11 Sept 2012drilling progress report● Neutral
Icon says Halifax-1 (ATP 855P, Beach 60%) has reached 3,326m of a planned 4,130m and entered the Roseneath Formation. The first core is to be taken in the Epsilon. No new result.
Past year: ▼ 33%(83.5c – 1.29 AUD)
Each one in plain English, with the numbers worked through for a shareholder.
11 Sept 2012drilling progress report● Neutral
Icon says Halifax-1 (ATP 855P, Beach 60%) has reached 3,326m of a planned 4,130m and entered the Roseneath Formation. The first core is to be taken in the Epsilon. No new result.
10 Sept 2012farm in farm out agreement▲ GoodMajor
Beach signed a farm-in on 4 September for 30% of the Est Cobalcescu block, offshore Romania (Black Sea), with Melrose and Petromar. Cost is about US$8.4m in 2012 and an estimated US$24.8m over three years. Subject to Romanian approval; Beach's first Europe entry.
10 Sept 2012drilling result▲ Good
Cooper Energy reports Butlers-5 (PEL 92, Beach 75% operator) found an 8m gross oil column in the Namur Sandstone, higher than expected. It will be cased as a producer; Butlers-6 follows, then Tinah-1.
5 Sept 2012drilling spud▲ Good
Cooper Energy (25% partner) says a three-well campaign in PEL 92 (Beach 75% operator) has started, with Butlers-5 spudded 5 September to a planned 1,356m. Butlers-6 and an exploration well follow; the field is producing about 2,500 bopd.
5 Sept 2012resource reserve update▲ Good
Drillsearch repeats Beach's preliminary estimate of over 10 million barrels recoverable at Bauer (PEL 91, Beach 40%), against the 6.7 million barrels 2P audited by GCA in July. A fresh audit including Bauer-6, -7 and -8 is due by October 2012.
5 Sept 2012joint venture update● Neutral
Petratherm, operator of the Paralana geothermal JV (Beach 21%), has been invited to apply for about A$13m of ARENA grant money towards a nominal A$26m, two-year next stage including drilling Paralana 3. Application is due late September 2012; Petratherm is still seeking its own share of funding.
5 Sept 2012drilling progress report▲ GoodMajor
Beach's August drilling report repeats known results (Bauer-6/-7/-8, Tomcat-1 dry, Halifax-1 shale gas test) but adds a preliminary Bauer field estimate of over 10 million barrels recoverable (over 4 million net to Beach). Hoss-1 (WA-208P, Beach 10%) offshore was dry.
4 Sept 2012drilling progress report● Neutral
Icon says Beach-operated Halifax-1 (ATP 855P, Beach 60%) reached 2,878m and a drill stem test of an unexpected shallow Nappamerri sand flowed dry gas at about 0.2 MMscf/d, with no stable rate. The main REM target is still to be drilled to 4,130m.
30 Aug 2012drilling result▲ GoodMajor
Drillsearch reports Bauer-8 (PEL 91, Beach 40% operator) found 10m net Namur oil pay and will be cased as a producer, extending the Bauer field north. Two more appraisal wells are proposed by end 2012, and Drillsearch expects a further reserves increase.
30 Aug 2012investor presentation● Neutral
September investor presentation repeating FY12 results and FY13 guidance. Shows 2P reserves of 93 MMboe and 2C contingent resources of 466 MMboe, using a new unconventional booking method. Nil debt apart from the A$150m converts.
29 Aug 2012drilling result▼ BadMajor
Senex reports Tomcat-1 (PEL 111, Beach 40%) found a sand channel but no hydrocarbons and was plugged and abandoned. Mustang-1 (almost 2,500 bopd in testing) is being completed for production, and Snatcher-7 is now drilling.
28 Aug 2012other▲ Good
Media release summarising the FY12 results: record revenue A$619m and underlying profit A$122m. Management expects Western Flank oil to reach about 10,000 barrels a day by end of FY13. Repeats figures from the full-year report.
28 Aug 2012production update▲ GoodMajor
FY13 guidance: production of 8.5 to 9.0 MMboe (versus 7.5 in FY12) and capital spending of A$350-450m, including A$120-150m on unconventional exploration. Beach expects to fund this in full from cash flow, A$379m cash and its A$150m facility.
28 Aug 2012investor presentation▲ Good
FY12 results presentation repeating known figures: revenue A$619m, profit A$164m, production 7.5 MMboe. Shows 2P reserves of 93 MMboe, up 20% (earlier estimate was about 95). Largely a re-statement of the results release.
