tcf of resource, gas sale MOUs of 390 PJ. It says the environmental assessment and grid connection agreement are now lodged. Share price $0.83, cash $17m.