Each one in plain English, with the numbers worked through for a shareholder.
4 Aug 2010drilling progress report▲ Good
Henderson 4-25H was fracture stimulated and flowed about 1,000 bbl/d of oil and fluids on test. Watson West-1 (Beach 38%) is suspended as an oil producer; Encounter-1 shale gas well, delayed earlier, is due to start late August; heavy rain halted Canunda and Coonatie work.
Beach agreed to fund A$2.7m of Petratherm's Paralana costs early and no longer has to pay the first A$5m of Paralana 3, though it pays 21% of costs. Fracture stimulation of Paralana-2, planned earlier, is now set for August 2010.
June quarter: production 1.6 MMboe (down 7%), revenue A$125.8m (up 23%), cash A$169.9m. FY10 production was 7.35 MMboe, close to the 7.4 guidance; the A$43m Arrow receivable is now due after shareholder approval of the Shell/PetroChina offer.
21 July 2010asset acquisition disposition▲ GoodMajor
Beach agreed with Sundance to buy about a 15% net revenue interest in Bakken Sections 26 and 35, adding to its Section 25 stake. The Henderson 4-26/35H well starts early August, targeting about 600,000 barrels gross; it builds shale experience for the Cooper Basin.
Petratherm, Beach's Paralana geothermal partner, signed the A$62.762m Commonwealth REDP funding deed, resolving the earlier open funding question. Money for a 30 MW demonstration depends on proving the concept, planned for 2011.
Drillsearch says the PEL 91 joint venture (Beach operator 40%, Drillsearch 60%) plans up to five Western Flank oil wells, targeting 3.5 million barrels mean unrisked recoverable. Drilling needs a rig and should start by Dec 2010/Jan 2011; Chiton returns to production in early August.
Watson West-1 (Naccowlah Block, Beach 38.5% per Drillsearch) found 6-8 feet of oil pay and will be completed as a Basal Birkhead oil producer. Initial oil in place is estimated at 300,000-400,000 barrels, a small near-field discovery.
First monthly drilling report: Canunda-1 (Beach 50%) flowed 10.5 MMscf/d with high condensate, now choked back by trucking limits. Inca-1 (30%) is suspended as a future oil producer, and Henderson 4-25H reached 4,865 m TD, with fracture stimulation due end July.
Drillsearch (Beach's 50% partner) reports Canunda-1 produced over 2,500 barrels of condensate in 10 days. It is choked back to about 1 MMscf/d and 180 bbl/d of liquids by storage and trucking limits; no reserve estimate is given yet.
Beach manager Gordon Moseby gave a general presentation on world energy demand and the case for gas in Australia. It is background education with no new company results, figures or decisions.
Beach signed a non-binding MOU with Japan's ITOCHU to explore supplying gas from its onshore Australian portfolio to a possible integrated LNG project. It is an investigation only, with no commitment or financial terms stated.
Beach guides FY10 underlying profit of $30-40m and will write off about $64m of Bass Basin exploration. A further $43m from Arrow is booked if the Shell/PetroChina offer completes. BMG owners are weighing options beyond a replacement FPSO.
Chairman's letter to shareholders restating the $140m cash, no debt and the $64m Bass Basin write-off. It also says the proposed Resources Super Profit Tax adds uncertainty in Australia, and that Beach holds a majority of Somerton. Mostly repeats known points.
Beach signed the Production Sharing Agreement for 100% of the Lake Tanganyika South concession in Tanzania, completing the earlier exclusive negotiation right. The 11-year term has a well commitment in each of the second and third phases, with the option to relinquish at the end of each phase.
Media release repeating the Tanzania PSA signing for 100% of Lake Tanganyika South, pitched at Uganda-style rift oil plays. It restates the 4+4+3 year phases and a well in each of phases two and three. No new substance.
The two-well PEL 218 shale gas program is delayed to mid-late August, starting with Encounter-1, because rig parts were held up by weather in Thailand. Holdfast-1 now follows. Beach will also move to monthly routine drilling reports.
Weekly report: Genoa North-2 is cased and suspended as a future oil producer and the rig moves to the Inca-1 exploration well. Henderson 4-25H is at 3,166 m, starting its horizontal section.
Weekly report: Genoa North-2 (Beach 30%) spudded 3 June and is drilling at 1,811 m. Henderson 4-25H in North Dakota's Bakken play (Beach 23.15%, with Sundance) is at 1,932 m.
ROC says BMG (Beach 30%) was shut in from 4 May after repairs to the FPSO mooring turret and buoy, and restarted on 6 June. Repairs finished without incident.
UBS conference presentation by the Managing Director repeating known points: 66 MMboe 2P, $140m cash and no debt, FY10 guidance 7.4 MMboe, shale gas wells, Egypt first oil and Tanzania PSA timing. No new substance.
Santos-operated Genoa-3 (Beach 30%) spudded on 18 May, the first Cooper Basin drilling since the floods. Beach expects all three Santos rigs back at work before the end of June.
Petratherm reports a four-day community consultation on the Paralana geothermal project, well received by stakeholders. It is a step toward the fracture stimulation Beach (earning 21% per our records; release says up to 36%) is waiting on. No new results.
Macquarie conference presentation on Cooper Basin shale gas. It repeats known points but gives FY10 production guidance as now 7.4 MMboe (down from 8.0, citing flooding) and cash of $140m at 31 March 2010, with no debt.
From 1 July 2010 Neil Gibbins becomes Chief Operating Officer and Steve Masters Chief Commercial Officer. Hector Gordon stays an Executive Director while acting as Managing Director of Somerton Energy.
5 May 2010asset acquisition disposition● NeutralMajor
Essential Petroleum Resources relaunches as Somerton Energy (ASX: SNE). Beach now holds 51.9% and is providing financial assistance. Hector Gordon becomes its Managing Director and Bob Kennedy chairman, completing the restructure Beach had proposed.
Drillsearch reports the extended production test at the Brownlow wet gas discovery (PEL 106 Beach Farmin Block, Beach 50% operator) has begun: 10 MMscf/d sampled with 120 bbl/d condensate, then 18 MMscf/d on a 1-inch choke. A Canunda test follows.
Beach signed an MOU with US firm General Atomics to study algae-based bio oil and fuel production in the Cooper Basin. Commercial plants of 1,000-2,000 hectares are targeted by June 2015 if studies succeed. It is only an evaluation, with no financial commitment stated.
Beach's weekly report said Cooper/Eromanga drilling remained suspended after the heavy rainfall and was not expected to resume until mid-April to mid-May. The Coonatie-16 gas development well (Beach 17.14%) stayed suspended at 1,132 m, with no restart before 1 May.