28 June 2022drilling progress report▼ Bad
Central reports Palm Valley-12 at 2,278m on 27 June, 220m in the week, with gas shows from 1,778-2,278m. Its CEO says drilling has been difficult, behind schedule and over budget. The JV will consider a horizontal lateral to appraise P3.
NZOG relays Central's update: Palm Valley-12 drilled 220m in a week to 2,278m in the P4 unit. Gas shows through 1,778-2,278m and minor gas flows suggest no significant fractures in the P3. Arumbera target still 3,560m; Cue holds 15%.
NZOG relays Central's update: Palm Valley-12 casing is cemented and drilling resumed, but total lost circulation hit at 2,024m. Underbalanced air drilling then took the well to 2,058m on 20 June. Cue holds 15%.
Central reports Palm Valley-12 at 2,058m on 20 June after casing was cemented, with total lost circulation at 2,024m. It switched to underbalanced air drilling. Same content as the NZOG release.
NZOG relays Central's update: Palm Valley-12 at 2,005m on 13 June, with the week spent cementing casing and running remedial cement plugs. Drilling resumes once the required seal strength is reached. Cue holds 15%.
Central reports Palm Valley-12 at 2,005m on 13 June. Cementing the casing in fractured rock has been problematic, with losses continuing, and several remedial cement plugs have been run. Drilling resumes once the shoe is strong enough.
Central reports Palm Valley-12 at section depth of 1,998m on 6 June, 51m drilled in the week after fluid losses. Casing is being cemented and faster drilling is expected. Same content as the NZOG release.
NZOG relays Central's update: Palm Valley-12 reached section depth of 1,998m on 6 June, only 51m in a week, with the 9 5/8-inch casing being cemented. Central expects faster drilling afterwards. Arumbera target still 3,560m; Cue holds 15%.
NZOG relays that Palm Valley-12 reached only 1,947m by 30 May, just 67m in a week, as fractures in the P1 unit cause fluid losses needing repeated cement jobs. Drilling is slower than anticipated; Cue holds 15%.
Central reports Palm Valley-12 at 1,947m on 30 May, only 67m drilled in a week as fractures in the P1 unit cause fluid losses and repeated cement jobs. Same content as the NZOG release; Cue holds 15%.
Central reports Palm Valley-12 at 1,880m in the Pacoota P1 unit, apparently intersecting the fracture system, which it calls encouraging. Fluid losses slowed progress to 193m in a week. Same content as the NZOG release.
NZOG relays Central's update: Palm Valley-12 at 1,880m, in the main productive Pacoota P1 zone, where natural fractures were hit, which the operator calls encouraging. Fluid losses slowed drilling to 193m in a week. Cue holds 15%.
Central reports Palm Valley-12 at 1,687m on 16 May, with 584m drilled in line with expectations. The 12¼-inch section is due to finish around 2,005m on 18 May. Same content as the NZOG release.
NZOG relays Central's update: Palm Valley-12 at 1,687m on 16 May, 584m drilled in the week. The 12¼-inch section is due to finish around 2,005m on 18 May. Cue holds 15%.
Palm Valley-12 reached 1,103m on 5 May, the planned end of the 17.5-inch section. The 13 3/8-inch casing is cemented and drilling of the next hole section resumes 10 May. No new result.
Central reports Palm Valley-12 at 820m on 2 May, with 599m drilled in the week. The 17.5-inch section is planned to end at 1,100m, then casing is run. No new result.
Central reports Palm Valley-12 at 221m on 25 April, drilling ahead after cementing the 20-inch conductor. Arumbera target is 3,560m, total depth 3,980m in early June. Same content as the NZOG release.
NZOG relays Central's update: Palm Valley-12 was at 221m on 25 April, drilling ahead after setting the conductor. Arumbera target is at 3,560m; total depth 3,980m expected early June. Cue holds 15%.
NZOG announces Palm Valley-12 began drilling on 17 April 2022, targeting the Arumbera Sandstone about 1,300m below known gas, to about 4,144mMD in roughly 61 days. If unsuccessful it will be sidetracked into the Pacoota. Cue holds 15%. Spud follows the one-month rig delay.
Cue confirms Palm Valley-12 began drilling on 17 April 2022, targeting the deeper Arumbera Sandstone, with a Pacoota sidetrack if that fails. Expected to take about 61 days. Cue holds 15%. Repeats the NZOG release.
Central confirms Palm Valley-12 spud on 17 April 2022, first of two wells with Dingo-5. Targets 123 PJ mean prospective gas (gross, unrisked); Arumbera expected in early June. Central says the wells are free-carried by NZOG and Cue.
NZOG relays Cue's Mahato reserves upgrade and shows its combined position: 1P reserves 13.0 mmboe at 1 Jan 2022, versus 12.9 mmboe at 1 Jul 2021. Its CEO says financing options will be finalised shortly.
Cue raised Mahato PB field reserves: net 2P rose 322% to 1.4 mmbbl and net 1P rose to 1.1 mmbbl, with gross 2P at 20.9 mmbbl. Cue holds 12.5% and plans regular reserve reviews as drilling continues.
Mahato PB-09, the ninth PB field producer, is online at about 500 bopd from the Bekasap C sand. Field output is about 5,500 bopd. It is the first of five wells in the next program; PB-10 is next. Cue holds 12.5%.
NZOG relays that Central has updated its Mereenie, Palm Valley and Dingo reserves. NZOG is reviewing and has not adopted the new volumes; its reserves stay unchanged until a formal assessment. No Cue figures are given in the text provided.
Cue notes Central's updated Amadeus Basin reserves (Mereenie, Palm Valley, Dingo). Cue is reviewing them and will fold any impact into regular reporting, including coiled tubing and upcoming drilling results. No new figures given.
Central says the Ensign 963 rig has left its Canning Basin job and is mobilising to Palm Valley. The Palm Valley Deep well spud remains on schedule for late March 2022, as reset in January.
NZOG relays Cue's news that Mahato PB-08 is online at about 600 bopd, completing phase 1, with PB field output about 5,600 bopd. Repeats the Cue release; no new information.