24 Jan 2006drilling progress report● Neutral
Great Artesian reports Udacha-1 at 2197 m after a bit change, in the Nappamerri Formation. Routine progress.
Past year: ▼ 33%(83.5c – 1.29 AUD)
Each one in plain English, with the numbers worked through for a shareholder.
24 Jan 2006drilling progress report● Neutral
Great Artesian reports Udacha-1 at 2197 m after a bit change, in the Nappamerri Formation. Routine progress.
23 Jan 2006drilling progress report▼ Bad
Manta-2 casing parted at about 163 m after reaching 971 m, so the well was plugged and a new path started, adding about 5 days. This delays the 35-day Manta-2 program that began 17 January (Beach 50%). Basker production resumed at about 8,000 bpd.
23 Jan 2006drilling progress report● Neutral
Great Artesian reports Udacha-1 at 2188 m in the Nappamerri Formation, repeating Beach's update. It restates the prospect's up to 2.3 MMbbl oil or 10.5 BCF gas (P10) potential. Routine progress.
23 Jan 2006drilling progress report● Neutral
Udacha-1 at 2188 m, drilling ahead in the Nappamerri Formation, heading toward the Patchawarra target. Routine progress.
20 Jan 2006drilling progress report● Neutral
Udacha-1 at 1862 m, drilling ahead in the Adori Sandstone, repeating the earlier 20 January update. Routine progress.
20 Jan 2006drilling progress report● Neutral
Udacha-1 at 1862 m, drilling ahead in the Adori Sandstone. The main Patchawarra target is expected near 2326 m. Routine progress.
19 Jan 2006drilling progress report● Neutral
Beach reports Udacha-1 at 1428 m in the Oodnadatta Formation. Routine progress.
19 Jan 2006drilling progress report● Neutral
Enterprise Energy reports Udacha-1 at 1428 m; a trip replaced a washed-out drill pipe. Routine progress.
19 Jan 2006drilling progress report● Neutral
Rawson's weekly report: Udacha-1 at 1428 m. Rawson would earn 10% of any production licence. Routine progress.
19 Jan 2006drilling progress report● Neutral
Udacha-1 at 1428 m after pulling out of the hole for a washout. Routine progress.
19 Jan 2006drilling progress report● Neutral
Magellan's weekly report: Udacha-1 at 1428 m, with 960 m drilled in the week and surface casing set at 732 m. Routine progress.
18 Jan 2006drilling spud● Neutral
Beach confirms Manta-2 spudded 17 January 2006, the second of five wells to develop Basker-Manta (Beach 50%). It is expected to take about 35 days; Basker-3, 4 and 5 follow with the same rig.
18 Jan 2006drilling progress report● Neutral
Udacha-1 at 1323 m in the Oodnadatta Formation after a bit change. Routine progress.
18 Jan 2006drilling progress report● Neutral
Beach reports Udacha-1 at 1319 m in the Oodnadatta Formation. Routine progress.
18 Jan 2006drilling spud▲ GoodMajor
Anzon says Manta-2 development well spudded 17 January, starting full field development of Basker-Manta (Beach 50%). Once all wells are done, peak output could reach 35,000 bopd. Manta-2 is due to complete mid-February.
17 Jan 2006drilling progress report● Neutral
Udacha-1 at 1160 m, drilling ahead in the Allaru Mudstone. Routine progress.
17 Jan 2006drilling progress report● Neutral
Enterprise Energy reports Udacha-1 at 1160 m, drilling on towards the first objective. Routine progress.
17 Jan 2006drilling progress report● Neutral
Beach reports Udacha-1 at 1160 m in the Allaru Mudstone. Routine progress.
16 Jan 2006drilling progress report● Neutral
Beach reports Udacha-1 at 901 m, drilling ahead in the Mackunda Formation. Routine progress.
16 Jan 2006drilling progress report● Neutral
Udacha-1 at 901 m, drilling ahead after setting surface casing. Routine progress.
16 Jan 2006drilling progress report● Neutral
Partner Enterprise Energy reports Udacha-1 at 901 m in the Mackunda Formation, surface casing run and tested. Routine progress.
13 Jan 2006drilling progress report● Neutral
Beach reports Udacha-1 at 736 m, preparing to run surface casing. Routine progress.
13 Jan 2006drilling progress report● Neutral
Udacha-1 at 736 m, preparing to run and cement surface casing. Routine progress.
12 Jan 2006drilling progress report● Neutral
Great Artesian's copy of the Udacha-1 report: 468 m, drilling ahead, with surface casing planned near 750 m. Nothing new beyond the operator's update.
12 Jan 2006production update▲ GoodMajor
Partner Anzon reports first oil cargo (300,000 barrels) shipped from Basker-Manta, in which Beach holds 50%. Basker-2 has averaged 8,000 barrels a day, with four more wells due onstream in the third quarter. Reserves are 30.1 million barrels proved and probable.
12 Jan 2006production update▲ GoodMajor
Beach announces its first offshore oil sale: over 121,000 barrels worth about A$10 million from Basker-Manta, where it now holds 50% (up from 25%). This more than doubles daily production from about 2,800 bopd onshore. Four more wells are planned.
12 Jan 2006drilling progress report● Neutral
Udacha-1 was at 468 m, drilling ahead in the Winton Formation. No new result.
12 Jan 2006drilling progress report● Neutral
Magellan's weekly report: Udacha-1 at 468 m. It also reports Currambar-1, a non-Beach well, cased and suspended. Nothing new for Beach.
11 Jan 2006drilling spud● Neutral
Partner Rawson Resources reports Udacha-1 spudded at 11.30am on 11 January 2006. Rawson would earn 10% of any production licence. Beach is operator with 15%. Duplicate of known news from a partner's perspective.
11 Jan 2006drilling spud● Neutral
Beach-operated Udacha-1 is due to start drilling on 11 January, targeting 2775 m in about 19 days. Beach holds 15% of any production licence. Great Artesian also reported Kiana-1, another oil discovery, produced 6,955 barrels by end-December.