28 Aug 2012annual report▲ GoodMajor
FY12 full-year report: revenue A$619m, profit after tax A$164m (versus a A$97.5m loss in FY11), record underlying profit A$122m. Final dividend 1.5c, making 2.25c for the year. Cash A$379m; production 7.5 MMboe.
28 Aug 2012regulatory community update▼ Bad
Lakes Oil's chairman says Victoria has put a moratorium on fracture stimulation, which would hit Beach's planned fracs on Wombat-4 and Boundary Creek 2 in the PRL2 Gippsland earn-in before Christmas. Beach has begun seeking approvals; the impact on Beach is not quantified.
23 Aug 2012drilling progress report● Neutral
Partner Icon says Halifax-1 (ATP 855P, Beach 60%) has drilled to 2,611m and is running intermediate casing. It repeats the 300 Tcf gas-in-place hope for PEL 218 and the funding terms (Beach funds first A$16m). No new result.
23 Aug 2012drilling spud● Neutral
Drillsearch reports Bauer-8 (PEL 91, Beach 40% operator) spudded 22 August, 530m north-north-east of Bauer-5. It is the fourth and final well in the current Bauer program and will also test the Birkhead oil found at Bauer-5.
20 Aug 2012material agreement● Neutral
Advent Energy (unlisted, via MEC Resources) signed a land access and data sharing agreement with Beach over a Beach airborne gravity and magnetic survey planned for later in 2012 in the onshore Bonaparte Basin. It builds on Beach's Territory Oil and Gas farm-in.
20 Aug 2012drilling result▲ Good
Drillsearch reports Bauer-6 (PEL 91, Beach 40% operator) logged 9m net Namur pay and potentially 4m McKinlay pay, with only minor Birkhead oil shows. It will be cased as a producer and shows the field extends further west. Rig moves to Bauer-8.
17 Aug 2012flow test result▲ GoodMajor
Santos, operator of the Cooper Basin JV (Beach 20.21%), says the Moomba-191 vertical shale well stabilised at 2.6 MMscfd, peaking at 3.0. Beach says this supports its unconventional program, including a planned first horizontal well later in 2012.
14 Aug 2012drilling result▲ Good
Senex cased Snatcher-6 (PEL 111, Beach 40%) after a 10.5m gross Birkhead oil column with 5.2m net pay. It is the first well of the continuing Snatcher appraisal program. The rig now moves to Tomcat-1.
14 Aug 2012drilling progress report● Neutral
Partner Icon says Halifax-1 (ATP 855P, Beach 60%) is drilling at 1,605m after casing set at 847m. Restates the 300 Tcf gas-in-place hope for PEL 218 and the funding terms. No new result.
10 Aug 2012drilling spud▲ Good
Drillsearch reports Bauer-6 (PEL 91, Beach 40% operator) spudded 9 August and will also test the Birkhead. The joint venture added a fourth development well, Bauer-8, 500m north-east of Bauer-5, after the Bauer-5 success.
9 Aug 2012flow test result▲ Good
Drillsearch reports extended production testing began at Coolawang-1, a wet gas discovery in PEL 106B (Beach 50% operator), for up to 20 days. Early clean-up flows of gas and condensate are called encouraging. No rates given.
6 Aug 2012drilling result▲ Good
Drillsearch reports Bauer-7 (PEL 91, Beach 40% operator) logged 9.5m net Namur pay and 4m McKinlay pay, and will be cased as a producer. It supports the field's eastern extension. Rig moves to Bauer-6.
6 Aug 2012drilling spud● NeutralMajor
Partner Icon reports Halifax-1 (ATP 855P, Beach 60% on funding the first A$16m) spudded 4 August to 4,130m, with total depth in about 55 days. This is the first vertical well in Beach's second Nappamerri Trough gas permit.
3 Aug 2012production update▲ Good
Extended production tests began on four Abu Sennan wells in Egypt (Beach 22%), with combined flow up to 2,524 bopd. Tests run six months to estimate volumes in place. ASA-1X, the first of three more approved wells, spudded 1 August.
2 Aug 2012drilling progress report● Neutral
Drillsearch says Bauer-7 (PEL 91, Beach 40% operator) found no reservoir sands or shows in the Birkhead, so the Bauer-5 Birkhead find was not repeated there. It is still expected to be cased as a McKinlay and Namur producer.
1 Aug 2012admin correction● Neutral
Amended July drilling report, changing only the Halifax-1 line from already spudded on 1 August to expected to spud on 2 August. Otherwise identical to the original.