19 Jan 2016drilling result▼ BadMajor
Te Kiri North-1 reached 4,629 m and is being plugged and abandoned. Mt Messenger had shows but low reservoir quality, and the Eocene target came in lower than predicted. It fulfils Cue's remaining permit obligations. Resolves the 20%-interest exploration thread as a disappointment.
Naga Selatan-2 spudded on 7 January 2016 in the Mahakam Hilir PSC, which Cue holds 100% and operates. It is Cue's first operated exploration well, planned to take 15 days to 2,240 ft. This follows the delay from the earlier November 2015 plan.
Te Kiri North-1 spudded on 16 December 2015 in PEP 51149, onshore Taranaki, with Cue holding 20% and Todd operating. The operator's best-case estimates are 10 mmbbl of oil and ~75 bcf of gas, plus 35 bcf more. About 50 days to reach target depth.
Rig contracted for Naga Selatan-2 in the 100%-owned Mahakam Hilir PSC, with spud planned early January 2016 to 2,240 ft in 15 days. Cue estimates 37.8 mmstb mean prospective oil at 35% chance of success (earlier context cited 25 mmbbl).
Indonesian government approval received for Cue's farm-in to the Mahato PSC from Bukit, giving Cue a 12.5% interest. Two wells are planned for 2H 2015, with Cue's share of costs for the wells and seismic capped. This resolves the pending-approval thread.
Cue farmed into the Mahato PSC, onshore Central Sumatra, taking a 12.5% interest from Bukit, subject to government approval. Two wells are planned for 2015 with Cue's cost share capped; terms are confidential. Adds to the Indonesian onshore push after Mahakam Hilir.
Whio-1 reached 2,824m total depth and is being abandoned. It found sandstones in all objectives but could not confirm commercial hydrocarbons. A disappointing exploration result, though Cue (14%) was free-carried by OMV.
Whio-1 at 2,670m, nearing planned depth of 2,879m. Preliminary indications suggest reservoir-quality sandstones in the targeted formations, to be assessed by wireline logs at total depth. No hydrocarbons reported.
Whio-1 at 1,582m. The upper targets (Whio A, M2A, Upper Moki) are water-bearing, a negative sign; the deeper Mangahewa, Kaimiro and Farewell targets remain to be tested.
Whio-1 spudded 23 July 2014 in PEP 51313, 4.5 km from the Maari platform, planned depth 2,879m. Mean unrisked prospective resource is 18 million barrels (100%). Cue (14%) is free-carried by OMV. Matches the expected ~May spud, slightly later.
Naga Utara-2 sidetrack reached 1,847m and is being plugged and abandoned. Hydrocarbon indications were judged insufficient to justify testing, and hole condition prevented pressure and fluid sampling. Disappointing result for Cue's 40%; future exploration decision pending.
Naga Utara-2 was successfully sidetracked around the stuck pipe and is drilling at 1,676m toward a revised total depth of 2,078m. Next report due 3 January 2014.
Attempts to free the stuck drill string failed and it was cut at 1,482m. The operator is preparing to sidetrack around the obstruction. Second mechanical problem after the Naga Utara-1 difficulties.
Naga Utara-2 drill string became stuck at 1,817m because of the formation; recovery operations are under way. A setback for the Mahakam Hilir well in which Cue holds 40%.
Naga Utara-2 is at 1,559m, drilling ahead in the final 8½ inch section toward a proposed total depth of 2,065m after casing was set at 1,497m. No results yet.
Manaia-2/2A is being plugged and abandoned as planned. Mangahewa results were in line with expectations; Moki oil samples were taken, but fluid analysis is ongoing, so no oil volume is yet confirmed. Last weekly report.
Manaia-2/2A reached total depth of 2891m on 4 November and is being logged. Elevated gas readings and oil fluorescence were seen in the Mangahewa Formation. Significance to be evaluated.
Partner Horizon Oil (10%) says Manaia-2/2A met its drilling objectives, with oil indications in Moki samples and cores. Mangahewa data will help optimise a planned additional development well. Mostly repeats Cue's own reports; analysis continues.
Manaia-2 was sidetracked at 2005m after a cement plug and renamed Manaia-2A. It is drilling toward a deeper planned depth of 2886m. Potential is stated as at least 11 million barrels gross.
Manaia-2 casing was cemented, but debris at the bottom halted drilling at 2008m; the debris has been cleared and drilling ahead toward 2,850m is being prepared. Minor setback.
Manaia-2 logging finished; oil-indicating fluid samples and oil-stained cores were recovered from the Moki Formation, with analysis ongoing. Operator is preparing to run 9 5/8 inch casing. Early encouraging signs, not yet a confirmed result.
Naga Utara-2 spudded 5 October in Mahakam Hilir (Cue 40%), appraising gas shows at Naga Utara-1 that were not fully evaluated due to mechanical problems. Planned depth is 2,068m over about 62 days. It follows the earlier planned Naga Merah-1 follow-up.