3 Apr 2006other▲ Good
Beach's company update restates the 40% Tipton West reserve rise (2P 174 PJ) and the Harpoono-2 oil discovery. It also confirms a drilling schedule of more than 30 wells in 2006, and says Braemar power station gas sales from March 2007.
Beach sets a 5% discount for the dividend reinvestment plan on the 2006 interim dividend, giving a share issue price of $1.16192. Administrative detail on the 0.5c dividend already declared.
Anzon reports Basker-5 reached 3640 m with better-than-expected logs: 57.4 m of hydrocarbon pay (18.3 m oil, 33.5 m gas), and the structure top over 20 m higher than expected. Wells are due to be perforated in early May; a reserves review follows drilling.
Beach confirms Christies-5 spudded 30 March, drilling at 369 m toward a planned 1840 m. It appraises the north-west extent of the 2003 Birkhead/Hutton oil pool and is the second Christies well; Beach 75%.
Anzon (operator, Beach 50%) delivered a second Basker-Manta cargo of about 400,000 barrels, worth about $35m, to a Victorian refiner. Basker-2 averages about 7,000 bopd; full five-well development is expected to average 25,000 bopd.
Beach's weekly report: Christies-4 cased and suspended, with Christies-5 due to spud around 31 March. Basker-5 reached 3640 m; Harpoono-2 at 354 m; Tipton West wells progress (3 of 85 completed). No new significant results.
Beach reports Christies-4 will be cased and suspended after finding oil pay. A repeat test (DST 2) flowed 653 bopd of oil plus 1150 barrels of water a day. It extends the 2003 Birkhead/Hutton discovery south-east; Christies-5 is the second well in the program.
Partner Cooper Energy reports Christies-4 reached 1859 m, with oil on logs and an open-hole test flowing 650 bopd with 1150 barrels of water a day. The well will be cased and suspended for completion and tie-back. Cooper's final release on this well.
Stuart Petroleum spudded Harpoono 2 on 27 March, with Harpoono 3 to follow. Beach holds 33.33% and Stuart is operator. The wells target Murta oil (pre-drill P50 oil in place 0.69 million barrels) and a possible McKinlay oil pool; success could add two more exploration wells.
Media release on the VIC/P46 farm-in (17.5% to 50%, Beach operator; Mitsui subsidiary Mittwell holds 25%). Management says the Fermat prospect could hold over one trillion cubic feet of gas, which is a pre-drill estimate. Next Basker cargo is over 410,000 bbl.
Beach agrees to farm in to acquire a further 32.5% of Otway Basin permit VIC/P46, lifting its stake from 17.5% to 50% and taking over as operator. 3D seismic is planned later in 2006, with one well in 2007; subject to documentation and assignment.
Essential Petroleum (the permit's current operator) says it accepted Beach's offer to lift Beach's stake in offshore Otway Basin permit VIC/P46 from 17.5% to 50%. Beach becomes operator; Essential keeps 25% and is substantially carried through a 3D seismic and drilling program costing over $20m.
Beach starts weekly drilling reports. Christies-4 at 911 m; Basker-5 at 3191 m with Basker-3 and 4 cased at the surface; Tipton West wells being drilled. No new results.
Cooper Energy reports Christies-4 at 911 m, with 9 5/8-inch casing set. Drilling continues toward 1684 m, with a possible open-hole production test. Routine progress.
Beach confirms Christies-4 spud on 17 March, targeting the Birkhead/Hutton oil pool south-east extension to 1684 m. Beach is switching to weekly drilling reports on Tuesdays.
Beach lodges the prospectus for the free bonus options: 1 per 10 shares held at 31 March, up to about 53 million, exercisable at A$1.00 until 30 September 2006. Full exercise would raise roughly A$53m (inference).
Christies-4 spudded at midnight on 17 March and has drilled to 47 m. Beach holds 75% and Cooper Energy 25%. Routine appraisal well in the existing Christies oil field.
Cooper Energy says Christies-4, an oil appraisal well in the Christies field, should spud 17 March using Century 3. Planned depth is 1684 m, taking 8-10 days.
Strike Oil, a partner, says Beach's ATP633P permit entitles it to a 15% interest. It plans 3D seismic in Q2 and a follow-up well on the Gidgee oil discovery around year-end. Repeats the known permit award.
Beach's final Middleton-1 report: rig being released and moving about 30 km west to Christies-4, expected to spud around 17 March. Beach holds 75% of Christies, Cooper Energy 25%.
Arrow Energy's operations update says Tipton West development drilling has begun, with 75 wells planned in the initial program and first gas scheduled for Q1 2007. It restates Beach's farm-in for 40% by funding the first A$35m.
Great Artesian's final Middleton-1 report: casing is being run before rig release. Gas zones, including the 11.8 mmcf/d interval, may get cased-hole testing within 2-3 months depending on equipment.
Beach clarifies bonus options (1 per 10 shares at 31 March) will be entered on 18 April but not listed until 1 May 2006, after the prospectus is mailed around 26 April. Timing clarification only.
Great Artesian repeats the final Middleton-1 test: 11.8 mmcf/d, minor condensate, no water. The well will be cased and suspended pending completion equipment.